123essaywriting

ITC505 ICT Project Management 2

Academic Anxiety?

Get an original paper within hours and nail the task

156 experts online

Free Samples

ITC505 ICT Project Management 2

.cms-body-content table{width:100%!important;} #subhidecontent{ position: relative;
overflow-x: auto;
width: 100%;}

ITC505 ICT Project Management 2

0 Download10 Pages / 2,371 Words

Course Code: ITC505
University: Charles Sturt University

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Question:

You are to prepare, based on the Virtucon/ Globex scenario.
You are required to develop a charter for the Project including:
Part One:
MOV – Measurable Organisational Value
(This is the goal of the project and is utilised to define the value that your team project will bring to your client)

Identify the desired area of impact – Rank the following areas in terms of importance: Strategy / Customer / Financial / Operational / Social

With reference to your project, identify one or two of the following types of value:

Better – is improving quality important to your client?

Faster – does your client want to increase efficiency?

Cheaper – is cutting costs important?

Do more – does your client want to continue its growth?

Develop an appropriate metric – this sets the target and expectation of all the stakeholders. It is important to determine a quantitative target that needs to be expressed as a metric in terms of an increase or decrease of money.

Determine the timeframe for achieving the MOV – ask yourselves, when do we want to achieve this target metric?

Part Two:
Define Scope and produce a Scope Management Plan
Define the scope of the project and detail how the scope will be managed.
Provide a list of Resources
Identify and detail the resources for the project using MS Project where appropriate, including:

People (and their roles), plus any extra personnel that is required for the project.

Technology – any hardware, network and softw are need to support the team and your client.

Facilities – where will most of the teamwork be situated?

Other – for example, travel, training etc.

Part Three:
Using MS Project, develop a schedule using a high-level Work Breakdown Structure (WBS). It should include:

 Milestones for each phase and deliverable

This will tell everyone associated with the project that the phase or deliverable was completed satisfactorily.

 Activities / Tasks

Define a set of activities/tasks that must be completed to produce each deliverable.

 Resource Assignments

Assign people and resources to each individual activities.

 Estimates for Each Activity / Task

Develop a time estimate for each task or activity to be completed.

 Project Budget

Develop a budget using the time and resources estimated for each task or activity
Part Four:
Project Risk Analysis and Plan

Document any assumptions you have made about the project

Using the Risk Identification Framework outlined in your text as a basis, identify five risks to the project – one for each of the five phases of the methodology.
Analyse these risks, assign a risk to an appropriate member, and describe a strategy for the management of each specific risk.

Part Five:
Quality Management Plan. It should include:

A short statement that reflects your team’s philosophy or objective for ensuring that you deliver a quality system to your client.

Develop and describe the following that your project team could implement to ensure quality: A set of verification activities A set of validation activities

Part Six:
Closure and Evaluation
Researching for the closure checklist and project evaluation

To prepare for this task, you will be required to provide an annotated bibliography.

Write an Annotated Bibliography for three (3) relevant texts or readings around project evaluation. The Annotated Bibliography is a critical examination of the most relevant, recent and scholarly research on the topic area that is not just a summary of the articles you have read.
You will submit this as an appendix to your project evaluation documentation.
Ensure that the AB submitted by you is your own work and has not been submitted elsewhere and comply with the University’s requirements for academic integrity.
Use the following resource to guide you around the research tools: http://student.csu.edu.au/__data/assets/pdf_file/0009/186444/annotate1.pdf http://libguides.csu.edu.au/itc

Develop a closure checklist that the project team will use to ensure that the project has been closed properly.
Develop a project evaluation –outline and discuss how your project’s MOV will be evaluated.

 
Answer:

Project Overview and Description
This project is mainly based on the development of a computer based system that is requested by Globex for assistance in the TAHS program. In this project, Virtucon will need to develop the proposed system that will have the following main features:
Student Details – The system will have entry and record feature for the student details who are enrolled in the TAHS program conducted by Globex.
Apprentice Tracking – The system will have a feature for tracking the apprentices who are enrolled within the TAHS program.
Skills Requirements – The system will also record the skills requirements for the placement in the industry.
Part One: MOV
Measurable Organisational Value
The goal of the project is to develop a computer based system that can be utilized for managing the TAHS (Training and Apprenticeship Program for High School Students) program proposed by Globex. The success of the project will be measured by the increase in the number of effective placements in agricultural equipment manufacturing sector.
 
Desired Area of Impact
In terms of importance, the areas are ranked as follows.

Areas

Ranking Justification

Strategy

The strategy is to enhance the TAHS program using computer based system

Operational

The computer based system will provide necessary features for the TAHS program.

Financial

Globex wants to minimize operational as well as project costs

Social

Globex wants to place more skilled students in the industry

Customer

There is no specific customer associated with this project

Project Value
From the given values, the two most important values that are essential for this project are Better and Do More. “Better” value refers to the improvement in the quality of recruitment in the manufacturing sector as the interested students will be trained and the best performing students will be placed in the industry once the academic session is complete (Kerzner & Kerzner, 2017). “Do More” value refers to the growth of the organization by recruiting efficient and trained employees in the manufacturing sector.
 
Appropriate Metric
It is expected that after the project, the organization will be able to reduce annual expenses by 20% as it will no longer need to train employees on frequent basis. Furthermore, with the placement of more efficient and trained employees, the annual productivity of the company in terms of profit is expected to rise by at least 30%.
Timeframe
The timeframe has been set for 6 months for achieving the Measurable Organisational Value after the project is completed. These six months have been taken for providing the students with sufficient time for undergoing the training process and getting ready for the placement. Within this period, the recruitment process will also be conducted in which the best students will be placed in the sector.
Summary of MOV
This project supports the effective training and placement of the students who are interested in joining the agricultural equipment manufacturing industry. The project will also be assisted by a computer based system that will help the students to understand the operations and the training process will also be faster and more efficient (Kundra & Sharma, 2015).
Part Two: Scope Management Plan
Scope is defined as a limitation or boundary within which a project must remain in order to be feasible (Schwalbe, 2015). The scope of this particular project is to develop a computer based system for assisting the TAHS program that will help the placement of the interested students in the manufacturing sector. The project will be supervised from time to time to ensure it does not move out of scope and suitable changes can also be implemented as per the requirements.
The list of resources is shown as follows.

Resource Category

Resource Name

Max. Units

Std. Rate

People

Project Manager

100%

$ 150.00/hr

Project Supervisor

100%

$ 110.00/hr

Finance Manager

100%

$ 125.00/hr

Technical Expert

100%

$ 95.00/hr

Project Team Members

100%

$ 165.00/hr

Technology

Hardware and Software Costs

 

$ 15,000.00

Development and Other Costs

 

$ 10,000.00

The facilities will be provided in a specific project camp and travel and accommodation costs will be provided to the project team members as per the expenses.
 
Part Three: Work Breakdown Structure
The entire duration of the project, resource allocation and estimated budget costs of the project are shown in the following table.

Task Name

Start

Finish

Resource Names

Cost

Development of Computer-Based System for Managing TAHS

Tue 2/5/19

Mon 7/8/19

 

$ 243,320.00

   Initiation phase

Tue 2/5/19

Tue 2/19/19

 

$ 22,480.00

      Requirement analysis of the project

Tue 2/5/19

Fri 2/8/19

Project Manager, Project Supervisor

$ 8,320.00

      Develop an initial plan for the computer based system

Mon 2/11/19

Fri 2/15/19

Project Manager, Project Supervisor

$ 10,400.00

      Analyze the feasibility of the project

Mon 2/18/19

Tue 2/19/19

Finance Manager, Project Supervisor

$ 3,760.00

      Milestone 1: Proceed with the Plan

Tue 2/19/19

Tue 2/19/19

 

$ 0.00

   Planning phase

Wed 2/20/19

Wed 3/6/19

 

$ 18,480.00

      Identification of Project Resource Requirements

Wed 2/20/19

Fri 2/22/19

Project Supervisor

$ 2,640.00

      Prepare Project Schedule and Budget

Mon 2/25/19

Tue 2/26/19

Finance Manager, Project Supervisor

$ 3,760.00

      Create Project Team

Wed 2/27/19

Wed 2/27/19

Project Manager

$ 1,200.00

      Develop Project Execution Plan

Thu 2/28/19

Mon 3/4/19

Project Supervisor, Project Team Members, Technical Expert

$ 8,880.00

      Allocate Budget and Resources for Project

Tue 3/5/19

Wed 3/6/19

Finance Manager

$ 2,000.00

      Milestone 2: Proceed to System Design

Wed 3/6/19

Wed 3/6/19

 

$ 0.00

   Design phase

Thu 3/7/19

Wed 4/17/19

 

$ 77,400.00

      Design the Computer Based System

Thu 3/7/19

Wed 3/20/19

Project Team Members, Technical Expert, Hardware and Software Costs[1]

$ 35,800.00

      Develop System Features

Thu 3/21/19

Wed 4/3/19

Project Team Members, Technical Expert

$ 20,800.00

      Coding and Design

Thu 4/4/19

Wed 4/17/19

Project Team Members, Technical Expert

$ 20,800.00

      Milestone 3: Completion of Design

Wed 4/17/19

Wed 4/17/19

 

$ 0.00

   Testing phase

Thu 4/18/19

Wed 5/1/19

 

$ 20,800.00

      White Box Testing

Thu 4/18/19

Fri 4/19/19

Project Team Members, Technical Expert

$ 4,160.00

      User-acceptance Testing

Mon 4/22/19

Tue 4/23/19

Project Team Members, Technical Expert

$ 4,160.00

      Performance Testing

Wed 4/24/19

Thu 4/25/19

Project Team Members, Technical Expert

$ 4,160.00

      Black Box Testing

Fri 4/26/19

Mon 4/29/19

Project Team Members, Technical Expert

$ 4,160.00

      System Performance Testing

Tue 4/30/19

Wed 5/1/19

Project Team Members, Technical Expert

$ 4,160.00

      Milestone 4: Testing Complete and Launch

Wed 5/1/19

Wed 5/1/19

 

$ 0.00

   Preparation for System Implementation

Thu 5/2/19

Fri 6/28/19

 

$ 87,360.00

      Enrollment of Interested Students

Thu 5/2/19

Wed 5/15/19

Project Manager, Project Supervisor

$ 20,800.00

      Analyze Training Requirements

Thu 5/16/19

Fri 5/17/19

Project Manager, Project Supervisor

$ 4,160.00

      Conduct Discussion Session with the Training Faculty

Mon 5/20/19

Tue 5/21/19

Project Manager, Project Supervisor

$ 4,160.00

      Set Up Training Rooms

Wed 5/22/19

Fri 5/24/19

Project Manager, Project Supervisor

$ 6,240.00

      Set Up Training Equipments

Mon 5/27/19

Tue 5/28/19

Project Manager, Project Supervisor

$ 4,160.00

      Set Up Training Schedule

Wed 5/29/19

Thu 5/30/19

Project Manager, Project Supervisor

$ 4,160.00

      Allocate Faculties to Training Modules

Fri 5/31/19

Mon 6/3/19

Project Manager, Project Supervisor

$ 4,160.00

      Conduct First Phase of Training

Tue 6/4/19

Mon 6/24/19

Project Manager, Project Supervisor

$ 31,200.00

      Assess Skills of the Students

Tue 6/25/19

Wed 6/26/19

Project Manager, Project Supervisor

$ 4,160.00

      Evaluate Training Results

Thu 6/27/19

Fri 6/28/19

Project Manager, Project Supervisor

$ 4,160.00

      Milestone 5: System Implementation Complete

Fri 6/28/19

Fri 6/28/19

 

$ 0.00

   Closing Phase

Mon 7/1/19

Mon 7/8/19

 

$ 16,800.00

      Review and Appraisal

Mon 7/1/19

Thu 7/4/19

Project Manager

$ 4,800.00

      Finish All Payments

Fri 7/5/19

Mon 7/8/19

Development and Other Costs[1], Finance Manager

$ 12,000.00

      Milestone 6: Stakeholder Sign Off

Mon 7/8/19

Mon 7/8/19

Finance Manager, Project Manager, Project Supervisor, Project Team Members, Technical Expert

$ 0.00

Part Four: Risk Analysis and Plan
Assumptions
The following assumptions have been made in the project.

The project will be completed within the given timeframe.
The estimated budget will be sufficient for the project.
The project benefits will be realized within 6 months of completion.

Risk Identification
The five risks identified for the project are as follows.

Time overshoot may lead to additional expenses in the project.
Budget overshoot can be a major risk if the estimation is not done properly.

Legal risks can occur if the placement process is not licensed and authorized by the relevant governing body.

Poor quality hardware may lead to the failure of the development of the system.
The students may not be ready to take part in the training system.

Risk Management Strategy
The risk management strategy for each of the identified risk is described as follows.

Appropriate project roadmap is to be developed along with the schedule that must be followed throughout the project.
Accurate estimation of budget should be done along with consideration of buffer budget.

Apply for training and placement licenses before proceeding with the project.

Procure hardware and other equipments from a reliable vendor.
Integrate the training program with the course modules gradually for the students.

 
Part Five: Quality Management Plan
The philosophy of the team is to ensure the project plan is closely followed and all the customer requirements are met before signing off.

Verification Activities

Validation Activities

Verify the feasibility of the project plan

Validate project proposal

Verify the availability of resources for project

Validate project charter

Verify the program requirements

Validate launch of system

Verify training and placement license

Validate project report

Part Six: Closure and Evaluation
Annotation 1: Binder, J. (2016). Global project management: communication, collaboration and management across borders. Routledge.
According to the authors, project evaluation is one of the most vital parts of a project. While the main part of the project is done through the execution phase, it is important to determine whether all requirements have been met and the project has been successfully completed. This process is done during the project evaluation phase where all the project progresses are checked and validated. Moreover, it is also checked whether all the project milestones have been successfully fulfilled before validating the completion of the project. The authors also emphasized that the project must be evaluated by the project manager with the assistance of a technical expert if necessary and the project manager will have the right to restart the project execution if the evaluation results show that all the requirements have not been met.
Annotation 2: Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
The authors have described several methods for conducting the evaluation process of the project. According to them, creating an evaluation checklist is an effective way of evaluating the outcomes of the project. The checklist will remind the project manager to identify all necessary aspects and requirements of the project. Another method suggested by the authors is periodic evaluation of the project that can be done in parallel with the execution of the project.
Annotation 3: Marchewka, J. T. (2014). Information technology project management. John Wiley & Sons.
As per the authors, generally project evaluation is followed by project closing. However, there are many project managers who rush to close the project in order to avoid budget and time overshoots and deliver the project to the client within time. The authors have warned against using this approach as skipping the evaluation process may lead to serious complications in the project outcome. The authors have emphasized that project evaluation is an integral part of any project and must not be skipped even if it requires some additional time or budget.
Closure Checklist
The closure checklist is developed as follows.

The system has been successfully developed and launched.
The faculty stuffs are well trained for the program.
The interested students are enrolled for the program.
All risks and issues have been successfully addressed.

Project Evaluation
The project’s MOV will be evaluated based on the quality of recruitments done after the program is completed (Marchewka, 2014). The new recruitments should be well trained in the program and will be able to integrate with the industry’s operational standards and requirements. A timeline has been set at 6 months for realizing the benefits after the first phase of the program.
 
References
Aga, D. A., Noorderhaven, N., & Vallejo, B. (2016). Transformational leadership and project success: The mediating role of team-building. International Journal of Project Management, 34(5), 806-818.
Binder, J. (2016). Global project management: communication, collaboration and management across borders. Routledge.
Burke, R., & Barron, S. (2014). Project management leadership: building creative teams. John Wiley & Sons.
Conforto, E. C., Salum, F., Amaral, D. C., da Silva, S. L., & de Almeida, L. F. M. (2014). Can agile project management be adopted by industries other than software development?. Project Management Journal, 45(3), 21-34.
Crawford, J. K. (2014). Project management maturity model. Auerbach Publications.
Harrison, F., & Lock, D. (2017). Advanced project management: a structured approach. Routledge.
Heldman, K. (2018). PMP: project management professional exam study guide. John Wiley & Sons.
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Kilibarda, G. D., Šobaji?, V. M., Beri?, I. M., & Jovanovi?, P. M. (2016). Software project management. Tehnika, 71(1), 145-152.
Kundra, T., & Sharma, A. (2015). Software project management. Int. J. Res.
Lee, M. R. (2016). Leading virtual project teams: Adapting leadership theories and communications techniques to 21st century organizations. Auerbach Publications.
Marchewka, J. T. (2014). Information technology project management. John Wiley & Sons.
Niazi, M., Mahmood, S., Alshayeb, M., Qureshi, A. M., Faisal, K., & Cerpa, N. (2016). Toward successful project management in global software development. International Journal of Project Management, 34(8), 1553-1567.
Ramazani, J., & Jergeas, G. (2015). Project managers and the journey from good to great: The benefits of investment in project management training and education. International Journal of Project Management, 33(1), 41-52.
Redick, A., Reyna, I., Schaffer, C., & Toomey, D. (2014). Four-factor model for effective project leadership competency. Journal of Information Technology and Economic Development, 5(1), 53.
Schwalbe, K. (2015). Information technology project management. Cengage Learning.

Free Membership to World’s Largest Sample Bank

To View this & another 50000+ free samples. Please put
your valid email id.

E-mail

Yes, alert me for offers and important updates

Submit 

Download Sample Now

Earn back the money you have spent on the downloaded sample by uploading a unique assignment/study material/research material you have. After we assess the authenticity of the uploaded content, you will get 100% money back in your wallet within 7 days.

UploadUnique Document

DocumentUnder Evaluation

Get Moneyinto Your Wallet

Total 10 pages

PAY 6 USD TO DOWNLOAD

*The content must not be available online or in our existing Database to qualify as
unique.

Cite This Work
To export a reference to this article please select a referencing stye below:

APA
MLA
Harvard
OSCOLA
Vancouver

My Assignment Help. (2020). ICT Project Management 2. Retrieved from https://myassignmenthelp.com/free-samples/itc505-ict-project-management-2.

“ICT Project Management 2.” My Assignment Help, 2020, https://myassignmenthelp.com/free-samples/itc505-ict-project-management-2.

My Assignment Help (2020) ICT Project Management 2 [Online]. Available from: https://myassignmenthelp.com/free-samples/itc505-ict-project-management-2[Accessed 19 December 2021].

My Assignment Help. ‘ICT Project Management 2’ (My Assignment Help, 2020) accessed 19 December 2021.

My Assignment Help. ICT Project Management 2 [Internet]. My Assignment Help. 2020 [cited 19 December 2021]. Available from: https://myassignmenthelp.com/free-samples/itc505-ict-project-management-2.

×
.close{position: absolute;right: 5px;z-index: 999;opacity: 1;color: #ff8b00;}

×

Thank you for your interest
The respective sample has been mail to your register email id

×

CONGRATS!
$20 Credited
successfully in your wallet.
* $5 to be used on order value more than $50. Valid for
only 1
month.

Account created successfully!
We have sent login details on your registered email.

User:

Password:

When you’re struggling with a complicated essay topic and wonder how to write an impeccable essay, MyAssignenthelp.com can provide all the assistance you need. Writing an engaging essay is a piece of cake for our writers, and they can help you boost your grades remarkably. We have also appointed efficient paper editors who ensure the quality of your essay papers remains the best. So, whenever you’re contemplating, “Who can write my essay for me?” we will be there with our services. You can avail or assistance for different types of essays. All in all, our site will provide the best essay writing service to help you stay ahead in your academic journey.

Latest Project Management Samples

div#loaddata .card img {max-width: 100%;
}

SBM 1201 Project Scope, Time And Cost Management
Download :
0 | Pages :
12

Course Code: SBM1201
University: Asia Pacific International College

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answer:
Introduction
This project plan deals with the development of a fuel-efficient HHO Generator. The HHO fuel cells may appear to provide high fuel efficiency to the users. Nevertheless, there are a few confinements and focuses to be seen, as given beneath. This is to clear up that there is NO 100% substitution of petroleum derivative by including HHO cell. HHO gas is otherwise called Brown Gas, yet this is to illuminate that HHO gas is n…
Read
More
Tags:
Australia Footscray Management organisational behviour University of New South Wales Masters in Business Administration 

HS2061 Information Systems Project Management
Download :
0 | Pages :
9

Course Code: HS2061
University: Holmes Institute

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answer:
Case Overview:
The project owner of the Signed, sealed, delivered courier service is facing the problems of managing order of couriers in the synchronised manner. The project manager is incapable of managing central warehouse for the dispatching of products. The important information can be lost with the passage of time. The inventory management of the warehouse is the major concern for the owner of the company. He is looking forward …
Read
More

OPS 935 Project Management
Download :
0 | Pages :
11

Course Code: OPS935
University: University Of Wollongong

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answer:
Introduction
This essay explores the impacts of digital technologies on project management. It explores how adoption of digital technologies by companies for managing their project have affected their, project managers, human resource, business processes, timelines, deliverables, and practices  of risk management, people management and quality management.
Impact of Digital technologies on Project Management Practices
Digital te…
Read
More
Tags:
Australia Saint Kilda Management International Management University of New South Wales Masters in Business Administration 

ITC505 ICT Project Management
Download :
0 | Pages :
10

Course Code: ITC505
University: Charles Sturt University

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answers
Case Study- Social Media Research Center
Task-1: Project Charter
Project Objectives
The main objective of the project is to develop a web-based system within the organization “Social Media research Center”. It is analyzed that the Social Media research center wants to develop the web based system in order to connect people with the organization for promoting its research center. The web-based system that is developed conta…
Read
More
Tags:
Australia Alfredton Management IT Network Security  University of New South Wales Masters in Business Administration 

ITC505 ICT Project Management
Download :
0 | Pages :
7

Course Code: ITC505
University: Charles Sturt University

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answers
Part One- Project Name / Team / Description
Project Name:
RALS Solution
Team Name:
Consultants for RALS
Project Description:
RALS organizes show for the farmers and other related small business persons to display their latest technology equipment for betterment in the field of agriculture and crop production. The show has different types of stalls and other facilities for which many volunteers …
Read
More

Next

Need an essay written specifically to meet your requirements?

Choose skilled experts on your subject and get an original paper within your deadline

156 experts online

Your time is important. Let us write you an essay from scratch

Tips and Tricks from our Blog

11174 Introduction To Management

Free Samples 11174 Introduction To Management .cms-body-content table{width:100%!important;} #subhidecontent{ position: relative; overflow-x: auto; width: 100%;} 11174 Introduction

Read More »