ECM28EMD-Process For Monitoring And Control Of A Project

.cms-body-content table{width:100%!important;} #subhidecontent{ position: relative;
overflow-x: auto;
width: 100%;}

ECM28EMD-Process For Monitoring And Control Of A Project

1 Download14 Pages / 3,343 Words

Course Code: ECM28EMD
University: Middle East College

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Oman

Task
You are required to develop a strategic project plan in the form of a document not more than 4000 words, excluding appendices and references. There is considerable freedom of choice for
 
a suitable project scenario. But, whatever scenario you choose, assessment is against specific criteria that originate in the module learning outcomes. The module learning outcomes (1-5) are mapped to the following assessment criteria
 
1.Assess the business case for a project and recommend a strategy for reduction of uncertainties and the management of associated risk Assess the business case for a project and recommend a strategy for reduction of uncertainties and the management of associated risk
 
2.Recommend a suitable structure and process for monitoring and control of a project
 
3.Select and apply appropriate tools and techniques for the planning and management of a project
 
4.Formulate a strategy for the implementation of change.
 
 
Answer:

Introduction 
The project management holds an integral role for forming the implication management and aligning the utilization management. The completion of the works would be aligned with the management activity and management of the successive work completion. The integration has been managed with the consideration of the factors and managing the implication development. The following assignment would be implied with the integration of the improved work development. The business case analysis would be developed for listing the analysis of the factors for integration and alignment of the specific work completion. The assignment would include the analysis of project scope, objectives, KPI–project delivery, risk analysis, resource plan, estimation plan, communication plan, project schedule, monitoring and controlling strategy, changes applied on project schedule / cost, project status report, and change management details. The completion of the report would result in forming the final documentation development for the stakeholders.
Business Case
The business case is the analysis of the project background for the development of the effective and smart management processing. The implication of the works had been aligned with the utilization of the works and taking care of the project activities. The project plan would be developed for considering the specific alignment tools. The project would form the reduction of the OPEX/CAPEX in the organization by the installing the use of the ICT infrastructure, services, and resources. The project is also responsible for the utilization of the works and integrating the alignment of the factors for development of IT operations and enhancing the work alignment.
Project Scope, Objectives 
The project has been developed for utilizing the implication management operations and forming the successful integration of the activities. The project scope is an improved work proposition aligning the specific work execution and management of the activities. The project scope development has been largely implied with the factors for integrating the alignment of the specific work development. The scope of the project is given as,

Critical Factor Project Execution: The obtaining of the final decision has been developed for aligning the management of the works and the implication of the smart management development. The domain renaming was also a part of the project management processing.
Activity Scheduling Dependency: The development of the architecture would be supported by the development of effective documentation and processing. The project would include the scope development for the architectural design development.
Preparation of OGC Vertical Branding: The new branding for the OGC would be prepared with the alignment of the works for the continuation of the effective implication management.

The objectives of the project would be identified with the analysis of the completed analysis development model. The specific work would be developed considering the management of the factors and forming the management of the improved work development. The identified objectives of the project are,

To reduce the OPEX/CAPEX with the installation of the ICT infrastructure resources and services
To enhance of the maintainability for standardization and efficiency improvement development
To unify ICT policies, standards, and operations for reorganizing and specializing the IT departmental function enhancement

KPI – Project Delivery 
The key performance indicators of the project would be dependent on the key benefits for the project. The successful completion of the project would be dependent on the alignment of the works and the management of the activities would be effectively done for integrating the alignment for the successful management of the works. The ICT infrastructure development would be effectively implied with the continuation of the factors for the listing model. The shared services for multiple activities would be implied with the continuation of the improved management process. The key performance indicators for the project would be implied with the formation of the improved functional development. The listing of the key performance indicators would be implied with the formation of the successful listing management works. The key performance management activities would be implied with the listing of the activities and formation of the activities management. 
 
Risk Analysis
Risk identification
The project requires the use of the effective ICT technology development and implication for improving the services of the organization. The identified risk factors for the project are,
Excessive scope deviation: The deviation of the project from the scope is another major factor resulting in the formation of the issues for the users and problems for the developer. The change in requirements would result in causing the major setback for the project team to finish the project.
Project information and boundaries: The lack of the information related to the development of the effective and improved management process can result in forming the major implication issues. The major issues in technology information implementation is that it requires considerable amount of information for listing the management works.
Branding package timeliness: The delays in completion of the works would be highly cognitive in forming the alignment of the proper development. The activity would result in consumption of the time and if more amount of time is required for the activity to be completed then the final deliverable for the project would be delayed.
Resources for ICT Project Management: The shortage of resources is another major factor for causing the problem in completion of the works and the alignment of the improved management works. The lack of the resources would result in forming the issues in development of the smart work development.
Budget Availability: The lack of resources would result in minimizing the project budget resulting in major issues for the completion of the work. The lack of budget would tend to cause the major issues in forming the effective project budgeting.
Communication, Decision making and Authorities: The lack of communication would tend to form the impact in taking crucial decisions of the project and it would form the issues in forming the limitation management. The authorities of the project users would be formed for listing the development of the effective management processing.
Change Management issues: The change management issues would be dealt with the consideration of the factors for improved analysis and development. The change management would be impactful in forming the listing of the management processes. 
 
Level of engagement and cooperation from stakeholders: The level of the engagement and co-operations among the stakeholders would be tarnished due to the fact that the project leaders would be limited to the formation of the improved management.
Standardization and compliances: The standardization of the works related to the project activities would align with the considered for the formation of development. The compliance and standard operation would be aligned with the formation of the works aligned with the limitation of the activities and operations.
Risk categorization and analysis

Risk Name

Risk Type

Risk Description

Excessive scope deviation

External

The change in requirements would result in causing the major setback for the project team to finish the project.

Project information and boundaries

Internal

The major issues in technology information implementation is that it requires considerable amount of information for listing the management works.

Branding package timeliness

Internal

The delays in completion of the works would be highly cognitive in forming the alignment of the proper development.

Resources for ICT Project Management

Internal

The lack of the resources would result in forming the issues in development of the smart work development.

Budget Availability

Internal

The lack of budget would tend to cause the major issues in forming the effective project budgeting.

Communication, Decision making and Authorities
 

External

The lack of communication would tend to form the impact in taking crucial decisions of the project and it would form the issues in forming the limitation management.

Change Management issues
 

Internal

The change management issues would be dealt with the consideration of the factors for improved analysis and development.

Level of engagement and cooperation from stakeholders

External

The level of the engagement and co-operations among the stakeholders would be tarnished due to the fact that the project leaders would be limited to the formation of the improved management.

Standardization and compliances

Internal

The standardization of the works related to the project activities would align with the considered for the formation of development.

Risk management and mitigation plan

Risk Name

Risk Management Strategy

Risk Mitigation Plan

Excessive scope deviation

Avoid

Scope Management Plan should be used

Project information and boundaries

Exploit

Information Collection from various authentic resources

Branding package timeliness

Mitigate

Time Management Plan should be used

Resources for ICT Project Management

Transfer

Resource Management Plan should be used

Budget Availability

Avoid

Budget Management Plan should be used

Communication, Decision making and Authorities
 

Mitigate

Communication Plan should be used

Change Management issues
 

Avoid

Change Management Plan should be used

Level of engagement and cooperation from stakeholders

Share

Engagement and Motivation among the project stakeholders should be used

Standardization and compliances

Accept

Government and ACS standards should be followed

Resource Plan 
The resources required for the project include many human resources for taking care of the work and implying the listing of the works. It would be helpful for the alignment of the works and deploying the listing of the works and forming better and improved management operations.  

Role

Name

Responsibilities

Project Sponsor(s)

Abdulaziz Al-Mujaibi

Providing the specific alignment of the works and integrating the listing of the cohesive work development

Steering Committee

 

The steering committee would be responsible for analyzing the final output and aligning the implication of the listing works

Project Manager

Hakeem Al-Tauqi

Management of the works would be aligned with the management works listing the completion of the formation works.

Team Members

Ashraf Al-Jafari

Leading Project team members for the analysis of the works and forming the development of the activities

Kamran Ilyas

TelecomNetwork Lead

Faisal Qureishi

cybersecurityMobility Lead

Estimation Plan 
The project estimation plan would be developed with the compilation and development. The cost estimation and the time calculation is done for ensuring the smart work development works. The alignment would be implied for the management works and forming the successful management of the works. The estimation plan would be developed for integrating the listing of the alignment of works. The estimation plan is deployed with the continuation of the smart analysis and formation of the successive work alignment. 
 
Communication Plan
The communication plan for the project would be developed for ensuring the deployment of the effective work integration and listing of the works. The deployment of the smart work ethics would be employed for aligning the communication protocols and methods for transferring information from one source to other or many. The information sharing has also some probable frequencies for being executed. The following is the communication protocol/plan for the project,

Communication Mean

Information

Sender

Receiver

Frequency

Reports/Documents

Project Progress

Project Manager / Project Team

Client/ Project Manager

Weekly

Emails

Change Implication

Client

Project Manager

Once

Meetings

Project Requirements/

Project Manager /Client

Project Team/ Project Manager

Once

Telephone/SMS

Scope Development

Quality Analyst

Project Manager

Monthly

Project Schedule 
Task List

WBS

Task Name

0

IT Integration (base)

1

   Activity 1

2

   Activity 2

3

   Activity 3

4

   Activity 4

5

   Activity 5

6

   Activity 6

7

   Activity 7

8

   Activity 8

9

   Activity 9

10

   Activity 10

11

   Activity 11

12

   Activity 12

13

   Activity 13

14

   Activity 14

Summary tasks
The project summary tasks would be developed with the implication of the agile methodology for integrating the work development. The project summary tasks include the project initiation, project planning, project designing, project executing, project monitoring, and project closing.
WBS

Predecessor linking

WBS

Task Name

Predecessors

0

IT Integration (base)

 

1

   Activity 1

 

2

   Activity 2

 

3

   Activity 3

 

4

   Activity 4

1

5

   Activity 5

1

6

   Activity 6

1

7

   Activity 7

1

8

   Activity 8

7SS

9

   Activity 9

7SS

10

   Activity 10

9SS+65 days

11

   Activity 11

9SS+65 days

12

   Activity 12

9SS+65 days

13

   Activity 13

12SS+66 days

14

   Activity 14

12SS+66 days

Resource allocation

Role

Responsibilities

Project Sponsor(s)

Providing the specific alignment of the works and integrating the listing of the cohesive work development

Steering Committee

The steering committee would be responsible for analyzing the final output and aligning the implication of the listing works

Project Manager

Management of the works would be aligned with the management works listing the completion of the formation works.

Team Members

Leading Project team members for the analysis of the works and forming the development of the activities

TelecomNetwork Lead

cybersecurityMobility Lead

Gantt Chart
 
Network analysis diagrams
 
Monitoring and controlling strategy 
Mile Stone
The milestone for the project plan involves Kick off meeting, Plan approval, Design Completion, Development Completion, Testing Documentation, and Project Closure. 
 
Base line 
The status date for the baseline schedule is 11/18/18 and it has been given below,

% Complete

WBS

Task Name

Duration

Start

Finish

43%

0

IT Integration (base)_baseline

325 days

Mon 4/2/18

Fri 6/28/19

100%

1

   Activity 1

65 days

Mon 4/2/18

Fri 6/29/18

100%

2

   Activity 2

65 days

Mon 4/2/18

Fri 6/29/18

100%

3

   Activity 3

65 days

Mon 4/2/18

Fri 6/29/18

77%

4

   Activity 4

130 days

Mon 7/2/18

Fri 12/28/18

77%

5

   Activity 5

130 days

Mon 7/2/18

Fri 12/28/18

77%

6

   Activity 6

130 days

Mon 7/2/18

Fri 12/28/18

77%

7

   Activity 7

130 days

Mon 7/2/18

Fri 12/28/18

38%

8

   Activity 8

260 days

Mon 7/2/18

Fri 6/28/19

38%

9

   Activity 9

260 days

Mon 7/2/18

Fri 6/28/19

18%

10

   Activity 10

195 days

Mon 10/1/18

Fri 6/28/19

18%

11

   Activity 11

195 days

Mon 10/1/18

Fri 6/28/19

18%

12

   Activity 12

195 days

Mon 10/1/18

Fri 6/28/19

0%

13

   Activity 13

129 days

Tue 1/1/19

Fri 6/28/19

0%

14

   Activity 14

129 days

Tue 1/1/19

Fri 6/28/19

Critical Path

Float/Slack

WBS

Task Name

Early Start

Early Finish

Late Start

Late Finish

Total Slack

0

IT Integration (base)

Mon 4/2/18

Fri 6/28/19

Mon 4/2/18

Fri 6/28/19

0 days

1

   Activity 1

Mon 4/2/18

Fri 6/29/18

Mon 4/2/18

Fri 6/29/18

0 days

2

   Activity 2

Mon 4/2/18

Fri 6/29/18

Mon 4/1/19

Fri 6/28/19

260 days

3

   Activity 3

Mon 4/2/18

Fri 6/29/18

Mon 4/1/19

Fri 6/28/19

260 days

4

   Activity 4

Mon 7/2/18

Fri 12/28/18

Mon 12/31/18

Fri 6/28/19

130 days

5

   Activity 5

Mon 7/2/18

Fri 12/28/18

Mon 12/31/18

Fri 6/28/19

130 days

6

   Activity 6

Mon 7/2/18

Fri 12/28/18

Mon 12/31/18

Fri 6/28/19

130 days

7

   Activity 7

Mon 7/2/18

Fri 12/28/18

Mon 7/2/18

Fri 12/28/18

0 days

8

   Activity 8

Mon 7/2/18

Fri 6/28/19

Mon 7/2/18

Fri 6/28/19

0 days

9

   Activity 9

Mon 7/2/18

Fri 6/28/19

Mon 7/2/18

Fri 6/28/19

0 days

10

   Activity 10

Mon 10/1/18

Fri 6/28/19

Mon 10/1/18

Fri 6/28/19

0 days

11

   Activity 11

Mon 10/1/18

Fri 6/28/19

Mon 10/1/18

Fri 6/28/19

0 days

12

   Activity 12

Mon 10/1/18

Fri 6/28/19

Mon 10/1/18

Fri 6/28/19

0 days

13

   Activity 13

Tue 1/1/19

Fri 6/28/19

Tue 1/1/19

Fri 6/28/19

0 days

14

   Activity 14

Tue 1/1/19

Fri 6/28/19

Tue 1/1/19

Fri 6/28/19

0 days

Reflection & Conclusion 
I have been playing the role of the project manager for the project and it had been a very wonderful experience managing an IT project. The implication of the works would be implied with the continuation of the specific development management. It was not easy for managing an IT project as per my experience due to its ever-changing scope. The performance factor also plays a significance role for taking care of the work development.
The integration had been managed with the consideration of the factors and managing the implication development. The following assignment had been implied with the integration of the improved work development. The business case analysis had be developed for listing the analysis of the factors for integration and alignment of the specific work completion. The assignment had include the analysis of project scope, objectives, KPI–project delivery, risk analysis, resource plan, estimation plan, communication plan, project schedule, monitoring and controlling strategy, changes applied on project schedule / cost, project status report, and change management details. 
 
Bibliography
Beringer, C., Jonas, D. and Kock, A., 2013. Behavior of internal stakeholders in project portfolio management and its impact on success. International Journal of Project Management, 31(6), pp.830-846.
Bozic, K.J., Ward, L., Vail, T.P. and Maze, M., 2014. Bundled payments in total joint arthroplasty: targeting opportunities for quality improvement and cost reduction. Clinical Orthopaedics and Related Research®, 472(1), pp.188-193.
Burke, R., 2013. Project management: planning and control techniques. New Jersey, USA.
Carver, C.L. and Klein, C.S., 2013. Action research: A tool for promoting faculty development and continuous improvement in leadership preparation.
Clark, D.M., Silvester, K. and Knowles, S., 2013. Lean management systems: creating a culture of continuous quality improvement. Journal of clinical pathology, pp.jclinpath-2013.
Dale, B.G. and Plunkett, J.J., 2017. Quality costing. Routledge.
Dessinger, J.C. and Moseley, J.L., 2015. Confirmative evaluation: Practical strategies for valuing continuous improvement. John Wiley & Sons.
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project Management Institute.
Fryer, K., Ogden, S. and Anthony, J., 2013. Bessant’s continuous improvement model: revisiting and revising. International Journal of Public Sector Management, 26(6), pp.481-494.
Fuller, M.A., Valacich, J.S., George, J.F. and Schneider, C., 2017. Information Systems Project Management: A Process and Team Approach, Edition 1.1. Prospect Press.
Goetsch, D.L. and Davis, S.B., 2014. Quality management for organizational excellence. Upper Saddle River, NJ: pearson.
Harrison, F. and Lock, D., 2017. Advanced project management: a structured approach. Routledge.
Heagney, J., 2016. Fundamentals of project management. Amacom.
Holtskog, H., 2013. Continuous Improvement beyond the Lean understanding. Procedia CIRP, 7, pp.575-579.
Hwang, B.G. and Ng, W.J., 2013. Project management knowledge and skills for green construction: Overcoming challenges. International Journal of Project Management, 31(2), pp.272-284.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Kerzner, H., 2018. Project management best practices: Achieving global excellence. John Wiley & Sons.
Lam, M., O’Donnell, M. and Robertson, D., 2015. Achieving employee commitment for continuous improvement initiatives. International Journal of Operations & Production Management, 35(2), pp.201-215.
Larson, E.W., Gray, C.F., Danlin, U., Honig, B. and Bacarini, D., 2014. Project management: The managerial process (Vol. 6). Grandview Heights, OH: McGraw-Hill Education.
Leach, L.P., 2014. Critical chain project management. Artech House.
Lemire, M., Demers-Payette, O. and Jefferson-Falardeau, J., 2013. Dissemination of performance information and continuous improvement: a narrative systematic review. Journal of health organization and management, 27(4), pp.449-478.
Magar, V.M. and Shinde, V.B., 2014. Application of 7 quality control (7 QC) tools for continuous improvement of manufacturing processes. International Journal of Engineering Research and General Science, 2(4), pp.364-371.
Marchewka, J.T., 2014. Information technology project management. John Wiley & Sons.
Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), pp.202-217.
Mitra, A., 2016. Fundamentals of quality control and improvement. John Wiley & Sons.
Nadeem, E., Olin, S.S., Hill, L.C., Hoagwood, K.E. and Horwitz, S.M., 2013. Understanding the components of quality improvement collaboratives: a systematic literature review. The Milbank Quarterly, 91(2), pp.354-394.
Nicholas, J.M. and Steyn, H., 2017. Project management for engineering, business and technology. Routledge.
Oakland, J.S., 2014. Total quality management and operational excellence: text with cases. Routledge.
Okongwu, U., Morimoto, R. and Lauras, M., 2013. The maturity of supply chain sustainability disclosure from a continuous improvement perspective. International Journal of Productivity and Performance Management, 62(8), pp.827-855.
Owen, M., 2013. SPC and continuous improvement. Springer Science & Business Media.
Ross, J.E., 2017. Total quality management: Text, cases, and readings. Routledge.
Sahno, J., Shevtshenko, E., Karaulova, T. and Tahera, K., 2015. Framework for continuous improvement of production processes. Engineering Economics, 26(2), pp.169-180.
Schwalbe, K., 2015. Information technology project management. Cengage Learning.
Singh, J. and Singh, H., 2015. Continuous improvement philosophy–literature review and directions. Benchmarking: An International Journal, 22(1), pp.75-119.
Swartling, D. and Poksinska, B., 2013. Management initiation of continuous improvement from a motivational perspective. Journal of Applied Economics and Business Research, 3(2), pp.81-94.
von Thiele Schwarz, U., Augustsson, H., Hasson, H. and Stenfors-Hayes, T., 2015. Promoting employee health by integrating health protection, health promotion, and continuous improvement: a longitudinal quasi-experimental intervention study. Journal of Occupational and Environmental medicine, 57(2), pp.217-225.
Walker, A., 2015. Project management in construction. John Wiley & Sons.

Free Membership to World’s Largest Sample Bank

To View this & another 50000+ free samples. Please put
your valid email id.

E-mail

Yes, alert me for offers and important updates

Submit 

Download Sample Now

Earn back the money you have spent on the downloaded sample by uploading a unique assignment/study material/research material you have. After we assess the authenticity of the uploaded content, you will get 100% money back in your wallet within 7 days.

UploadUnique Document

DocumentUnder Evaluation

Get Moneyinto Your Wallet

Total 14 pages

PAY 9 USD TO DOWNLOAD

*The content must not be available online or in our existing Database to qualify as
unique.

Cite This Work
To export a reference to this article please select a referencing stye below:

APA
MLA
Harvard
OSCOLA
Vancouver

My Assignment Help. (2019). Process For Monitoring And Control Of A Project. Retrieved from https://myassignmenthelp.com/free-samples/ecm28emd-process-for-monitoring-and-control-of-a-project.

“Process For Monitoring And Control Of A Project.” My Assignment Help, 2019, https://myassignmenthelp.com/free-samples/ecm28emd-process-for-monitoring-and-control-of-a-project.

My Assignment Help (2019) Process For Monitoring And Control Of A Project [Online]. Available from: https://myassignmenthelp.com/free-samples/ecm28emd-process-for-monitoring-and-control-of-a-project[Accessed 19 December 2021].

My Assignment Help. ‘Process For Monitoring And Control Of A Project’ (My Assignment Help, 2019) accessed 19 December 2021.

My Assignment Help. Process For Monitoring And Control Of A Project [Internet]. My Assignment Help. 2019 [cited 19 December 2021]. Available from: https://myassignmenthelp.com/free-samples/ecm28emd-process-for-monitoring-and-control-of-a-project.

×
.close{position: absolute;right: 5px;z-index: 999;opacity: 1;color: #ff8b00;}

×

Thank you for your interest
The respective sample has been mail to your register email id

×

CONGRATS!
$20 Credited
successfully in your wallet.
* $5 to be used on order value more than $50. Valid for
only 1
month.

Account created successfully!
We have sent login details on your registered email.

User:

Password:

Are you looking for customised essay paper writing service? Hire us for comprehensive solutions for your paper. We will help you with a plethora of interesting essay topics to write about. No matter if you need help with reflective essays or compare contrast essays, MyAssignmenthelp.com shall always assist you with the best solutions on time. Even if you are dealing with a challenging essay, read through our 500-word essay examples for helpful insights and idea. If you are bothered whether the essay solutions will be original, then stay assured of the fact that our experts use advanced plagiarism checker. This helps them to produce well-knit essays with zero traces of plagiarism.

Latest Project Management Samples

div#loaddata .card img {max-width: 100%;
}

SBM 1201 Project Scope, Time And Cost Management
Download :
0 | Pages :
12

Course Code: SBM1201
University: Asia Pacific International College

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answer:
Introduction
This project plan deals with the development of a fuel-efficient HHO Generator. The HHO fuel cells may appear to provide high fuel efficiency to the users. Nevertheless, there are a few confinements and focuses to be seen, as given beneath. This is to clear up that there is NO 100% substitution of petroleum derivative by including HHO cell. HHO gas is otherwise called Brown Gas, yet this is to illuminate that HHO gas is n…
Read
More
Tags:
Australia Footscray Management organisational behviour University of New South Wales Masters in Business Administration 

HS2061 Information Systems Project Management
Download :
0 | Pages :
9

Course Code: HS2061
University: Holmes Institute

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answer:
Case Overview:
The project owner of the Signed, sealed, delivered courier service is facing the problems of managing order of couriers in the synchronised manner. The project manager is incapable of managing central warehouse for the dispatching of products. The important information can be lost with the passage of time. The inventory management of the warehouse is the major concern for the owner of the company. He is looking forward …
Read
More

OPS 935 Project Management
Download :
0 | Pages :
11

Course Code: OPS935
University: University Of Wollongong

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answer:
Introduction
This essay explores the impacts of digital technologies on project management. It explores how adoption of digital technologies by companies for managing their project have affected their, project managers, human resource, business processes, timelines, deliverables, and practices  of risk management, people management and quality management.
Impact of Digital technologies on Project Management Practices
Digital te…
Read
More
Tags:
Australia Saint Kilda Management International Management University of New South Wales Masters in Business Administration 

ITC505 ICT Project Management
Download :
0 | Pages :
10

Course Code: ITC505
University: Charles Sturt University

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answers
Case Study- Social Media Research Center
Task-1: Project Charter
Project Objectives
The main objective of the project is to develop a web-based system within the organization “Social Media research Center”. It is analyzed that the Social Media research center wants to develop the web based system in order to connect people with the organization for promoting its research center. The web-based system that is developed conta…
Read
More
Tags:
Australia Alfredton Management IT Network Security  University of New South Wales Masters in Business Administration 

ITC505 ICT Project Management
Download :
0 | Pages :
7

Course Code: ITC505
University: Charles Sturt University

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answers
Part One- Project Name / Team / Description
Project Name:
RALS Solution
Team Name:
Consultants for RALS
Project Description:
RALS organizes show for the farmers and other related small business persons to display their latest technology equipment for betterment in the field of agriculture and crop production. The show has different types of stalls and other facilities for which many volunteers …
Read
More

Next

Need an essay written specifically to meet your requirements?

Choose skilled experts on your subject and get an original paper within your deadline

156 experts online

Your time is important. Let us write you an essay from scratch

Tips and Tricks from our Blog

11174 Introduction To Management

Free Samples 11174 Introduction To Management .cms-body-content table{width:100%!important;} #subhidecontent{ position: relative; overflow-x: auto; width: 100%;} 11174 Introduction

Read More »