Development Of CRM System Within The Organization
0 Download9 Pages / 2,043 Words
Question:
Discuss about the development of CRM system within the organization.
Answer:
Title
The title of the project is “development of CRM system” within the organization “Tier One Suppliers Insurance Group”.
Scope Overview
The scope of the project is mainly categorized into in-scope and out-scope.
In-scope: The in-scope of the project includes:
Up gradation of information system of the organization “Tier One Supplier Insurance Group”
Developing CRM system within the organization
Issuing tablets to the workers of the organization
Integration of laptop and tablets with the TOSIG system
Out scope: The out scope of the project includes:
Proper training facility is not provided to the workers of the organization
Information about the suppliers are not elaborated
Business case
The organization “Tier One Suppliers Insurance Group” offers insurance service for improving stockyards, fencing, storage silos, building as well as machinery. The main aim of the organization is to maintain its customers and to enhance the number of insurance products that is delivered to the customer of the organization. The staffs of the organization needs to re-enter information within the TOSIG system at the end of the day and after then they generally receives a report. However, one of the major concern that is rising is that the organization is missing opportunities for selling insurance, as their agents does not have the ability of receiving report in the field. Another factor that is reducing the sale of insurance is that the organizational staff spend much time in the office in entering information into the system for visiting the site. One of the major threat that the organization is getting is due to the entrance of other insurance companies within Australia. In order to resolve all the issues and challenges, the organization wants to upgrade their information system into CRM system. The organization provides tablets as well as laptop to the agents and integrate them with the TOSIG system so that the data will directly move to the cloud thus reducing the time that the argents generally spend on entering data.
Background
The organization “Tier one supplier insurance group” generally helps in offering insurance to the tier one suppliers for improving buildings, fencing, stockyards, machinery as well as storage silos. The organization is operating from the last 65 years and they generally pride themselves on traditional values in order to maintain long-term relationships with the clients of the organization. They generally underwrite insurance on 6.7 billion dollar and have 150 agents on the field who mainly involves in maintaining offices for enhancing the number of insurance products that is mainly offered to the clients. The organization also want to enhance the sales of insurance within medium as well as small size organizations in various regional areas.
Milestone schedule
Task Name
Duration
Start
Finish
Implementation of CRM system
58 days
Fri 11-05-18
Tue 31-07-18
Project initiation phase
13 days
Fri 11-05-18
Tue 29-05-18
Business case development
3 days
Fri 11-05-18
Tue 15-05-18
Identifying need for CRM system
2 days
Wed 16-05-18
Thu 17-05-18
Undertaking feasibility analysis
2 days
Fri 18-05-18
Mon 21-05-18
Defining project activities
1 day
Tue 22-05-18
Tue 22-05-18
Establishment of project charter
3 days
Wed 23-05-18
Fri 25-05-18
Appointment of team members
2 days
Mon 28-05-18
Tue 29-05-18
Milestone 1: Completion of project initiation phase
0 days
Tue 29-05-18
Tue 29-05-18
Planning phase of the project
15 days
Wed 30-05-18
Tue 19-06-18
Project plan development
3 days
Wed 30-05-18
Fri 01-06-18
Resource plan development
2 days
Mon 04-06-18
Tue 05-06-18
Financial plan development
3 days
Wed 06-06-18
Fri 08-06-18
Quality plan development
2 days
Mon 11-06-18
Tue 12-06-18
Creation of acceptance plan
3 days
Wed 13-06-18
Fri 15-06-18
Development of communication plan
2 days
Mon 18-06-18
Tue 19-06-18
Milestone 2: Completion of planning phase
0 days
Fri 15-06-18
Fri 15-06-18
Execution phase of the project
26 days
Wed 20-06-18
Wed 25-07-18
Project prototype development
4 days
Wed 20-06-18
Mon 25-06-18
Drafting configuration plan
3 days
Tue 26-06-18
Thu 28-06-18
Data transfer
4 days
Fri 29-06-18
Wed 04-07-18
Database connection
2 days
Thu 05-07-18
Fri 06-07-18
Response time testing
5 days
Mon 09-07-18
Fri 13-07-18
Query testing
3 days
Mon 16-07-18
Wed 18-07-18
Acceptance testing
2 days
Thu 19-07-18
Fri 20-07-18
Software testing
1 day
Mon 23-07-18
Mon 23-07-18
Testing data warehouse
1 day
Tue 24-07-18
Tue 24-07-18
Connection testing
1 day
Wed 25-07-18
Wed 25-07-18
Milestone 3:Completion of execution phase
0 days
Wed 25-07-18
Wed 25-07-18
Closure phase
4 days
Thu 26-07-18
Tue 31-07-18
Post project review
2 days
Thu 26-07-18
Fri 27-07-18
Stakeholder sign off
1 day
Mon 30-07-18
Mon 30-07-18
Go live
1 day
Tue 31-07-18
Tue 31-07-18
Milestone 4: Completion of project closure phase
0 days
Tue 31-07-18
Tue 31-07-18
Risks, assumptions and constraints
Project risk
Risk
Description
Impact
Probability
Mitigation process
Schedule slippage
If the project schedule is not tracked properly then the project manager faces challenges in finishing the project within the expected deadline
Significant
Very Likely
In order to resolve the issues the project manager must track the schedule of the project regular for making sure that the project is going in the right direction.
Budget shortfall
If the budget of the project is not managed appropriately then the project faces challenges due to shortage of project budget
Significant
Likely
In order to mitigate the issue it is necessary to use earned value analysis for making sure that proper amount budget is utilized on the project.
Inexperienced project manager
If the project managers are not experienced then they faces lot of issues and challenges in finishing the project.
Moderate
Possible
The problem can be avoided by hiring experienced project managers within the project.
Improper integration
If the system is not integrated properly, in the cloud then the data that is entered will not store within the cloud and as a result, the data as well as information can get lost.
Significant
Likely
It can be mitigated by the checking the problem by the system engineer who generally fixes the problem.
Improper management
If the project is not managed properly within the project then it will be quite difficult to finish the project on expected time and budget.
Moderate
Possible
Proper management strategies must be utilized by the staffs of the organization for managing the project in each of the phase of the project.
Assumption
The assumptions that are made within the project are as follows:
The entire project will get finished within the budget of around $10 000.
It is expected that the project of CRM development will get finished within 58 days.
It is assumed that the project will follow the project scope during the entire progress phase.
Constraints
The constraints of the project are as follows:
Time: The development of CRM system must be finished within 58 days otherwise the budget that is associated with project development will increase.
Budget: The entire project should be finished within the budget $10 000.
Scope: The project must follow the scope in order execute the entire project within the expected budget and time.
Stakeholder list
The stakeholders who are involved within the project are listed in the table below:
Stakeholders
Responsibilities
Project manager
The project manager mainly engages within the project in order to manage, monitor as well as execute the project from the initiation until the closure phase of the project.
Project planner
The project planner mainly engages in estimating the resources as well as time that is needed in finishing the project effectively. They also monitors as well as determines the effectiveness of the project with the help of proper qualitative and quantitative tools.
Human resource manager
The human resource manager is the person who mainly engages in hiring the team members for the project.
Financial manager
The financial managers plays a great role in managing the budget of the project successfully.
Application engineer
The application engineers are responsible for developing, designing as well as implementing various applications as well as programs. They are generally able to create applications that generally respond to the needs as well as requirements of the customers. In addition to this, they also provide technical support.
Database administrator
The database administrator is responsible for software installation, maintenance, data extraction, loading, transformation, specialized handling of data, proper database backup and recovery. The database administrator also plays a great role in minimizing the risks that is associated with the database software.
Technical analyst
The technical analyst are the person who are mainly responsible for administering IT systems for recommending proper efficient modifications for improving the efficiency as well as for reducing the operations by determining appropriate procedures for all the IT related technologies that generally assists in all equipment configuration.
Risk manager
The risk manager is the person who mainly involves within the project and analyzes the risks as well as challenges that are associated within the project in order to resolve them with the help of proper mitigation strategy.
Bibliography
Badewi, A., 2016. The impact of project management (PM) and benefits management (BM) practices on project success: Towards developing a project benefits governance framework. International Journal of Project Management, 34(4), pp.761-778.
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project Management Institute.
Heldman, K., 2018. PMP: project management professional exam study guide. John Wiley & Sons.
Joslin, R. and Müller, R., 2015. Relationships between a project management methodology and project success in different project governance contexts. International Journal of Project Management, 33(6), pp.1377-1392.
Kerzner, H., 2017. Project management metrics, KPIs, and dashboards: a guide to measuring and monitoring project performance. John Wiley & Sons.
Kucharska, W. and Kowalczyk, R., 2016. Trust, Collaborative Culture and Tacit Knowledge Sharing in Project Management–a Relationship Model.
Marcelino-Sádaba, S., Pérez-Ezcurdia, A., Lazcano, A.M.E. and Villanueva, P., 2014. Project risk management methodology for small firms. International journal of project management, 32(2), pp.327-340.
Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), pp.202-217.
Riol, H. and Thuillier, D., 2015. Project management for academic research projects: balancing structure and flexibility. International Journal of Project Organisation and Management, 7(3), pp.251-269.
Svejvig, P. and Andersen, P., 2015. Rethinking project management: A structured literature review with a critical look at the brave new world. International Journal of Project Management, 33(2), pp.278-290.
Todorovi?, M.L., Petrovi?, D.?., Mihi?, M.M., Obradovi?, V.L. and Bushuyev, S.D., 2015. Project success analysis framework: A knowledge-based approach in project management. International Journal of Project Management, 33(4), pp.772-783.
Too, E.G. and Weaver, P., 2014. The management of project management: A conceptual framework for project governance. International Journal of Project Management, 32(8), pp.1382-1394.
Free Membership to World’s Largest Sample Bank
To View this & another 50000+ free samples. Please put
your valid email id.
Yes, alert me for offers and important updates
Submit
Download Sample Now
Earn back the money you have spent on the downloaded sample by uploading a unique assignment/study material/research material you have. After we assess the authenticity of the uploaded content, you will get 100% money back in your wallet within 7 days.
UploadUnique Document
DocumentUnder Evaluation
Get Moneyinto Your Wallet
Total 9 pages
PAY 5 USD TO DOWNLOAD
*The content must not be available online or in our existing Database to qualify as
unique.
Cite This Work
To export a reference to this article please select a referencing stye below:
APA
MLA
Harvard
OSCOLA
Vancouver
My Assignment Help. (2019). Development Of CRM System Within The Organization. Retrieved from https://myassignmenthelp.com/free-samples/development-of-crm-system-within-the-organization.
“Development Of CRM System Within The Organization.” My Assignment Help, 2019, https://myassignmenthelp.com/free-samples/development-of-crm-system-within-the-organization.
My Assignment Help (2019) Development Of CRM System Within The Organization [Online]. Available from: https://myassignmenthelp.com/free-samples/development-of-crm-system-within-the-organization[Accessed 19 December 2021].
My Assignment Help. ‘Development Of CRM System Within The Organization’ (My Assignment Help, 2019)
My Assignment Help. Development Of CRM System Within The Organization [Internet]. My Assignment Help. 2019 [cited 19 December 2021]. Available from: https://myassignmenthelp.com/free-samples/development-of-crm-system-within-the-organization.
×
.close{position: absolute;right: 5px;z-index: 999;opacity: 1;color: #ff8b00;}
×
Thank you for your interest
The respective sample has been mail to your register email id
×
CONGRATS!
$20 Credited
successfully in your wallet.
* $5 to be used on order value more than $50. Valid for
only 1
month.
Account created successfully!
We have sent login details on your registered email.
User:
Password:
MyAssignmenthelp.com strives towards providing exceptional essay help at an affordable price. Students, from various parts of Australia, prefer our servicers because we provide high-quality essay assistance at a pocket-friendly price. We receive numerous requests ‘help me do my essay’ or ‘can someone write my essay’ from students every day. We efficiently fulfill those requests and provide students needed essay writing help art an affordable price.
Latest Project Management Samples
div#loaddata .card img {max-width: 100%;
}
SBM 1201 Project Scope, Time And Cost Management
Download :
0 | Pages :
12
Course Code: SBM1201
University: Asia Pacific International College
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answer:
Introduction
This project plan deals with the development of a fuel-efficient HHO Generator. The HHO fuel cells may appear to provide high fuel efficiency to the users. Nevertheless, there are a few confinements and focuses to be seen, as given beneath. This is to clear up that there is NO 100% substitution of petroleum derivative by including HHO cell. HHO gas is otherwise called Brown Gas, yet this is to illuminate that HHO gas is n…
Read
More
Tags:
Australia Footscray Management organisational behviour University of New South Wales Masters in Business Administration
HS2061 Information Systems Project Management
Download :
0 | Pages :
9
Course Code: HS2061
University: Holmes Institute
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answer:
Case Overview:
The project owner of the Signed, sealed, delivered courier service is facing the problems of managing order of couriers in the synchronised manner. The project manager is incapable of managing central warehouse for the dispatching of products. The important information can be lost with the passage of time. The inventory management of the warehouse is the major concern for the owner of the company. He is looking forward …
Read
More
OPS 935 Project Management
Download :
0 | Pages :
11
Course Code: OPS935
University: University Of Wollongong
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answer:
Introduction
This essay explores the impacts of digital technologies on project management. It explores how adoption of digital technologies by companies for managing their project have affected their, project managers, human resource, business processes, timelines, deliverables, and practices of risk management, people management and quality management.
Impact of Digital technologies on Project Management Practices
Digital te…
Read
More
Tags:
Australia Saint Kilda Management International Management University of New South Wales Masters in Business Administration
ITC505 ICT Project Management
Download :
0 | Pages :
10
Course Code: ITC505
University: Charles Sturt University
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answers
Case Study- Social Media Research Center
Task-1: Project Charter
Project Objectives
The main objective of the project is to develop a web-based system within the organization “Social Media research Center”. It is analyzed that the Social Media research center wants to develop the web based system in order to connect people with the organization for promoting its research center. The web-based system that is developed conta…
Read
More
Tags:
Australia Alfredton Management IT Network Security University of New South Wales Masters in Business Administration
ITC505 ICT Project Management
Download :
0 | Pages :
7
Course Code: ITC505
University: Charles Sturt University
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answers
Part One- Project Name / Team / Description
Project Name:
RALS Solution
Team Name:
Consultants for RALS
Project Description:
RALS organizes show for the farmers and other related small business persons to display their latest technology equipment for betterment in the field of agriculture and crop production. The show has different types of stalls and other facilities for which many volunteers …
Read
More
Next