Question:
This assignment requires you to apply what you have learned in the module by planning an improvement project or by planning to implement an entirely new project of your choice in your work place.
Your Tasks must include the following:• Identifying or selecting a Project to be managed• Produce a statement of work (SOW) overall project goals.• Develop a work breakdown structure (WBS)
• Define the products or deliverables upon the completion of the said project.• Estimate time and cost needed for completing various sub-tasks in order to complete the full project.• Assessing the HR requirement when assembling the Project team.• Assess the risks if any for the project• Analyze task dependencies to identify project’s critical path and project schedule.• Assess project quality through regular monitoring of progress and nature of progress.• Provisions for Project closure.
Note that, in this assignment, you are planning a project and not doing it. Also note that planning requires a number of assumptions of the setting where the project is carried out and therefore you need to have a specific organization in mind, while youplan for them.
Answer:
ABC is a trading organization that provides trading support to investors and training to the brokers getting into trading business. The company has been operating online through various business networking platforms such as LinkedIn and other specialized traders’ platforms where they are registered (Dinsmore & Brewin, 2010). However, the company realizes the need to have a new website so that it can have a detailed presentation of services and portfolios and engage potential customers on the website which is likely to give them more conversion. The company has decided to use the open source content management system called WordPress for it is one of the most popular systems across globe. The project is going to be outsourced to a third-party development contractor (BENAIJA1 & KJIRI, 2013).
Project Management Plan
Project Selection
The company was approached by an organization that lists various types of businesses online and the company had suggested ABC the allow them to register them for the services that would allow creation of a webpage for the company that would look like a website. A promise was given that the page will give the company more traction into the online space (EU, 2005). After discussion with the team, management discovered that there was another option which was to develop a full-fledged website for company instead of just a page.
The two project presented opportunities from which only one could be selected (AG, 2013). The project selection was made using a scoring model in which the management representatives were asked to score each project on certain criteria such that the project assuming higher total score was selected. The criteria included cost of development, expected rate of return, ownership, control, rate of conversion, exposure, quality of deliverables, timelines, strategic alignment, and so on. The development of own website got a higher score in the process which is why the same project has been proposed here (Baguley, 2008).
Background
This project would involve development of a website for an organization that is into trading business. The contract for the development has been awarded to an IT organization that acts as an independent contracting agency (GALWAY, 2004). The website development project would include development of user’s interfaces, website pages, graphics, and content elements. It would have interfaces designed for the customers to connect to the brand through chat and email functionalities. The project would take five phases for completion and these include project initiation, project planning, website designing, implementation, and project closure (Cliff COnsulting, 2007).
The project would begin with purpose of a domain name and webspace. Once these are in place, a content management system called WordPress would be installed on the DNS acquired. A plan would then be developed for executing the remaining project activities needed to complete the project. It would include plan for the management of different areas of project management including schedule management, budgeting, project scope management, risk management, and resource management. A design would then be developed for the website pages and then the project plan would be implemented (C.R & Thomas, 2011).
Implementation stage would include development of the website features, interfaces, graphics, and content. Once all these components of the website are developed, they would be installed on the CMS and testing would be followed to identify any bugs in the website. This statement of work defines all these activities that are in the scope of the project. The project has been allotted a budget of $1,00,000 and the website development needs to be completed in 6 months starting from initiation till the closure of the project (Leroy, 2012).
Project Scope
The project would be completed in five stages including initiation, planning, designing, implementation, and project closure. In initiation phase, the independent contractor would gather requirements for the project by interviewing the company representatives. The requirements gathered would be used for planning and designing stages of the project (Heerkens, 2015). Based on these requirements, the project would be planned and the design would be developed for the website. After the approval of the design, actual website would be coded and then tested. The project scope would define the outcome and deliverables of the project (Dinsmore & Brewin, 2010).
Activities within the scope of the website development include:
Procurement of domain name and webspace for the website
Installation of content management system
Creation of the design for the development of the website
Development of website features based on the approved design(Ayyalaraju, 2017)
Installation of WordPress widgets for development of planned features on the website
Coding for the customization of the website features
Testing of the website to identify bugs and eliminate them(Cliff COnsulting, 2007)
Activities that are not in the project scope include:
Training the employees of the company on the use of CMS
Launching the website for the public to see(Ayyalaraju, 2017)
Work Requirements
The project would have the following requirements to be fulfilled in each stage of the project:
Initiation: In this phase, the contractor would be selected and outsourced the work of the website development. The contractor would get the DNS and webspace for the website development and install a CMS on the space. Once that is done, the contractor would interview the key stakeholders of the project to understand their requirements (Leroy, 2012).
Planning: In this stage, the contractor would develop the website involving installation of plugins needed for the development of different website components including chat functionality, home page slider, testimonials, feature boxes, and blog pages. It also included development of codes for customization of website features and interfaces (Ayyalaraju, 2017).
Designing: A design would be developed for the website in this stage which would be based on the requirements of the project and would form the basis for the development of the CSS or PHP codes (Liu, 2013).
Implementation: In this stage, the plugins would be installed as planned on the website and the customization of the website features and components would be done using the custom coding done on PHP and CSS. In this phase, the developed website code would also be tested to identify if there are any bugs. These bugs would be eliminated when found and the updated code would be finalized for the website (AG, 2013).
Closure: By this stage, all the deliverables of the project would be completed and they would be recorded in the project closure documentation by the contractor. This would include the review of the project completion based on which the company head would take a decision on the acceptance of the developed website. The acceptance from the client organization would mark the completion of the project and the client would give a final sign off (Mushtaq, 2016).
The tasks would be executive in a sequence as covered in the Work Break Down Structure provided below (Devi & Reddy, 2012):
Project Initiation
Contractor Selection
Set-up
DNS
Webspace
WordPress CMS installation
Requirement Gathering(Baguley, 2008)
Planning
Budgeting
Scheduling
Resource Management
Roles & Responsibilities
Team Management
Scope Management
Risk Management(Devi & Reddy, 2012)
Designing
Features
Functionalities
Pages
Graphics(Baguley, 2008)
Implementation
Website Development
Theme installation
Plugins
Content development
Uploading of Graphics
Custom coding(RCF, 2003)
Testing
System testing
Functional testing
Use Acceptance testing(RCF, 2003)
Project Closure
Project Acceptance
Project documentation
Project sign off (Devi & Reddy, 2012)
Schedule
Assuming the project starting on 1st Sept 2018, it would have the following milestones:
Task
Finish Date
Contractor Selection
1st Sept 2018
Set-up
10th Oct 2018
Requirement gathering
17th Oct 2018
Project Management Planning
25th Nov 2018
Website design
28th Nov 2018
Website Design review & approval
30th Nov 2018
Plugins installation
27th Nov 2018
Content Development Uploading (Bruce & Langdon, 2009)
31st Dec 2018
Custom Coding
25th Jan 2019
Testing
24th Feb 2018
Project Completion review
25th Dec 2018
Project Closure Documentation
28th Feb 2018
Project Sign off
5th Mar 2019
Budget
The website development project has a budget of $1,00,000 in which all the stages of the project would be covered. The budget would be released in portions depending on the requirement of each stage of the project (SAEO, 2015).
Acceptance Criteria
The project would be reviewed at the end of each stage and only after the outcome of each stage is accepted will the final project be seen as accepted. The criteria for acceptance at each stage of the project are as follows (C.R & Thomas, 2011):
Initiation Stage acceptance criteria:
Installation of DNS, web space, and CMS is completed
Selected contractor has both capabilities and experience of working on website development projects(Sabyasachi, 2018)
Planning Stage completion acceptance criteria:
All key stakeholders have participated in the requirements gathering stage
The plan explains how each of the following project components would be handled(Cliff COnsulting, 2007)
Budget
Schedule
Risks(Kärri, 2014)
Scope
Resources(Ponnappa, 2014)
All the human resources have been assigned appropriate responsibilities
Design stage acceptance criteria:
The design presented has all the components needed on the website(DESPA, 2014)All the needed functionalities and features have been identified and covered in the design
Implementation stage completion acceptance criteria (OECD, 2014):
All the required features have been installed on the website
The website is able to provide all the required functionalities as identified in the requirement gathering process
Custom code has been implemented on the website successfully
All the codes have been tested and corrected for bugs
Project Closure stage acceptance criteria:
All the details of the project progress have been documented
Project deliverables have been sufficiently reviewed by the client organization(Bruce & Langdon, 2009)
Acceptance
The following company representatives have accepted that the project has been successfully completed:
ABC Company
Website Development Contractor
Company name
Company name
Allen Booze
Dale Williams
Full name
Full name
CEO
Project Manager
Title
Title
Signature
Signature
Date
Date
Deliverables
The deliverables of this project include:
Content management system installed on the new DNS
A design suggesting features and components for a website
Plugins installed on the website delivering required functionalities on the website
Content uploaded on the website including the textual content and the graphics(Langley, 2015)
Custom codes delivered as per the needs of the company
Positive testing completed to ensure that there are no bugs in the codes(Dinsmore & Brewin, 2010)
Team Management
The team would be assigned the responsibilities for taking care of the development of the project involved in various ways into different stages. There are five people in the team of the contractor who would be involved in the development process and these include project management, IT manager, developer, content writer, and graphic designer. The roles and responsibilities of the team members are listed below (DESPA, 2014):
Responsibilities of the project manager would include:
Coordinate with the client to collect the project requirements
Ensure that project activities are completed within time and within the assigned budget(Leroy, 2012)
Coordinate with the team members and guide them to ensure smooth completion of work
Monitor project process and keep a tab on deliverables to ensure they are up to date
Identify risks on the project and plan contingency and mitigation strategies to deal with them(Heerkens, 2015)
Responsibilities of the IT manager would include:
Procure licenses for DNS and webspace and ensure that WordPress is installed
Ensure that the website also has required plugins for security, SEO, and backups updated(EU, 2005)
Responsibilities of the developer would include:
Identify required plugins and install them with appropriate content added
Code plugins to add custom functionalities as per project requirements(Liu, 2013).
Responsibilities of the content writer would include:
Identify needs of the content and write content for the website
Deliver content as per the design on desired timelines
Ensure that the content is copy cape tested and is well proofread and edited
Responsibilities of the graphic designer would include:
Procure graphics and modify them as per the needs of the project
Create illustrations wherever needed for the website
Deliver graphics as per the design on desired timelines(Mushtaq, 2016)
A RACI Chart would help identify their responsibilities and accountabilities which would help the project manager ensure that they are all adhering to their part and it would also make it easy for the manager to identify who should be taking first action in case of any risks appearing. The exercise would also ensure that everyone is made responsible for a task is also accountable (EU, 2005).
Project Tasks
Project Sponsor
Project Manager
Website Developer
IT Manager
Content Writer
Graphic Designer
Project Planning
CI
RAC
CI
CI
CI
CI
Scheduling
A
RAC
CI
CI
CI
CI
Budgeting
A
RAC
I
CI
I
I
Initiation
A
RAC
I
I
I
I
Website development
CI
RAC (OECD, 2014)
R
RA (Mushtaq, 2016)
RAC
RAC
Installation
I
CI
RAC
RAC
I
I
Coding
I
CI
RAC
RACI
I
I
Testing
I
CI
RAC
RAC
I
I
Risk Management
CI
RAC
CI
CI
I
I
Resource Management
CI
RAC
CI
CI
I
I
Time Management
CI
RAC
CI
CI
I
I
Project Closure
RA (Oracle, 2009)
RAC
I
I
I
I (Langley, 2015)
Risk Management
Risk management involves identification of risks that can occur on a project and deployment of the response plan to deal with them. Typical responses to any project risk would be avoidance if possible, transfer of the risk to other party, mitigation of risk in the case of occurrence, and ignorance if the risks is unlikely to affect the project in a major way but its resolution can be a significant cost to the company. The choice of the strategy to use and the risks that have to be prioritized would depend on the level of severity these risks present to the project which would be calculated on the basis of their likelihood of occurrence and the potential impact they would have on the project (Oracle, 2009).
The table below identifies some possible risks on the project as well as presents the level of severity and the response plan. The table also identifies the person who would be responsible for ensuring that the appropriate response plan has been taken. With this chart, there would also be a risk registered prepared that will record all these details and would also record the actions actually taken for the risks by the team as the project would progress. This would help the team keep a tab on the risks and ensure that they do not impact the project deliverables much and are well taken care of (GALWAY, 2004).
Risk
Impact
Probability
Ranking
Response
Responsibility
Project going overbudget (Wickboldt, 2011)
Medium
High (Ponnappa, 2014)
6
Mitigate: Monitor project progress and control costs in case they still escalate, utilize a contingency fund that has to be set aside during budgeting. In case the funds are still insufficient, take approval for additional funds to be given from the project sponsor (Wickboldt, 2011).
Project Manager
Content delivery delays
High
Medium
6
Mitigate: Put a random content and continue with coding and development and replace the content with actual post development (Oracle, 2009)
Developer
Coding errors
High
Medium
6
Mitigate: Conduct thorough tests on the website and correct any identified bugs
Developer
Scope variations
High
Low (SAEO, 2015)
Mitigate: Incorporate only the changes needed and avoid those costing more without any major benefits to the company (OECD, 2014)
Project Manager
Gaps in communication
(Liu, 2013)
Medium
Medium
4
Avoid: Coordinate with the team members to ensure everything is on paper
Project Manager
Project Closure
The project would be marked as completed once all the deliverables have been completed. The project manager would take a review of the project completion and document everything about the project status including the lessons learned. This review would be given to the project owner who would be approving it to mark its completion (Sabyasachi, 2018).
Conclusions
This project is planned for the development of a new website for the ABC company that is into trading business. The company uses online business platforms to promote itself but is now planning too increase its online presence with the development of a website. The project was selected between two options that included trading page development on a business marketplace and a full fledged website development. The website development has been selected as the project too be developed based on eh scoring model that involves views of all the team members of the company.
The report presented the project scope which included procurement of DNS and web space, installation of CMS, installation of plugins, customization of pages, development of content and graphics, and testing of the developed codes. The project is assigned to five key members of the third part service provided and they include project manager, IT manager, developer, writer, and graphic designer. A number of risks have been identified such as cost escalation, delays in deliver, and gaps in communication and appropriate plan for responding to them has been presented.
Based on the planning process, certain recommendations can be made for the project manger and the project organization to ensure smooth and successful delivery of the project and these include:
While developing project scope, all the requirements given by the stakeholders must be considered and thus, it is important that the project manager interviews all major stakeholders of the company to ensure al requirements re sufficiently identified
The project manager must work to avoid occurring of risks that can have a major impact on the project and should take up those risks on priority for solution that present high level of severity for the project which could be 6 or more.
The RACI chart and risk management chart must be distributed to the team so that everyone know what is expected from them and when they should act on priority
The project manager must set aside come contingency amount like 10% of the total project budget and get the same approved by the sponsor at the beginning itself so that in the cases of unavoidable risks and consequences, the contingency amount can be utilized without affecting the outcome of the project much. This would save time and efforts of the project manager who would not need to take additional approvals from the sponsor in case of emergencies.
References
AG, 2013. Monitoring, review and evaluation, s.l.: Australian Government, pp. 37-56.
Ayyalaraju, R., 2017. Requirement Analysis and Gathering – and Gathering – a Primer a Primer, s.l.: SOAIS, pp. 12-15.
Baguley, P., 2008. Project management. London: Hodder Education, pp. 14-15.
BENAIJA1, K. & KJIRI, L., 2013. Project portfolio selection: Multi-criteria analysis and interactions between projects, s.l.: ENSIAS, pp. 37-56.
Bruce, A. & Langdon, K., 2009. Project management. London: Dorling Kindersley..
C.R, K. & Thomas, S. M., 2011. Requirement Gathering for small Projects using Agile Methods. IJCA, pp. 122-128, pp. 7-12.
Cliff COnsulting, 2007. A Systems Implementation Project Planning Guide, s.l.: Cliff Consulting, pp. 11-12.
DESPA, M. L., 2014. Comparative study on software development methodologies. Database Systems Journal, pp. 37-56.
Devi, T. & Reddy, V., 2012. Work Breakdown Structure of the Project. International Journal of Engineering Research and Applications , pp. 683-686.
Dinsmore, P. C. & Brewin, J. C., 2010. The AMA Handbook of Project management, s.l.: AMACOM, pp. 17-20.
EU, 2005. Human Resources management strategies to support organizational changes, s.l.: EU, , pp. 17-20.
GALWAY, L., 2004. Quantitative Risk Analysis for Project Management, s.l.: Rand Corporation, pp. 213-214.
Heerkens, G., 2015. Project management. USA: Mcgraw-Hill Education, pp. 71-81.
Kärri, T., 2014. Creating risk measurement model to project portfolio management in construction company, s.l.: LAPPEENRANTA UNIVERSITY OF TECHNOLOGY, pp. 7-12.
Langley, M. A., 2015. Delivering on Strategy: The Power of Project Portfolio Management, s.l.: Deloitte, pp. 17-18.
Leroy, A., 2012. Requirements Gathering Rules Basic guidelines for any project, s.l.: BDPA National Technology Conference, pp. 7-12.
Liu, F., 2013. Rutherford Library Renovation Project Plan, s.l.: University of Alberta Library, pp. 11-12.
Mushtaq, J., 2016. Different Requirements Gathering Techniques and Issues. INTERNATIONAL JOURNAL OF SCIENTIFIC & ENGINEERING RESEARCH, pp. 835-840, pp. 117-118.
OECD, 2014. Risk Management and Corporate Governance, s.l.: OECD Publishing, pp. 71-72.
Oracle, 2009. Managing Risk with Project Portfolio Management in the Oil and Gas Industry During an Economic Downturn , s.l.: Oracle, pp. 65-66.
Ponnappa, G., 2014. Project Stakeholder Management.. Project Management Journal, pp. 1-3.
RCF, 2003. Work Breakdown Structure, s.l.: U.S. Department of Energy, pp. 7-12.
Sabyasachi, 2018. The Importance of Having Clearly Defined Acceptance Criteria in Your Projects, s.l.: Simplilearn, pp. 1-2.
SAEO, 2015. Cost Estimating Manual for Projects , s.l.: SAEO, pp. 7-12.
Wickboldt, J. A., 2011. A framework for risk assessment based on analysis of historical information of workflow execcution in IT systems, s.l.: LUME, pp. 8-9.
Free Membership to World’s Largest Sample Bank
To View this & another 50000+ free samples. Please put
your valid email id.
Yes, alert me for offers and important updates
Submit
Download Sample Now
Earn back the money you have spent on the downloaded sample by uploading a unique assignment/study material/research material you have. After we assess the authenticity of the uploaded content, you will get 100% money back in your wallet within 7 days.
UploadUnique Document
DocumentUnder Evaluation
Get Moneyinto Your Wallet
Total 14 pages
PAY 9 USD TO DOWNLOAD
*The content must not be available online or in our existing Database to qualify as
unique.
Cite This Work
To export a reference to this article please select a referencing stye below:
APA
MLA
Harvard
OSCOLA
Vancouver
My Assignment Help. (2021). Project Management. Retrieved from https://myassignmenthelp.com/free-samples/leb2018-project-management/source-content.html.
“Project Management.” My Assignment Help, 2021, https://myassignmenthelp.com/free-samples/leb2018-project-management/source-content.html.
My Assignment Help (2021) Project Management [Online]. Available from: https://myassignmenthelp.com/free-samples/leb2018-project-management/source-content.html[Accessed 19 December 2021].
My Assignment Help. ‘Project Management’ (My Assignment Help, 2021)
My Assignment Help. Project Management [Internet]. My Assignment Help. 2021 [cited 19 December 2021]. Available from: https://myassignmenthelp.com/free-samples/leb2018-project-management/source-content.html.
×
.close{position: absolute;right: 5px;z-index: 999;opacity: 1;color: #ff8b00;}
×
Thank you for your interest
The respective sample has been mail to your register email id
×
CONGRATS!
$20 Credited
successfully in your wallet.
* $5 to be used on order value more than $50. Valid for
only 1
month.
Account created successfully!
We have sent login details on your registered email.
User:
Password:
At MyAssignmenthelp.com, we understand that when students get stuck with tough assignments, they look for affordable services. To assist students with complex assignments, we have built a team of skilled cheap essay writers. MyAssignmenthelp.com has become one stop solution for all students who often look for answers related to their search similar to do my essay at the cheap rate or who can write my essay at affordable prices. Students prefer hiring us as we have the best provisions to render services related to do my essay online at a reasonable rate.
Latest Project Management Samples
div#loaddata .card img {max-width: 100%;
}
SBM 1201 Project Scope, Time And Cost Management
Download :
0 | Pages :
12
Course Code: SBM1201
University: Asia Pacific International College
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answer:
Introduction
This project plan deals with the development of a fuel-efficient HHO Generator. The HHO fuel cells may appear to provide high fuel efficiency to the users. Nevertheless, there are a few confinements and focuses to be seen, as given beneath. This is to clear up that there is NO 100% substitution of petroleum derivative by including HHO cell. HHO gas is otherwise called Brown Gas, yet this is to illuminate that HHO gas is n…
Read
More
Tags:
Australia Footscray Management organisational behviour University of New South Wales Masters in Business Administration
HS2061 Information Systems Project Management
Download :
0 | Pages :
9
Course Code: HS2061
University: Holmes Institute
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answer:
Case Overview:
The project owner of the Signed, sealed, delivered courier service is facing the problems of managing order of couriers in the synchronised manner. The project manager is incapable of managing central warehouse for the dispatching of products. The important information can be lost with the passage of time. The inventory management of the warehouse is the major concern for the owner of the company. He is looking forward …
Read
More
OPS 935 Project Management
Download :
0 | Pages :
11
Course Code: OPS935
University: University Of Wollongong
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answer:
Introduction
This essay explores the impacts of digital technologies on project management. It explores how adoption of digital technologies by companies for managing their project have affected their, project managers, human resource, business processes, timelines, deliverables, and practices of risk management, people management and quality management.
Impact of Digital technologies on Project Management Practices
Digital te…
Read
More
Tags:
Australia Saint Kilda Management International Management University of New South Wales Masters in Business Administration
ITC505 ICT Project Management
Download :
0 | Pages :
10
Course Code: ITC505
University: Charles Sturt University
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answers
Case Study- Social Media Research Center
Task-1: Project Charter
Project Objectives
The main objective of the project is to develop a web-based system within the organization “Social Media research Center”. It is analyzed that the Social Media research center wants to develop the web based system in order to connect people with the organization for promoting its research center. The web-based system that is developed conta…
Read
More
Tags:
Australia Alfredton Management IT Network Security University of New South Wales Masters in Business Administration
ITC505 ICT Project Management
Download :
0 | Pages :
7
Course Code: ITC505
University: Charles Sturt University
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answers
Part One- Project Name / Team / Description
Project Name:
RALS Solution
Team Name:
Consultants for RALS
Project Description:
RALS organizes show for the farmers and other related small business persons to display their latest technology equipment for betterment in the field of agriculture and crop production. The show has different types of stalls and other facilities for which many volunteers …