123essaywriting

Emergency For Cholera Outbreak In Yemen

Academic Anxiety?

Get an original paper within hours and nail the task

156 experts online

Free Samples

Emergency For Cholera Outbreak In Yemen

.cms-body-content table{width:100%!important;} #subhidecontent{ position: relative;
overflow-x: auto;
width: 100%;}

Emergency For Cholera Outbreak In Yemen

0 Download16 Pages / 3,848 Words

Question:
Discuss about the Emergency Response for Cholera outbreak in Yemen.
 
 
Answer:
Introduction

In recent times, Yemen has faced one of the most severe cholera epidemics in the world. After coming into control in some time, the outbreak again resurged claiming the lives of a huge number of people and affect the health of few million people of the country. As a result, a project was authorized to provide emergency medical response to the cholera affected areas. The project based on setting up health camps, sending medical staff delegates in the regions to treat the patients and others. In addition to the appointment of medical stuffs, the project required a constant supply of medicines and medical equipments so that the medical staffs and nurses could be able to treat the patients and provide them with sufficient dosage of vaccination and medicines. Due to the large scale of the outbreak, the medicine supplies in the country was completely exhausted and hence, the medicines and vaccines were needed to be imported from other countries that resulted in the increase of the project costs and overall time.
In this report, a risk management plan has been developed based on the risks associated with the emergency response project.
Risk Management: Background of the Chosen Project
The chosen project is based on emergency response for Cholera outbreak in Yemen that took place within the period of May to October 2017. In the last quarter of 2016, a massive cholera outbreak took place in Yemen that reached an alarming level during April-May. As per an overall WHO estimated, nearly 900,000 people were affected with cholera with further rise in the value was projected for the next few weeks. The huge outbreak also claimed a large number of lives with almost 1% of the affected people reached fatality due to lack of timely and proper treatment of cholera. The outbreak was not limited to a single area – it spread over more than 150 districts of the country that were included in 16 Governorates of the country. While the cholera slowly came under control during March-April 2017, a resurgence of the cholera occurred in late April 2017 that claimed even more lives than the previous outbreak. The fatality rate also increased significantly to 1.6% of all the affected people and the cholera spread over an even bigger area – 180 districts in 18 Governorates.
In order to bring the cholera under control and treat the infected people, an emergency response project was initiated by appointing a large number of human resources including helpers, physicians, nurses, logistics assistants and others. The main objective of the project was to move from place to place and provide immediate medications to the affected people in the area. In addition to the healthcare support staffs, the medications and medical equipments were also needed to be carried from place to place in the areas of the outbreak. However, when the healthcare staffs were carried from place to place, it was needed to be ensured that the staffs are healthy and do not catch cholera during the treatment processes. Hence, sufficient amount of medical protection was to be provided to the patients as well as the healthcare staffs sent there for treatment of cholera. The project also required regular supply of medicines and medical equipments so that the physicians could be able to treat the patients and provide them with sufficient dosage of vaccination and medicines. Due to the large scale of the outbreak, the medicine supplies in the country was completely exhausted and hence, the medicines and vaccines were to be imported from other countries that resulted in the increase of the project costs and overall time. The project also required setting up field hospitals and health camps where the cholera struck most severely. The staffs in these camps did not need to move from place to place for providing services. Medicines, food and water had to be supplied from outside as the existing water sources were contaminated with cholera bacteria. The emergency response drive was continued till October 2017 when the outbreak slowly came within control and there were ample supply of cholera vaccine in the country.
 
Identification of Associated Risks
Due to the severity of the case and the epidemic situation of the country, there are a huge number of risks associated with the project. These risks are discussed as follows.
Health Risk – By far the most serious risk associated with the project is the health risk of the support and medical staff. Cholera is one of the most contagious diseases and hence, in spite of taking suitable amount of precautions and medications, the disease can easily spread from the patients to the physicians. This risk is further aggravated by the fact that it has taken the form of an epidemic and can easily spread on the healthcare staffs. Other support staffs like logistics assistants, health camp managers and others may also catch the disease easily. If the healthcare staffs are affected by the disease, the project cannot be continued further and emergency evacuation will be required for the healthcare and support staffs.
Supplies – Another major risk associated with the project includes the supply of food and medicines for patients as well as the medical staffs. While the Government is entitled to provide safe food and water to the common people, the food and water for the medical staffs and medicines for the patients are to be delivered from outside. Due to extensive nature of the epidemic, all the cholera vaccines are used up and most of the water sources are contaminated with the cholera bacteria. Any person coming in contact with these water sources can easily catch cholera. Hence, the medical staffs are strictly banned from eating local food and coming in contact with the local water. Their food and water are to be delivered through supply vans that travel from place to place for delivery in the health camps. During the delivery as well, the food, water and medicines can get contaminated and hence, extra-precautions like anti-germ delivery vaults, disinfectants and hand sanitizers are to be used to prevent contamination during delivery.
Budget – Budget is one of the major risks associated with the project. Due to the nature and scale of the project, no proper budget can be estimated accurately. The treatment processes depend on the extent of the disease in the patients, number of patients in the area, availability of the medicines and others. Due to the repeated recurrence of the disease in Yemen within a period of few months, all the stocks of medicines and vaccines are completely exhausted and hence, it is needed to import the required medicines from other countries. As a result of the epidemic, the prices of the medicines and vaccines have also sky-rocketed and this solely makes a huge negative impact on the project itself.
Inaccessibility – Another risk associated with the project is the inaccessibility of certain cholera affected areas of the country. Some of the extreme rural areas of Yemen are affected by cholera and the medical staffs depend on the land transport to reach these places and deliver healthcare measures. Furthermore, there will be also significant inconvenience of delivery of food, water and medicines in these areas that may delay the treatment processes of the affected people.
Dumping of Dead Bodies – Due to the outbreak of cholera, many people have already died and some more people are expected to die in the near future as well. However, in the rural areas, the dead bodies are simply dumped anywhere near water sources and other locations from where the cholera spreads as well. Hence, the medical staffs need to ensure the bodies are dumped at a suitable place that is far from water or food sources in order to avoid further contamination.
Outrage from Local People – This is a possible risk that might be faced from the medical and healthcare staffs especially in the rural areas. Due to continuous infections of cholera without sufficient treatment and prompt healthcare services provided by the governments resulting in deaths of the patients, the local people may turn hostile against the healthcare staffs when they arrive at the sites for providing treatment. It is needed ensure that the local people are calmed down and treatment is provided to the patients as fast as possible.
 
Risk Evaluation and Risk Ranking
The risk evaluation is done for this project using what-if analysis as follows.

Division: Yemen Healthcare Division

Description of Operation: Emergency Response to Cholera Affected Areas

By: PLEASE FILL
Date: May 2017-October 2017
 

What if?

Answer

Probability

Consequences

Recommendations

 
The healthcare staffs and nurses catch cholera during treatment
 
 

The affected staffs will have to be immediately evacuated from the area for treatment

9

8

Some additional medical staffs are to be kept as back up and sent to the sites in place of the affected staffs.

Contamination occurs during delivering food, water and medicine packets

All the packets should be tested before receiving delivery, in case there are signs of contamination, they should dumped away far from the site

7

8

Sanitizers, hand gloves, anti-contamination vaults, disinfectants and others are to be used by the delivery staffs

The project is out of funds due to complete exhaustion of budget

Request to be sent to higher authority for additional funding or leave the camps if the requests are not granted

10

9

The project should not depend upon a fixed budget value; the periodic increases and additional expenses are to be considered

Some epidemic affected areas are inaccessible by regular transport

Use drones for supply of med kits and food, use air transport

6

7

All areas should be surveyed for accessibility before allocating healthcare staffs

Dead bodies are dumped near camp locations and contamination occurs from those

Help the local people to dump the bodies far away from residential area

8

9

Dig a graveyard far from the residential area

Local people show hostile behavior towards healthcare staff

Raise awareness regarding habits that cause the spread of cholera and the effectiveness of the vaccines against cholera

7

8

Provide ample food, water and medicine to the people living in the affected areas

 
 
Mitigation Strategies and Contingency Plans
The mitigation strategies and contingency plans are determined using risk register matrix as follows.

Risk Name

Chance of Occurrence

Effect on Project

Mitigation Strategy

Contingency Plan

Contagion

Extreme

Very High

Avoid direct touch with the patients, avoid drinking local water and eating local food

Use sanitizers, gloves, disinfectants and others

Contamination

Extreme

Extreme

Avoid holding local food or water during delivery of the medicines

Use sanitizers, gloves, disinfectants and others

Budget

Very High

Very High

Avoid too much additional costs

Send request to government to provide additional funding

Schedule

Medium

Medium

Follow the schedule as provided

Prepare a feasible schedule for the health camps

Accessibility

High

Medium

Survey the areas before setting up camp

Deliver the medicines, food and water using drones

Dead Body Dumping

High

High

Help the local people to dump the bodies far away from residential area

Petition to government for creating a graveyard far from the living areas

Hostile Behavior

Medium

High

Raise awareness regarding habits that cause the spread of cholera and the effectiveness of the vaccines against cholera

Provide ample food, water and medicine to the people living in the affected areas

Lack of Treatment Facility

High

Very High

Set up medical camps using available facilities

Request government to provide better temporary facilities

No Effect from Provided Medicines

Medium

Extreme

Try new medicines

Import other similar medicines for treatment

Insufficient Supply of Medicine

Very High

Very High

Ask government to provide more medicines

Contact private agencies to provide medicines

 
 
Risk Monitoring and Control Plans
For the risk monitoring and control plan, an estimated time schedule has been prepared as shown in the following table.

Task Name

Duration

Start

Finish

Risk Management and Control

233 days

Mon 01-05-17

Wed 21-03-18

   Project Initiation

17 days

Mon 01-05-17

Tue 23-05-17

      Initial Discussions

1 day

Mon 01-05-17

Mon 01-05-17

      Initial Planning for Project

4 days

Tue 02-05-17

Fri 05-05-17

      Preparation of the Proposal Document

2 days

Mon 08-05-17

Tue 09-05-17

      Sending a copy of proposal documents to government

2 days

Wed 10-05-17

Thu 11-05-17

      Getting Feedbacks from Employees

2 days

Fri 12-05-17

Mon 15-05-17

      Selection of Health Camp Sites

1 day

Tue 16-05-17

Tue 16-05-17

      Getting Approval from Government

5 days

Wed 17-05-17

Tue 23-05-17

      Finalization of the Project

0 days

Tue 23-05-17

Tue 23-05-17

   Project Preparations

13 days

Wed 24-05-17

Fri 09-06-17

      Survey of all Cholera Affected Areas

4 days

Wed 24-05-17

Mon 29-05-17

      Risk Assessment

5 days

Tue 30-05-17

Mon 05-06-17

      Prepare Risk Register Matrix

2 days

Tue 06-06-17

Wed 07-06-17

      Preparation of Risk Management Plan

1 day

Thu 08-06-17

Thu 08-06-17

      Preparation of Final Plan

1 day

Fri 09-06-17

Fri 09-06-17

      Proceed for Execution

0 days

Fri 09-06-17

Fri 09-06-17

   Project Execution

201 days

Mon 12-06-17

Mon 19-03-18

      Procurement of Initial Budget from Government

10 days

Mon 12-06-17

Fri 23-06-17

      Purchase of Medical Equipments and Medicines

10 days

Mon 26-06-17

Fri 07-07-17

      Gather Vehicles for Relocating to Camp Locations

5 days

Mon 10-07-17

Fri 14-07-17

      Set Up Camps

10 days

Mon 17-07-17

Fri 28-07-17

      Take Risk Management Measures

15 days

Mon 31-07-17

Fri 18-08-17

      Start Providing Healthcare Services

30 days

Mon 21-08-17

Fri 29-09-17

      Providing food and water

15 days

Mon 02-10-17

Fri 20-10-17

      Provide medicines

15 days

Mon 23-10-17

Fri 10-11-17

      Prevent Contamination of Water

10 days

Mon 13-11-17

Fri 24-11-17

      Take Suitable Safety Measures

15 days

Mon 27-11-17

Fri 15-12-17

      Update Reports to Government

10 days

Mon 18-12-17

Fri 29-12-17

      Study on Progress of the Healthcare

10 days

Mon 01-01-18

Fri 12-01-18

      Send Requests for More Food and Medicine

2 days

Mon 15-01-18

Tue 16-01-18

      Continue Treatment

5 days

Wed 17-01-18

Tue 23-01-18

      Spread Disinfectant

5 days

Wed 24-01-18

Tue 30-01-18

      Receive additional funding

5 days

Wed 31-01-18

Tue 06-02-18

      Receive more medicines

5 days

Wed 07-02-18

Tue 13-02-18

      Relocate Staffs

10 days

Wed 14-02-18

Tue 27-02-18

      Evacuate ill staffs

2 days

Wed 28-02-18

Thu 01-03-18

      Check reduction of contamination levels

10 days

Fri 02-03-18

Thu 15-03-18

      Check on healths of patients

2 days

Fri 16-03-18

Mon 19-03-18

      Return the staffs

0 days

Mon 19-03-18

Mon 19-03-18

   Project Closing

2 days

Tue 20-03-18

Wed 21-03-18

      Post Project Review

1 day

Tue 20-03-18

Tue 20-03-18

      Survey in the Selected Areas

1 day

Wed 21-03-18

Wed 21-03-18

      Stakeholder Sign Off

0 days

Wed 21-03-18

Wed 21-03-18

The costs are estimated based on the following resource usages.

Resource Name

Type

Max. Units

Std. Rate

Ovt. Rate

Cost/Use

Accrue At

Base Calendar

Project Manager

Work

100%

$250.00/hr

$0.00/hr

$0.00

Prorated

Standard

Medical Supervisor

Work

100%

$175.00/hr

$0.00/hr

$0.00

Prorated

Standard

Project Planner

Work

100%

$150.00/hr

$0.00/hr

$0.00

Prorated

Standard

Logistics Manager

Work

100%

$175.00/hr

$0.00/hr

$0.00

Prorated

Standard

Finance Manager

Work

100%

$125.00/hr

$0.00/hr

$0.00

Prorated

Standard

Local Guide

Work

100%

$65.00/hr

$0.00/hr

$0.00

Prorated

Standard

Support Staff

Work

100%

$600.00/hr

$0.00/hr

$0.00

Prorated

Standard

Food

Material

 

$75,000.00

 

$0.00

Prorated

 

Water

Material

 

$15,000.00

 

$0.00

Prorated

 

Medicines

Material

 

$12,000.00

 

$0.00

Prorated

 

Medical Equipments

Material

 

$20,000.00

 

$0.00

Prorated

 

Camp Setup Costs

Material

 

$10,000.00

 

$0.00

Prorated

 

Other Costs

Material

 

$5,000.00

 

$0.00

Prorated

 

Additionally, the total costs for the risk management process will incur costs as shown in the following table.

Task Name

Resource Names

Cost

Risk Management and Control

 

$905,800.00

   Project Initiation

 

$57,600.00

      Initial Discussions

Project Manager, Project Planner

$3,200.00

      Initial Planning for Project

Project Manager, Medical Supervisor

$13,600.00

      Preparation of the Proposal Document

Project Manager, Medical Supervisor

$6,800.00

      Sending a copy of proposal documents to government

Project Manager, Medical Supervisor

$6,800.00

      Getting Feedbacks from Employees

Project Manager, Medical Supervisor

$6,800.00

      Selection of Health Camp Sites

Project Manager, Medical Supervisor

$3,400.00

      Getting Approval from Government

Project Manager, Medical Supervisor

$17,000.00

      Finalization of the Project

 

$0.00

   Project Preparations

 

$24,200.00

      Survey of all Cholera Affected Areas

Medical Supervisor

$5,600.00

      Risk Assessment

Project Manager

$10,000.00

      Prepare Risk Register Matrix

Project Manager, Project Planner

$6,400.00

      Preparation of Risk Management Plan

Finance Manager

$1,000.00

      Preparation of Final Plan

Project Planner

$1,200.00

      Proceed for Execution

 

$0.00

   Project Execution

 

$820,600.00

      Procurement of Initial Budget from Government

Finance Manager

$10,000.00

      Purchase of Medical Equipments and Medicines

Finance Manager

$10,000.00

      Gather Vehicles for Relocating to Camp Locations

Logistics Manager, Medical Supervisor, Project Planner

$20,000.00

      Set Up Camps

Logistics Manager, Medical Supervisor, Project Planner

$40,000.00

      Take Risk Management Measures

Logistics Manager, Medical Supervisor, Project Planner

$60,000.00

      Start Providing Healthcare Services

Logistics Manager, Medical Supervisor, Project Planner

$120,000.00

      Providing food and water

Project Planner, Logistics Manager, Medical Supervisor

$60,000.00

      Provide medicines

Project Planner, Logistics Manager, Medical Supervisor

$60,000.00

      Prevent Contamination of Water

Project Planner, Logistics Manager, Medical Supervisor

$40,000.00

      Take Suitable Safety Measures

Project Planner, Logistics Manager, Medical Supervisor

$60,000.00

      Update Reports to Government

Project Planner, Logistics Manager, Medical Supervisor

$40,000.00

      Study on Progress of the Healthcare

Logistics Manager, Medical Supervisor, Project Planner

$40,000.00

      Send Requests for More Food and Medicine

Project Planner, Logistics Manager,Medical Supervisor

$8,000.00

      Continue Treatment

Project Planner, Logistics Manager, Medical Supervisor

$20,000.00

      Spread Disinfectant

Project Planner, Logistics Manager, Medical Supervisor

$20,000.00

      Receive additional funding

Logistics Manager, Medical Supervisor, Project Planner

$20,000.00

      Receive more medicines

Project Planner, Logistics Manager, Medical Supervisor

$20,000.00

      Relocate Staffs

Medical Supervisor, Logistics Manager, Project Planner

$40,000.00

      Evacuate ill staffs

Logistics Manager, Medical Supervisor, Project Planner

$8,000.00

      Check reduction of contamination levels

Logistics Manager, Medical Supervisor, Project Planner

$40,000.00

      Check on healths of patients

Support Staff, Food[1]

$84,600.00

      Return the staffs

Finance Manager, Support Staff, Project Manager, Project Planner, Local Guide, Logistics Manager, Medical Supervisor

$0.00

   Project Closing

 

$3,400.00

      Post Project Review

Project Manager

$2,000.00

      Survey in the Selected Areas

Medical Supervisor

$1,400.00

      Stakeholder Sign Off

Finance Manager, Support Staff, Project Manager, Project Planner, Local Guide, Logistics Manager, Medical Supervisor

$0.00

Conclusion
Finally, it can be concluded that there are a number of risks and issues that are associated with the project. While this project is based on emergency response to the cholera affected areas in Yemen, the most serious risk associated with the project is the health risk of the support and medical staff. In addition to the existing medical staffs, the support staffs like logistics assistants, health camp managers and others may also catch the disease easily due to extreme contagious nature of the disease. The main problem is that if the healthcare staffs are affected by the disease, the project cannot be continued further and emergency evacuation will be required for the healthcare and support staffs. Another major risk identified for the project includes lack of the supply of food and medicines for patients as well as the medical staffs. Again, due to the extensive nature of the epidemic, all the cholera vaccines are used up and most of the water sources are contaminated with the cholera bacteria. This also spreads disease among the medical staffs. Finally, budget is one of the major risks discussed in this report and also associated with the project. Due to the nature and scale of the project, no proper budget can be estimated accurately. The treatment processes depend on the extent of the disease in the patients, number of patients in the area, availability of the medicines and others and for these cases, the budget can significantly vary. Hence, all plans are to be made before proceeding with the project.
 
Bibliography
Binder, J. (2016). Global project management: communication, collaboration and management across borders. Routledge.
Boud, D., Cohen, R., & Sampson, J. (Eds.). (2014). Peer learning in higher education: Learning from and with each other. Routledge.
Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management. Project Management Institute.
Harrison, F., & Lock, D. (2017). Advanced project management: a structured approach. Routledge.
Heagney, J. (2016). Fundamentals of project management. AMACOM Div American Mgmt Assn.
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Schwalbe, K. (2015). Information technology project management. Cengage Learning.
Turner, R. (2016). Gower handbook of project management. Routledge.
Verzuh, E. (2015). The fast forward MBA in project management. John Wiley & Sons.
Walker, A. (2015). Project management in construction. John Wiley & Sons.

Free Membership to World’s Largest Sample Bank

To View this & another 50000+ free samples. Please put
your valid email id.

E-mail

Yes, alert me for offers and important updates

Submit 

Download Sample Now

Earn back the money you have spent on the downloaded sample by uploading a unique assignment/study material/research material you have. After we assess the authenticity of the uploaded content, you will get 100% money back in your wallet within 7 days.

UploadUnique Document

DocumentUnder Evaluation

Get Moneyinto Your Wallet

Total 16 pages

PAY 10 USD TO DOWNLOAD

*The content must not be available online or in our existing Database to qualify as
unique.

Cite This Work
To export a reference to this article please select a referencing stye below:

APA
MLA
Harvard
OSCOLA
Vancouver

My Assignment Help. (2019). Emergency For Cholera Outbreak In Yemen. Retrieved from https://myassignmenthelp.com/free-samples/emergency-for-cholera-outbreak-in-yemen.

“Emergency For Cholera Outbreak In Yemen.” My Assignment Help, 2019, https://myassignmenthelp.com/free-samples/emergency-for-cholera-outbreak-in-yemen.

My Assignment Help (2019) Emergency For Cholera Outbreak In Yemen [Online]. Available from: https://myassignmenthelp.com/free-samples/emergency-for-cholera-outbreak-in-yemen[Accessed 19 December 2021].

My Assignment Help. ‘Emergency For Cholera Outbreak In Yemen’ (My Assignment Help, 2019) accessed 19 December 2021.

My Assignment Help. Emergency For Cholera Outbreak In Yemen [Internet]. My Assignment Help. 2019 [cited 19 December 2021]. Available from: https://myassignmenthelp.com/free-samples/emergency-for-cholera-outbreak-in-yemen.

×
.close{position: absolute;right: 5px;z-index: 999;opacity: 1;color: #ff8b00;}

×

Thank you for your interest
The respective sample has been mail to your register email id

×

CONGRATS!
$20 Credited
successfully in your wallet.
* $5 to be used on order value more than $50. Valid for
only 1
month.

Account created successfully!
We have sent login details on your registered email.

User:

Password:

If you the essence of paraphrasing, then it would help you to avoid plagiarism issues in your assignments. However, if you are not aware of this particular aspect, it is ideal that you seek the help of the experts at MyAssignmnethelp.com. Years of experience provide our experts with an edge over novice writers to avoid plagiarism. Our experts resort to powerful paraphrase tools to provide you with genuine content. Thus, you receive online paraphrasing assistance without having to worry about the authenticity of various paraphrasing tools available online.

Latest Project Management Samples

div#loaddata .card img {max-width: 100%;
}

SBM 1201 Project Scope, Time And Cost Management
Download :
0 | Pages :
12

Course Code: SBM1201
University: Asia Pacific International College

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answer:
Introduction
This project plan deals with the development of a fuel-efficient HHO Generator. The HHO fuel cells may appear to provide high fuel efficiency to the users. Nevertheless, there are a few confinements and focuses to be seen, as given beneath. This is to clear up that there is NO 100% substitution of petroleum derivative by including HHO cell. HHO gas is otherwise called Brown Gas, yet this is to illuminate that HHO gas is n…
Read
More
Tags:
Australia Footscray Management organisational behviour University of New South Wales Masters in Business Administration 

HS2061 Information Systems Project Management
Download :
0 | Pages :
9

Course Code: HS2061
University: Holmes Institute

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answer:
Case Overview:
The project owner of the Signed, sealed, delivered courier service is facing the problems of managing order of couriers in the synchronised manner. The project manager is incapable of managing central warehouse for the dispatching of products. The important information can be lost with the passage of time. The inventory management of the warehouse is the major concern for the owner of the company. He is looking forward …
Read
More

OPS 935 Project Management
Download :
0 | Pages :
11

Course Code: OPS935
University: University Of Wollongong

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answer:
Introduction
This essay explores the impacts of digital technologies on project management. It explores how adoption of digital technologies by companies for managing their project have affected their, project managers, human resource, business processes, timelines, deliverables, and practices  of risk management, people management and quality management.
Impact of Digital technologies on Project Management Practices
Digital te…
Read
More
Tags:
Australia Saint Kilda Management International Management University of New South Wales Masters in Business Administration 

ITC505 ICT Project Management
Download :
0 | Pages :
10

Course Code: ITC505
University: Charles Sturt University

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answers
Case Study- Social Media Research Center
Task-1: Project Charter
Project Objectives
The main objective of the project is to develop a web-based system within the organization “Social Media research Center”. It is analyzed that the Social Media research center wants to develop the web based system in order to connect people with the organization for promoting its research center. The web-based system that is developed conta…
Read
More
Tags:
Australia Alfredton Management IT Network Security  University of New South Wales Masters in Business Administration 

ITC505 ICT Project Management
Download :
0 | Pages :
7

Course Code: ITC505
University: Charles Sturt University

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answers
Part One- Project Name / Team / Description
Project Name:
RALS Solution
Team Name:
Consultants for RALS
Project Description:
RALS organizes show for the farmers and other related small business persons to display their latest technology equipment for betterment in the field of agriculture and crop production. The show has different types of stalls and other facilities for which many volunteers …
Read
More

Next

Need an essay written specifically to meet your requirements?

Choose skilled experts on your subject and get an original paper within your deadline

156 experts online

Your time is important. Let us write you an essay from scratch

Tips and Tricks from our Blog

11174 Introduction To Management

Free Samples 11174 Introduction To Management .cms-body-content table{width:100%!important;} #subhidecontent{ position: relative; overflow-x: auto; width: 100%;} 11174 Introduction

Read More »