Concepts And Procedures Of Project Management

0 Download10 Pages / 2,290 Words

Question:
Discuss about the Concepts and Procedures of Project Management.
 
 
Answer:

Introduction
The project’s main objective is to illustrate the incorporation of concepts and procedures of project management for the concerned project with the up-gradation of the present security foundation unit of XYZ Group Ltd. The organization performs offshore marine operation and is also present in gas and oil sectors. The whole project will be administrated by the Principles of Project Management Body of Knowledge or PMBOK. One of the frequently utilized and trusted methodology of project management, PMBOK is easy to utilize and has tested and proven procedures. It consists of the best practices in regards to project management that can be applied to all types of projects. The IT foundation of the security unit, in this regard, would go through various stages of project management, and this includes planning and designing, and after that execution, and in the end, evaluation.
Project scope
Objective
To update XYZ Group Ltd.’s security unit’s IT infrastructure and to make it operational within the provided time period with pre-approved conditions and requested benefits, within a SGD 28,580 budget.
Following are key deliverables of the revamp security unit of XYZ  Group of the company:

To provide secure unit to the company.
To enhance daily operations of the company.
To enhance integrity and security of company’s information.

Deliverables
Following are key deliverables of the project:

The revamp process will include examining the current system and installation of new software on the system.
The installation process shall include backing up existing data.
The status and progress reports are required to be prepared and discussions should be held in team meetings.
All workstations will be provided with Windows Server 2012 and latest updated anti-virus software.

Milestones
Following are key milestones of revamp projectare as follows:

Finalize upgrade project plan – 1st October 2016
Take backup of existing data – 4th October 2016
Selection of hardware – 8th October 2016
Selection of vendor – 15th October 2016
Hardware installation – 20th October 2016
Testing of revamped network – 24th October 2016

Technical requirements
Following are key technical requirements of revamp project:

The plan for data backup should be prepared before revamping the unit.
All data should be stored at centralized server and must be accessed by authentic users only.

 
Limits and exclusions
Following are key limits and exclusions of revamp project:

All project hardware and software should be delivered as per the assigned deadline.
The client should approve the resources to be used in the project.
All deliverables should be made within the assigned budget of the project.
All deliverables should be made within the assigned deadline of the project.
The cost may increase if the project gets delayed but deadline cannot be extended.

Customer review
XYZ group of companies
Project Priorities
There exists a robust correlation between project management and performance, time, and the project’s cost factor. For recognizing the criteria which are to be limited or enhanced, a project matrix needs to be incorporated.

Constraint – The constraint specifies the criteria that are to be finished within the specified descriptions, scope, and time.
Enhance – These are the criteria which are cleared for the project, however, time and cost would enhance project value.
Accept – These criteria dictate that even though there is a slight amount of trade-off, it will still be approved to the project duration so that scope variation and budget overflow can be reduced.

Project Priority Matrix
During the whole refurbishment project of XYZ Group Ltd.’s security unit, one of the critical factors is time. This is due to the fact that in case the project duration goes beyond the approved deadline, then, the organization might lose out on budget and resources. Thus, the project manager needs to comply with the project deadline. It will be achieved by permitting some contingencies within the project. But, that is not desirable. The process of installation and upgradation’s backup plans can be modified, in accordance with the requirements of the project.

 

            Time

Performance

Cost

Justification

Constrain

 

X

 

Performance is the key constraint of the project as the network is revamped to increase the efficiency

Enhance

X

 

 

The time can expand as and when company comes up with new modificaitons.

Accept

 

 

X

It allows extra budget if it is possible to extend the deadline and improve the quality of the revamped unit.

Work Breakdown Structure

Level-3 packages of the WBS are as follows:

Requirement analysis – Study the current structure and design of the secure unit.
Conduct feasibility study – Finalize whether project is feasible to be done.
Finalize project plan – Create the project plan with required resources and deadline.
Prepare deliverables – Finalize deliverables of the project.
Finalize communication plan – Finalize communication plan for project resources.
Prepare testing plan – finalize testing plan to test the new network.
Finalize change management plan – Finalize change management plan to combat with new change requests in the project.
Finalize risk management plan – Finalize risk management plan to mitigate occurring risk in the project.
Sign-off of plan – Get the project approved by the client.
Conduct market research – Perform market research for new design of the network.
Prepare configuration plan – Finalize plan for configuring and installing new systems.
Prepare bill of the material – create bill of all the hardware and systems purchased.
Open tender – Open request for tenders from hardware vendors.
Create the criteria for vendor selection – Finalize selection criteria for vendors.
Finalize vendors for hardware – Select hardware vendor.
Perform quality check on selected hardware – conduct quality conduct for the new hardware installed and configured.
Store parts in warehouse – Store required hardware parts in warehouse of the company.
Test each machine–Conduct testing of each machine in the new network.
Sign-off of testing – Get approval on testing of all machines.
Place machine on the network – Conduct testing of entire new and revamped network.
Sign off of network testing – Get approval on network testing.

Cost Estimation
Top down estimation
Consensus was used of the project’s team members. Their consensus was based on their previous experience of other projects.

WBS

Task Name

 

1

IT Infrastructure up gradation

 

1.1

   Planning

 

1.1.1

      Requirement analysis

500

1.1.2

      Perform feasibility study

400

1.1.3

      Prepare detailed plan

300

1.1.4

      Finalize deliverables

200

1.1.5

      Prepare communication plan

200

1.1.6

      Prepare testing plan

200

1.1.7

      Prepare change management plan

200

1.1.8

      Prepare risk management plan

200

1.1.9

      Get signoffs on the plans and deliverables

80

1.2

   Analyze & Design

 

1.2.1

         Conduct compatibility study

400

1.2.2

Conduct market research

500

1.2.3

         Prepare detailed configuration plan for computers

400

1.2.4

         Prepare bill of the material

300

1.2.5

         Sign-off on the material bill

100

1.3

      Vendor selection

 

1.3.1

         Raise tender for hardware

800

1.3.2

         Prepare the criteria for vendor selection

300

1.3.3

         Identify vendors for hardware

300

1.3.4

      Backup existing data

400

1.4

      Raise invoice for hardware purchase

 

1.4.1

         Perform quality check on selected hardware

500

1.4.2

         Store parts in the warehouse

100

1.5

      Install

 

1.5.1

Upgrade hardware on critical machine

600

1.5.2

Install software on these machines

800

1.5.3

Give demo

100

1.5.4

Perform quality check on selected hardware

500

1.6.

      Machine test

 

1.6.1

         Test each machine

10000

1.6.2

         Sign-offs

100

1.7

      Network testing

 

1.7.1

         Place machine on the network

10000

1.7.2

         Sign-offs

100

 

Total cost

28580

(Duncan, 1996)
Bottom up estimation

WBS

Task Name

Unit Cost ($)

Quantity

Total Cost ($)

1

Revamp secure unit

 

 

 

1.1

   Planning

 

 

 

1.1.1

      Requirement analysis

500

1

500

1.1.2

      Perform feasibility study

400

1

400

1.1.3

      Prepare detailed plan

300

1

300

1.1.4

      Finalize deliverables

200

1

200

1.1.5

      Prepare communication plan

200

1

200

1.1.6

      Prepare testing plan

200

1

200

1.1.7

      Prepare change management plan

200

1

200

1.1.8

      Prepare risk management plan

200

1

200

1.1.9

      Get signoffs on the plans and deliverables

80

1

80

1.2

   Analyze & Design

 

 

 

1.2.1

         Conduct compatibility study

400

1

400

1.2.2

Conduct market research

500

1

500

1.2.3

         Prepare detailed configuration plan for computers

400

1

400

1.2.4

         Prepare bill of the material

300

1

300

1.2.5

         Sign-off on the material bill

100

1

100

1.3

      Vendor selection

 

1

 

1.3.1

         Raise tender for hardware

800

1

800

1.3.2

         Prepare the criteria for vendor selection

300

1

300

1.3.3

         Identify vendors for hardware

300

1

300

1.3.4

      Backup existing data

400

1

400

1.4

      Raise invoice for hardware purchase

 

 

 

1.4.1

         Perform quality check on selected hardware

500

1

500

1.4.2

         Store parts in the warehouse

100

1

100

1.5

      Install

 

 

 

1.5.1

Upgraed hardware on critical machine

600

1

600

1.5.2

Install software on these machines

800

1

800

1.5.3

Give demo

100

1

100

1.5.4

Perform quality check on selected hardware

500

1

500

1.6.

      Machine test

 

 

 

1.6.1

         Test each machine

1000

10

10000

1.6.2

         Sign-offs

100

1

100

1.7

      Network testing

 

 

 

1.7.1

         Place machine on the network

1000

10

10000

1.7.2

         Sign-offs

100

1

100

 

Total cost

 

 

28580

(Billows, 2016)
Time phased estimation
This method helps in calculating the earned value management metrics. It provides the overall cost of the businesss value statement. Apart from that, the continengecy funds it’s contains is derived from the risk plan.

Task Name

1st week

2nd week

3rd week

4th week

Revamp secure unit

 

 

 

 

   Planning

 

 

 

 

      Requirement analysis

500

 

 

 

      Perform feasibility study

400

 

 

 

      Prepare detailed plan

300

 

 

 

      Finalize deliverables

200

 

 

 

      Prepare communication plan

200

 

 

 

      Prepare testing plan

200

 

 

 

      Prepare change management plan

200

 

 

 

      Prepare risk management plan

200

 

 

 

      Get signoffs on the plans and deliverables

80

 

 

 

   Analyze & Design

 

 

 

 

         Conduct compatibility study

400

 

 

 

Conduct market research

500

 

 

 

         Prepare detailed configuration plan for computers

400

 

 

 

         Prepare bill of the material

300

 

 

 

         Sign-off on the material bill

100

 

 

 

      Vendor selection

 

 

 

 

         Raise tender for hardware

 

800

 

 

         Prepare the criteria for vendor selection

 

300

 

 

         Identify vendors for hardware

 

300

 

 

      Backup existing data

 

400

 

 

      Raise invoice for hardware purchase

 

 

 

 

         Perform quality check on selected hardware

 

500

 

 

         Store parts in the warehouse

 

100

 

 

      Install

 

 

 

 

Upgraed hardware on critical machine

 

 

600

 

Install software on these machines

 

 

800

 

Give demo

 

 

100

 

Perform quality check on selected hardware

 

 

500

 

      Machine test

 

 

 

 

         Test each machine

 

 

 

10000

         Sign-offs

 

 

 

100

      Network testing

 

 

 

 

         Place machine on the network

 

 

 

10000

         Sign-offs

 

 

 

100

 

3980

2400

2000

20200

 

3980

6380

8380

28580

(Kerzner, 2001)
 
References
Billows, D. (2016). Bottom-up Estimating. 4pm.com. Retrieved 27 July 2016, from https://www.4pm.com/bottom-up-estimating/
Duncan, W. (1996). A guide to the project management body of knowledge. Sylva, NC: PMI Communications.
Hyväri, I. (2006). Project management effectiveness in project-oriented business organizations. International Journal Of Project Management, 24(3), 216-225. https://dx.doi.org/10.1016/j.ijproman.2005.09.001
Introduction to Project Management: Principles, Techniques and Tools. (2013) (1st ed.). Retrieved from https://oe.ucdavis.edu/local_resources/docs/projectmanagementtraining.pdf
Kerzner, H. (2001). Project management. New York: John Wiley.

Free Membership to World’s Largest Sample Bank

To View this & another 50000+ free samples. Please put
your valid email id.

E-mail

Yes, alert me for offers and important updates

Submit 

Download Sample Now

Earn back the money you have spent on the downloaded sample by uploading a unique assignment/study material/research material you have. After we assess the authenticity of the uploaded content, you will get 100% money back in your wallet within 7 days.

UploadUnique Document

DocumentUnder Evaluation

Get Moneyinto Your Wallet

Total 10 pages

PAY 6 USD TO DOWNLOAD

*The content must not be available online or in our existing Database to qualify as
unique.

Cite This Work
To export a reference to this article please select a referencing stye below:

APA
MLA
Harvard
OSCOLA
Vancouver

My Assignment Help. (2017). Concepts And Procedures Of Project Management. Retrieved from https://myassignmenthelp.com/free-samples/concepts-and-procedures-of-project-management.

“Concepts And Procedures Of Project Management.” My Assignment Help, 2017, https://myassignmenthelp.com/free-samples/concepts-and-procedures-of-project-management.

My Assignment Help (2017) Concepts And Procedures Of Project Management [Online]. Available from: https://myassignmenthelp.com/free-samples/concepts-and-procedures-of-project-management[Accessed 19 December 2021].

My Assignment Help. ‘Concepts And Procedures Of Project Management’ (My Assignment Help, 2017) accessed 19 December 2021.

My Assignment Help. Concepts And Procedures Of Project Management [Internet]. My Assignment Help. 2017 [cited 19 December 2021]. Available from: https://myassignmenthelp.com/free-samples/concepts-and-procedures-of-project-management.

×
.close{position: absolute;right: 5px;z-index: 999;opacity: 1;color: #ff8b00;}

×

Thank you for your interest
The respective sample has been mail to your register email id

×

CONGRATS!
$20 Credited
successfully in your wallet.
* $5 to be used on order value more than $50. Valid for
only 1
month.

Account created successfully!
We have sent login details on your registered email.

User:

Password:

With time, MyAssignmenthelp.com has become one of the best college essay writing services. Our all rounded services give students the confidence to overcome assignment related issues. Our services are fast enough to meet most urgent deadlines. We are capable of delivering fast essay writing services with the help of our specially designed provisions and writers’ teams. Our urgent essay help services guarantee most rapid delivery of assignment solutions. Some of our most popular essay services are application essay help, exploratory essay help, literary review essay help and argumentative essay help.

Latest Project Management Samples

div#loaddata .card img {max-width: 100%;
}

SBM 1201 Project Scope, Time And Cost Management
Download :
0 | Pages :
12

Course Code: SBM1201
University: Asia Pacific International College

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answer:
Introduction
This project plan deals with the development of a fuel-efficient HHO Generator. The HHO fuel cells may appear to provide high fuel efficiency to the users. Nevertheless, there are a few confinements and focuses to be seen, as given beneath. This is to clear up that there is NO 100% substitution of petroleum derivative by including HHO cell. HHO gas is otherwise called Brown Gas, yet this is to illuminate that HHO gas is n…
Read
More
Tags:
Australia Footscray Management organisational behviour University of New South Wales Masters in Business Administration 

HS2061 Information Systems Project Management
Download :
0 | Pages :
9

Course Code: HS2061
University: Holmes Institute

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answer:
Case Overview:
The project owner of the Signed, sealed, delivered courier service is facing the problems of managing order of couriers in the synchronised manner. The project manager is incapable of managing central warehouse for the dispatching of products. The important information can be lost with the passage of time. The inventory management of the warehouse is the major concern for the owner of the company. He is looking forward …
Read
More

OPS 935 Project Management
Download :
0 | Pages :
11

Course Code: OPS935
University: University Of Wollongong

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answer:
Introduction
This essay explores the impacts of digital technologies on project management. It explores how adoption of digital technologies by companies for managing their project have affected their, project managers, human resource, business processes, timelines, deliverables, and practices  of risk management, people management and quality management.
Impact of Digital technologies on Project Management Practices
Digital te…
Read
More
Tags:
Australia Saint Kilda Management International Management University of New South Wales Masters in Business Administration 

ITC505 ICT Project Management
Download :
0 | Pages :
10

Course Code: ITC505
University: Charles Sturt University

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answers
Case Study- Social Media Research Center
Task-1: Project Charter
Project Objectives
The main objective of the project is to develop a web-based system within the organization “Social Media research Center”. It is analyzed that the Social Media research center wants to develop the web based system in order to connect people with the organization for promoting its research center. The web-based system that is developed conta…
Read
More
Tags:
Australia Alfredton Management IT Network Security  University of New South Wales Masters in Business Administration 

ITC505 ICT Project Management
Download :
0 | Pages :
7

Course Code: ITC505
University: Charles Sturt University

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answers
Part One- Project Name / Team / Description
Project Name:
RALS Solution
Team Name:
Consultants for RALS
Project Description:
RALS organizes show for the farmers and other related small business persons to display their latest technology equipment for betterment in the field of agriculture and crop production. The show has different types of stalls and other facilities for which many volunteers …
Read
More

Next

Need an essay written specifically to meet your requirements?

Choose skilled experts on your subject and get an original paper within your deadline

156 experts online

Your time is important. Let us write you an essay from scratch

Tips and Tricks from our Blog

11174 Introduction To Management

Free Samples 11174 Introduction To Management .cms-body-content table{width:100%!important;} #subhidecontent{ position: relative; overflow-x: auto; width: 100%;} 11174 Introduction

Read More »