Free Samples
Earned Value For The Project
.cms-body-content table{width:100%!important;} #subhidecontent{ position: relative;
overflow-x: auto;
width: 100%;}
Earned Value For The Project
0 Download8 Pages / 1,799 Words
Question:
Write an essay on Earned value for the project using the 50-50 Rule.
Answer:
1. Earned value for the project using the 50-50 Rule
The Earned value of a project is the total budgeted costs of the activities involved in the project (Vanhoucke 2013).
Budget
Begun?
Complete?
Actual cost
Task A
$3,100.00
Yes
Yes
$ 3,100.00
Task B
$4,000.00
Yes
Yes
$ 4,500.00
Task C
$2,500.00
Yes
Yes
$ 2,250.00
Task D
$4,000.00
Yes
No
$ 3,500.00
Task E
$3,500.00
Yes
Yes
$ 4,000.00
Task F
$2,500.00
No
No
$ –
Assumptions of 50-50 method for calculating the Earned Value:
EV is 0 before the start of an activity
EV is 50% of total activity budget after an activity is started
EV is 100% of the budget if the tasks is completed (Gupta 2014)
50-50 method
Task A
$ 3,100.00
Task B
$ 4,000.00
Task C
$ 2,500.00
Task D
$ 2,000.00
Task E
$ 3,500.00
Task F
$ –
Earned Value of the project
$ 15,100.00
2. Earned value for the project using the 0-100 Rule
Budget
Begun?
Complete?
Actual cost
Task A
$3,100.00
Yes
Yes
$ 3,100.00
Task B
$4,000.00
Yes
Yes
$ 4,500.00
Task C
$2,500.00
Yes
Yes
$ 2,250.00
Task D
$4,000.00
Yes
No
$ 3,500.00
Task E
$3,500.00
Yes
Yes
$ 4,000.00
Task F
$2,500.00
No
No
$ –
Assumptions of 0-100 method for calculating the Earned Value:
EV is 0 before the start of an activity
EV is 0 if an activity is not completed
EV is 100% of the budget if the task is completed (Gupta 2014)
0-100 method
Task A
$ 3,100.00
Task B
$ 4,000.00
Task C
$ 2,500.00
Task D
$ –
Task E
$ 3,500.00
Task F
$ –
Earned Value of the project
$ 13,100.00
3. Discrepancy of earned value figures when using the 50-50 Rule and 0-100 Rule
50-50 method
0-100 method
Task A
$ 3,100.00
$ 3,100.00
Task B
$ 4,000.00
$ 4,000.00
Task C
$ 2,500.00
$ 2,500.00
Task D
$ 2,000.00
$ –
Task E
$ 3,500.00
$ 3,500.00
Task F
$ –
$ –
Earned Value of the project
$ 15,100.00
$ 13,100.00
The earned value of a project helps in determining the quantity of tasks being completed to date and the amount of cost having spent for the amount of work (Vanhoucke 2013). From the analysis of the information of the earned values of the project, it can be evident that there is a discrepancy in the values as estimated using two different methods. In comparison with the results obtained by utilizing the two estimation methods, the earned value as calculated using the 50-50 method shows more accurate results. The reason is due to the fact that the 0-100 method does not take any information from the project budget until a particular activity is completed. In other words, the 0-100 method declares the Earned Value of the project to be $ 0 until the entire task is completed. However, the 50-50 method takes 50% of the activity to be completed even after a particular activity has just started.
Thus, in comparison, the 50-50 method helps in providing a closer approximation in reality than the 0-100 method. The main reason is that the 50-50 method declares the earned value of a particular activity to be greater than $ 0 while it is under progress.
4. Schedule Variance (SV) for the project as reported using the 50-50 Rule
Scheduled Variance of a project = =Earned value – Planned value
Planned Value = Total budget costs for the tasks completed so far
Budget
Begun?
Complete?
Actual cost
Task A
$3,100.00
Yes
Yes
$ 3,100.00
Task B
$4,000.00
Yes
Yes
$ 4,500.00
Task C
$2,500.00
Yes
Yes
$ 2,250.00
Task D
$4,000.00
Yes
No
$ 3,500.00
Task E
$3,500.00
Yes
Yes
$ 4,000.00
Task F
$2,500.00
No
No
$ –
Earned value of the project
$ 15,100
Planned value
$ 13,100
Planned value, PV = $ 13,100
Earned value, EV (using 50-50 method) = $ 15,100
Thus, Schedule Variance, SV = EV-PV= $ 2000
A positive SV represents that the project is ahead of the schedule (Tom and Paul 2013)
5. Schedule Performance Index (SPI)
Scheduled Performance Index= =Earned value /Planned value
Budget
Begun?
Complete?
Actual cost
Task A
$3,100.00
Yes
Yes
$ 3,100.00
Task B
$4,000.00
Yes
Yes
$ 4,500.00
Task C
$2,500.00
Yes
Yes
$ 2,250.00
Task D
$4,000.00
Yes
No
$ 3,500.00
Task E
$3,500.00
Yes
Yes
$ 4,000.00
Task F
$2,500.00
No
No
$ –
Earned value of the project
$ 15,100
Planned value
$ 13,100
Planned value, PV = $ 13,100
Earned value, EV (using 50-50 method) = $ 15,100
Thus, SPI = ($ 15,100/ $13,100) = 1.15
A positive SPI represents that the project is ahead of the schedule i.e., i.e., the project has achieved more than what is expected (Lipke 2013)
6. Cost Variance (CV) for the project as reported using the 50-50 Rule
Budget
Begun?
Complete?
Actual cost
Earned Value (using 50-50 rule
Task A
$3,100.00
Yes
Yes
$ 3,100.00
$3,100.00
Task B
$4,000.00
Yes
Yes
$ 4,500.00
$4,000.00
Task C
$2,500.00
Yes
Yes
$ 2,250.00
$2,500.00
Task D
$4,000.00
Yes
No
$ 3,500.00
$2,000.00
Task E
$3,500.00
Yes
Yes
$ 4,000.00
$3,500.00
Task F
$2,500.00
No
No
$ –
$ –
Earned value of the project
$ 15,100
Actual cost
$ 18,100.00
Cost Variance = Earned value – Actual cost
Actual cost =Total expenditure for the work so far = $ 18,100.00
Thus, Cost Variance, CV for the project = $ 15,100- $ 18,100= (-$ 3,000)
A negative CV represents that the project is over budget (Lipke 2013)
7. Cost Performance Index (CPI)
Cost Performance Index = =Earned value / Actual cost
Budget
Begun?
Complete?
Actual cost
Earned Value (using 50-50 rule
Task A
$3,100.00
Yes
Yes
$ 3,100.00
$3,100.00
Task B
$4,000.00
Yes
Yes
$ 4,500.00
$4,000.00
Task C
$2,500.00
Yes
Yes
$ 2,250.00
$2,500.00
Task D
$4,000.00
Yes
No
$ 3,500.00
$2,000.00
Task E
$3,500.00
Yes
Yes
$ 4,000.00
$3,500.00
Task F
$2,500.00
No
No
$ –
$ –
Earned value of the project
$ 15,100
Actual cost
$ 18,100.00
Thus, Cost Performance Index (CPI) for the project= ($15,100/ $ 18,100) = 0.83
A CPI having value
8. CPI to compute estimate at complete (EAC)
Estimate at Time or, EAC is a way for projecting the planned cost at the completion of the project based on the current data. It shows the variance in the actual final cost and the planned final cost (Caron, Ruggeri and Merli 2013).
EAC= BAC/ CPI (BAC is the total Budget at Completion)
Total budget for the project, (BAC) = $50,000
Thus, EAC for the project = ($50,000/ 0.83) = $ 59,933.77
9. Report on the progress of the project
From the earned value information as estimated for the project, it can be evident that the earned value for the project is less than what is expected from the same. This has been due to the fact than the tasks involved in the project are not properly scheduled. Moreover, the actual value of the work being completed in the project is behind its planned value. Moreover, the total tasks being completed in the project is not matching with the total budget of the tasks being estimated.
Summary of the calculations being estimated
Earned value = $ 15,100 (using 50-50 method)
= $ 13,100 (using 0-100 method)
Schedule Variance, SV = $ 2000
Schedule Performance Index, SPI = 1.15
Cost Variance, CV = – ($ 3,000)
Cost Performance Index, CPI = 0.83
Estimate at Completion, EAC = $ 59,933.77
Future projection
From the estimated information about the Schedule Variance (SV) and the Schedule Performance Index (SPI), it can be evident that the project has been ahead of the actual scheduled time and the project has been achieving more than what is expected from the same. However, the information about the Cost Variance (CV) and the Cost Performance Index (CPI) shows that the project has been running on over budget and has been varying in the actual final cost than what is planned final cost for the project. This can be evident from the EAC value for the project. Thus, the managers are required to provide a check on the expenses and reschedule the budget such that extra expenses could be saved. The managers are also required to reschedule the timeline for the project such that to ensure the running of the project within the estimated timeline and budget.
References
Caron, F., Ruggeri, F. and Merli, A., 2013. A Bayesian approach to improve estimate at completion in earned value management. Project Management Journal, 44(1), pp.3-16.
Gupta, R., 2014. Earned Value Management System. International Journal of Emerging Engineering Research and Technology, 2(4), pp.160-165.
Lipke, W., 2013. Earned Schedule–Ten Years After. The Measurable News (3), pp.15-21.
Tom, A.F. and Paul, S., 2013. Project monitoring and control using primavera. International Journal of Innovative Research in Science, Engineering and Technology, 2(3), pp.762-771.
Vanhoucke, M., 2013. The impact of project schedule adherence and rework on the duration forecast accuracy of earned value metrics. Project management: practices, challenges and developments, pp.95-131.
Free Membership to World’s Largest Sample Bank
To View this & another 50000+ free samples. Please put
your valid email id.
Yes, alert me for offers and important updates
Submit
Download Sample Now
Earn back the money you have spent on the downloaded sample by uploading a unique assignment/study material/research material you have. After we assess the authenticity of the uploaded content, you will get 100% money back in your wallet within 7 days.
UploadUnique Document
DocumentUnder Evaluation
Get Moneyinto Your Wallet
Total 8 pages
PAY 5 USD TO DOWNLOAD
*The content must not be available online or in our existing Database to qualify as
unique.
Cite This Work
To export a reference to this article please select a referencing stye below:
APA
MLA
Harvard
OSCOLA
Vancouver
My Assignment Help. (2017). Earned Value For The Project. Retrieved from https://myassignmenthelp.com/free-samples/earned-value-for-the-project.
“Earned Value For The Project.” My Assignment Help, 2017, https://myassignmenthelp.com/free-samples/earned-value-for-the-project.
My Assignment Help (2017) Earned Value For The Project [Online]. Available from: https://myassignmenthelp.com/free-samples/earned-value-for-the-project[Accessed 19 December 2021].
My Assignment Help. ‘Earned Value For The Project’ (My Assignment Help, 2017)
My Assignment Help. Earned Value For The Project [Internet]. My Assignment Help. 2017 [cited 19 December 2021]. Available from: https://myassignmenthelp.com/free-samples/earned-value-for-the-project.
×
.close{position: absolute;right: 5px;z-index: 999;opacity: 1;color: #ff8b00;}
×
Thank you for your interest
The respective sample has been mail to your register email id
×
CONGRATS!
$20 Credited
successfully in your wallet.
* $5 to be used on order value more than $50. Valid for
only 1
month.
Account created successfully!
We have sent login details on your registered email.
User:
Password:
MyAssignmenthelp.com delivers assignment help to millions of students of USA. We have in-house teams of assignment writers who are experts on wide ranges of subjects. We have appointed teams of native writers who provide assignment help to students in New York City and all over the USA. They are skilled assignment writers who successfully cater to search terms like do my assignment in the USA
Latest Project Management Samples
div#loaddata .card img {max-width: 100%;
}
SBM 1201 Project Scope, Time And Cost Management
Download :
0 | Pages :
12
Course Code: SBM1201
University: Asia Pacific International College
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answer:
Introduction
This project plan deals with the development of a fuel-efficient HHO Generator. The HHO fuel cells may appear to provide high fuel efficiency to the users. Nevertheless, there are a few confinements and focuses to be seen, as given beneath. This is to clear up that there is NO 100% substitution of petroleum derivative by including HHO cell. HHO gas is otherwise called Brown Gas, yet this is to illuminate that HHO gas is n…
Read
More
Tags:
Australia Footscray Management organisational behviour University of New South Wales Masters in Business Administration
HS2061 Information Systems Project Management
Download :
0 | Pages :
9
Course Code: HS2061
University: Holmes Institute
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answer:
Case Overview:
The project owner of the Signed, sealed, delivered courier service is facing the problems of managing order of couriers in the synchronised manner. The project manager is incapable of managing central warehouse for the dispatching of products. The important information can be lost with the passage of time. The inventory management of the warehouse is the major concern for the owner of the company. He is looking forward …
Read
More
OPS 935 Project Management
Download :
0 | Pages :
11
Course Code: OPS935
University: University Of Wollongong
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answer:
Introduction
This essay explores the impacts of digital technologies on project management. It explores how adoption of digital technologies by companies for managing their project have affected their, project managers, human resource, business processes, timelines, deliverables, and practices of risk management, people management and quality management.
Impact of Digital technologies on Project Management Practices
Digital te…
Read
More
Tags:
Australia Saint Kilda Management International Management University of New South Wales Masters in Business Administration
ITC505 ICT Project Management
Download :
0 | Pages :
10
Course Code: ITC505
University: Charles Sturt University
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answers
Case Study- Social Media Research Center
Task-1: Project Charter
Project Objectives
The main objective of the project is to develop a web-based system within the organization “Social Media research Center”. It is analyzed that the Social Media research center wants to develop the web based system in order to connect people with the organization for promoting its research center. The web-based system that is developed conta…
Read
More
Tags:
Australia Alfredton Management IT Network Security University of New South Wales Masters in Business Administration
ITC505 ICT Project Management
Download :
0 | Pages :
7
Course Code: ITC505
University: Charles Sturt University
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answers
Part One- Project Name / Team / Description
Project Name:
RALS Solution
Team Name:
Consultants for RALS
Project Description:
RALS organizes show for the farmers and other related small business persons to display their latest technology equipment for betterment in the field of agriculture and crop production. The show has different types of stalls and other facilities for which many volunteers …
Read
More
Next