ITECH2250 IT Project Management Techniques 1
.cms-body-content table{width:100%!important;} #subhidecontent{ position: relative;
overflow-x: auto;
width: 100%;}
ITECH2250 IT Project Management Techniques 1
0 Download6 Pages / 1,500 Words
Course Code: ITECH2250
University: Federation University
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Question:
Background – Project Charter
During the starting of a project, a Project Charter can be an important artefact. After top management determineswhich project/s to pursue, it is important to then notify the organisation of the project/s about to commence. TheProject Charter can be used to formally recognize/authorise the project, provide a summary of the details of theproject and nominate/identify the project manager. This artefact can clearly indicate to the project team and allstakeholders, the project objectives, scope and vision and help to demonstrate the broad requirements andexpectations of the project.Ina project managed using traditional (predictive/planned) project managementmethodologies, the Charter would bea document of just a few pages (around 3), formally outlining the key objectives, schedule and stakeholders. In aproject managed using more adaptive or agile methodologies, the document would be of a similar size, butperhaps less prescriptive but with greater breadth and would reflect the different approach used. It would also bedisplayed in the project team room. Hybrid forms that borrow from the traditional and agile can also exist.You can obtain more information about a Project Charter from chapters 3 and 4 of the course text – Schwalbe, K.(2016). Information Technology Project Management (8th ed.). Boston, MA: Cengage Learning.Keep all of the above in mind as you read the following case study.Case Study: Soliloquy Publishing Ltd. – Streaming Media Player SystemYou work for Soliloquy Publishing Ltd., a publishing house specialising in the promotion and publishing (hardcopyand electronic) of authors. Originally the company specialised in drama only content and inparticular those withhigh dialogue content presented in soliloquies1. The company has expandedintomany other forms of publicationssince then including fiction and non-fiction offerings. The company now operates in all Australian states andterritories and has a staff of over 50 people. It has recently reviewed its business objectives, corporate andmanagement structure as well as its operational procedures. It has resulted in Soliloquy implementing newpractices and a mission statement to help direct and manage future growth. Its new mission statement is “dialogueand prose, poetry and facts, these are the matters on which Soliloquy acts” and Soliloquy has a dream to bethought of as the first stop location for sophisticated web-based arts products.
Its CEO, Tristan Bard sees great potential growth in the area of interactive promotion of their product. As a result ofa review by Tristan, a number of projects were proposed and a business case constructed for each. The projectwith the most promising opportunities and that most closely aligned project with the company’s goals andobjectives – grow revenues and profits by 5% year on year for the next five years, improve visibility (increasedsight visits by 50% after two years) and increase financial returns (exceed ROI of 10% after delivery of project) -proved to be the Streaming Media Player System (SMPS). A SMPS would provide an opportunity for the companyto replace their existing web-based static content delivery and open up new opportunities for promoting interactivecontent, loyalty schemes and repeat subscriber activity. In order for the SMPS to be a success, it needs supportfrom all sections of the corporation, from literary agents, industry associations and from existing subscriptioncustomers. Its development also needs to have input from content delivery and advertising consultants.The SMPS as proposed will allow Soliloquy to provide streaming media content on their website and create a clientapplication that will be available for subscribers. These will provide various functions including “Read on-line”functionality, purchase of product, listening to excerpts read by actors, movie excerpts, a reading in conversationoption, loyalty club and an interactive book club. The facilities required to support this are expected to be a mediadatabase (a redesign of the company’s existing database is required), interactive web-based media player and aclient based media player with configuration, application and e-commerce functionality. The interactive web-basedmedia player is expected to allow promotion of product and options, selection of excerpts of products in audio andvideo form and a reading in conversation option as well as purchasing ability. The client based media player will allow the full streaming of read on line, audio books, movies, reading in conversation, loyalty club offerings andmanagement, interactive book club and purchasing ability. The client basedmedia player will only be for subscribers.The business case identified the budget at $700,000 with potential payback within 2 years of completion. Thisincludes project manager costs (part time), developer costs – six developers are expected to be hired – charges fora content consultant and an advertising consultant, advertising, licencing and equipment – hardware and softwarefor developers. There is no planned upgrade to existing hardware as part of this project since there is expected tobe spare capacity in the company’s existing infrastructure. The estimated time frame for completion of the projects six months. Soliloquy realizes there are major risks associated with this project including lack of client interestand it hopes that the project manager will be able to identify the appropriate stakeholders and address the risksinvolved. If the project can meet the above objectives and more importantly do this with a payback within two yearsof completion it will be deemed to have been a success.You have been appointed as Project Manager to manage this project. A project steering committee has beenformed consisting of Tristan, who is the main promoter and supporter, as well as Elijah.Z. Money, the ChiefFinancial Officer (CFO), Ignatius T. Shoppe, the Chief Information Officer (CIO) and yourself. You have alreadybeen approached by Elijah about the costings and he is worried about the acceptance/transfer of risks associatedwith the project. Additionally, you have read the local industry newspaper, The Scribe and have noted a number ofconcerning letter and articles by individuals as well as those by the Authors Protection Guild (APG) and ActorsEquity (AE). Some fellow employees have contacted you about their reservations about the system. You ponder all this and have commenced identifying the stakeholders and preparing a stakeholder management strategy and youwill use this information and the detail above to press ahead and finalise the ProjectCharter…Assessable Tasks/RequirementsYou are required to create a Project Charter for the case study provided: Soliloquy Publishing Ltd. – Streaming Media Player System. The project will be managed using the Agile SCRUM PM methodology. This is amethodology that, amongst other things, concentrates on sprints of work. The case study should provide you withsufficient information akin to a Business Case to allow you to create a Project Charter for the project. A template has been provided from your text that would be a template used when following a predictive/planned projectmanagement methodology. You need to modify this to reflect the different approach under an Agile SCRUM PMmethodology and present what might be calledahybrid Project Charter. One of the principles to keep in mind isthat under an Agile SCRUM approach you should have an idea of the different way you schedule work and what isexpected at the end of each sprint cycle – a deliverable or potentially deliverable product. You might also considerthat Agile SCRUM is not as document rich as predictive/planned methodologies, so it might be useful to state a fewmore things in your project charter since it may be the only place you put a visible and succinct boundary aroundand encapsulate what is being done in the project.While preparing the Project Charter, you need to clearly identify both organisation and project components andtheir interrelationships. You need to think about:1. the vision (why do this project? – i.e. does it align with the company vision?);2.the mission (once again is there some relationship between this project and the mission of theorganisation?),3.what are the organisation’s goals and objectives (the quantified satisfaction of these goals); and4.what is the project scope and what are its objectives and success criteria (may be a general statement butmight also include some reference to satisfying the objectives).You may also need to:1.identify other stakeholders, in consultation with the sponsor;predict high level costs involved in the project;2.hire a team for the duration of the project; and3.devise a high level plan for the number of Sprints involved in the project and the objective for each Sprint Cycle.You may need to make other necessary assumptions in preparing the Charter but make sure these are clearly stated.(You may be creative with your assumptions to ensure that your submission is unique).The Project Charter will be displayed on the wall in the project team room for the duration of the project and mayinclude information such as:1. Project title, project authorization date, start date and finish date2.Project manager’s name and contact details3. Description of vision, mission and goals/objectives for the organisation4. Project scope/objectives, assumptions and constraints5. Success criteria for the project6.Summary budget7. Summary schedule Start and end dates for each sprint Objectives, deliverables and milestones for each sprint8.Summary of the project management methodology9. Governance10. Roles and responsibilities11.Sign-off section for all stakeholders
Answer:
Mission of the Organization
The mission of the organization is to deliver a new system with extensive content and a new revenue system in which the clients will pay subscription fees for accessing contents. As per the mission, a new media database will be created and connected to the company website while a client application will be provided to the subscribers who will be able to access the contents through this application. If sufficient amount of client can be gained, the entire revenue structure of the company will grow resulting in the increase in annual profits.
Vision Statement
The vision of the company is to enter online streaming market with the aim to provide the customers with high quality as well as informative contents at minimal subscription price.
Goals and Objectives
The main goal of the company is to establish a client based application software through which, the clients will be able to access a huge variety of streaming and interactive contents given they have subscribed for the services. Through this system, the company will be able to gain revenue from the subscription prices taken from the clients.
The objectives of the project are as follows.
To develop a media server through which all video contents will be streamed
To design and develop an online application through which the clients will be able subscribe and access the video contents
To prepare and develop a subscription structure based on time period (monthly / yearly)
To include an online payment feature in the application
To test the accessibility of the application from different web browsers and smartphones
To complete the project within a time period of 6 months
To complete the project within a pre set budget of $700,000
Project Scope
Project Scope Statement
As per the requirements of the project, there can be number of in scope and out scope items that are specified as follows.
In Scope:-
Development of the online application is within the scope of the project.
Development of the media server is within the scope of the project.
Preparation of subscription structure is within the scope of the project.
Promotion of the application among the existing and projected customer bases is within the scope of the project.
Contract signing with various media distributors is within the scope of the project.
Out Scope:-
Development of business strategy is out of scope of this project.
Analysis of market and future predictions are out of scope of this project.
Project Assumptions
In order to develop the project charter, a number of assumptions have been made that are as follows.
It has been assumed that the allocated budget of $700,000 will be sufficient for the project.
It has been assumed that the expended amount can be recovered within a time period of 2 years.
It has been assumed that 6 months will be sufficient for the completion of the project.
It has been assumed that all the necessary features and requirements can be incorporated within the system.
Project Constraints
The constraints of the project are as follows.
Although a cost benefit has been estimated from the project, chances of reaching such values are less due to a number of risk factors including lack of client interest, high competition in market and others.
In spite of addition of the variety of features, the success of the project is not 100% ensured.
There might be copyright and imaging rights issues if contents are streamed in the application without the prior permission of artists / content creators.
Summary Budget
The summary budget for the project is shown in the following table.
Resource
Estimated Cost
Hardware for Developers
$50,000
Software for Developers
$100,000
Stakeholder Wages
$250,000
Developer Costs
$150,000
Consultancy Costs
$50,000
Licensing and Other Costs
$100,000
TOTAL
$700,000
Summary Schedule
Start and End Dates for Each Sprint
The start and end dates for each sprint of the project are shown in the following table.
Task Name
Duration
Start
Finish
Development of Online Streaming Media Player
134 days
Mon 4/30/18
Thu 11/1/18
Project Planning
10 days
Mon 4/30/18
Fri 5/11/18
Survey of Current Business System
2 days
Mon 4/30/18
Tue 5/1/18
Board Meeting
1 day
Wed 5/2/18
Wed 5/2/18
Determination of Mission and Vision
2 days
Thu 5/3/18
Fri 5/4/18
Prepare Project Plan
4 days
Mon 5/7/18
Thu 5/10/18
Authorization of the Project
1 day
Fri 5/11/18
Fri 5/11/18
Project Initiation
17 days
Mon 5/14/18
Tue 6/5/18
Appoint Stakeholders for Project
2 days
Mon 5/14/18
Tue 5/15/18
Develop Project Charter
5 days
Wed 5/16/18
Tue 5/22/18
Determine Project Scope
1 day
Wed 5/23/18
Wed 5/23/18
Create List of Deliverables
1 day
Thu 5/24/18
Thu 5/24/18
Make Assumptions
1 day
Fri 5/25/18
Fri 5/25/18
Evaluate Constraints
1 day
Mon 5/28/18
Mon 5/28/18
Develop Project Schedule
2 days
Tue 5/29/18
Wed 5/30/18
Estimate Project Budget
3 days
Thu 5/31/18
Mon 6/4/18
Approval of Project Plan
1 day
Tue 6/5/18
Tue 6/5/18
Project Execution
96 days
Wed 6/6/18
Wed 10/17/18
Assign Roles to Stakeholders
2 days
Wed 6/6/18
Thu 6/7/18
Hire Developers
4 days
Fri 6/8/18
Wed 6/13/18
Procure Budget for Project
2 days
Thu 6/14/18
Fri 6/15/18
Initiate Development
1 day
Mon 6/18/18
Mon 6/18/18
Prepare List of Features to be Added
2 days
Tue 6/19/18
Wed 6/20/18
Develop Media Database
20 days
Thu 6/21/18
Wed 7/18/18
Add All Required Features
15 days
Thu 7/19/18
Wed 8/8/18
Develop Client Application
30 days
Thu 8/9/18
Wed 9/19/18
Connect Application with Database
5 days
Thu 9/20/18
Wed 9/26/18
Run the System
2 days
Thu 9/27/18
Fri 9/28/18
Analyze Errors
2 days
Mon 10/1/18
Tue 10/2/18
Address Errors
4 days
Wed 10/3/18
Mon 10/8/18
Risk Management
4 days
Tue 10/9/18
Fri 10/12/18
Final Testing
2 days
Mon 10/15/18
Tue 10/16/18
Project Handover
1 day
Wed 10/17/18
Wed 10/17/18
Project Closing
11 days
Thu 10/18/18
Thu 11/1/18
Review of Project
5 days
Thu 10/18/18
Wed 10/24/18
Appraisal
2 days
Thu 10/25/18
Fri 10/26/18
Approval of Project Report
2 days
Mon 10/29/18
Tue 10/30/18
Stakeholder Sign Off
1 day
Wed 10/31/18
Wed 10/31/18
Official Closing
1 day
Thu 11/1/18
Thu 11/1/18
Objectives, Deliverables and Milestones
The objectives of the project that must be fulfilled are shown in the following work breakdown structure.
Figure 1: Work Breakdown Structure Showing Objectives of Project
The deliverables and milestones of the project including the proposed schedule for each sprint are shown in the following Gantt chart.
Summary of Project Management Methodology
The project management methodology to be followed for the project is Agile Scrum PM Methodology. This methodology framework will perfectly fit the requirements of the project as it will follow a specific execution structure as mentioned in Scrum method. Before starting the project, Scrum will allow the organization to develop a vision statement and a set of project goals and objectives. Based on these specifications, the project sprints will be determined within a fixed set of timeline. Within this timeline, the project sprints will be executed and then evaluated for further changes and additional requirements.
Governance
The project will have a suitable governance structure that will require the stakeholders of the project to manage and govern different aspects of the project. There are four main stakeholders of the project, namely the project manager, promoter, chief financial officer and chief information officer. Since their duties are allocated in different aspects of the project, they also need to govern these aspects so that the project does not go out of scope or any problems and issues can be promptly addressed and solved.
Roles and Responsibilities
The roles and responsibilities of the stakeholder in the project are as follows.
Stakeholder Name
Designation
Duty
PLEASE FILL
Project Manager
Preparation of charter, management of entire project
Tristan Bard
Main Promoter / Supporter
Approval of project, promotion of project
Elijah Z. Money
Chief Financial Officer
Management of project funds
Ignatius T. Shoppe
Chief Information Officer
Business analytics, providing suggestions regarding the system
Bibliography
Binder, J. (2016). Global project management: communication, collaboration and management across borders. Routledge.
Boud, D., Cohen, R., & Sampson, J. (Eds.). (2014). Peer learning in higher education: Learning from and with each other. Routledge.
Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management. Project Management Institute.
Harrison, F., & Lock, D. (2017). Advanced project management: a structured approach. Routledge.
Heagney, J. (2016). Fundamentals of project management. AMACOM Div American Mgmt Assn.
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Schwalbe, K. (2015). Information technology project management. Cengage Learning.
Turner, R. (2016). Gower handbook of project management. Routledge.
Verzuh, E. (2015). The fast forward MBA in project management. John Wiley & Sons.
Walker, A. (2015). Project management in construction. John Wiley & Sons.
Free Membership to World’s Largest Sample Bank
To View this & another 50000+ free samples. Please put
your valid email id.
Yes, alert me for offers and important updates
Submit
Download Sample Now
Earn back the money you have spent on the downloaded sample by uploading a unique assignment/study material/research material you have. After we assess the authenticity of the uploaded content, you will get 100% money back in your wallet within 7 days.
UploadUnique Document
DocumentUnder Evaluation
Get Moneyinto Your Wallet
Total 6 pages
PAY 4 USD TO DOWNLOAD
*The content must not be available online or in our existing Database to qualify as
unique.
Cite This Work
To export a reference to this article please select a referencing stye below:
APA
MLA
Harvard
OSCOLA
Vancouver
My Assignment Help. (2020). IT Project Management Techniques 1. Retrieved from https://myassignmenthelp.com/free-samples/itech2250-it-project-management-techniques-1.
“IT Project Management Techniques 1.” My Assignment Help, 2020, https://myassignmenthelp.com/free-samples/itech2250-it-project-management-techniques-1.
My Assignment Help (2020) IT Project Management Techniques 1 [Online]. Available from: https://myassignmenthelp.com/free-samples/itech2250-it-project-management-techniques-1[Accessed 19 December 2021].
My Assignment Help. ‘IT Project Management Techniques 1’ (My Assignment Help, 2020)
My Assignment Help. IT Project Management Techniques 1 [Internet]. My Assignment Help. 2020 [cited 19 December 2021]. Available from: https://myassignmenthelp.com/free-samples/itech2250-it-project-management-techniques-1.
×
.close{position: absolute;right: 5px;z-index: 999;opacity: 1;color: #ff8b00;}
×
Thank you for your interest
The respective sample has been mail to your register email id
×
CONGRATS!
$20 Credited
successfully in your wallet.
* $5 to be used on order value more than $50. Valid for
only 1
month.
Account created successfully!
We have sent login details on your registered email.
User:
Password:
MyAssignmenthelp.com is the perfect solution to render quality solution for all sort of academic issues. We have hired professionals from different fields of study to provide assistance with different subjects. We successfully have provided different types of assignment solutions on 100+ subjects. We have hired industry experts to deliver nursing assignment, hr assignment and finance assignment help. To offer quality content with IT assignments, we have hired IT professionals to render programming language assignment help and IT assignment help for other types of IT assignments as well.
Latest Project Management Samples
div#loaddata .card img {max-width: 100%;
}
SBM 1201 Project Scope, Time And Cost Management
Download :
0 | Pages :
12
Course Code: SBM1201
University: Asia Pacific International College
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answer:
Introduction
This project plan deals with the development of a fuel-efficient HHO Generator. The HHO fuel cells may appear to provide high fuel efficiency to the users. Nevertheless, there are a few confinements and focuses to be seen, as given beneath. This is to clear up that there is NO 100% substitution of petroleum derivative by including HHO cell. HHO gas is otherwise called Brown Gas, yet this is to illuminate that HHO gas is n…
Read
More
Tags:
Australia Footscray Management organisational behviour University of New South Wales Masters in Business Administration
HS2061 Information Systems Project Management
Download :
0 | Pages :
9
Course Code: HS2061
University: Holmes Institute
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answer:
Case Overview:
The project owner of the Signed, sealed, delivered courier service is facing the problems of managing order of couriers in the synchronised manner. The project manager is incapable of managing central warehouse for the dispatching of products. The important information can be lost with the passage of time. The inventory management of the warehouse is the major concern for the owner of the company. He is looking forward …
Read
More
OPS 935 Project Management
Download :
0 | Pages :
11
Course Code: OPS935
University: University Of Wollongong
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answer:
Introduction
This essay explores the impacts of digital technologies on project management. It explores how adoption of digital technologies by companies for managing their project have affected their, project managers, human resource, business processes, timelines, deliverables, and practices of risk management, people management and quality management.
Impact of Digital technologies on Project Management Practices
Digital te…
Read
More
Tags:
Australia Saint Kilda Management International Management University of New South Wales Masters in Business Administration
ITC505 ICT Project Management
Download :
0 | Pages :
10
Course Code: ITC505
University: Charles Sturt University
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answers
Case Study- Social Media Research Center
Task-1: Project Charter
Project Objectives
The main objective of the project is to develop a web-based system within the organization “Social Media research Center”. It is analyzed that the Social Media research center wants to develop the web based system in order to connect people with the organization for promoting its research center. The web-based system that is developed conta…
Read
More
Tags:
Australia Alfredton Management IT Network Security University of New South Wales Masters in Business Administration
ITC505 ICT Project Management
Download :
0 | Pages :
7
Course Code: ITC505
University: Charles Sturt University
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answers
Part One- Project Name / Team / Description
Project Name:
RALS Solution