Free Samples
Measurement For The Item Of Work
.cms-body-content table{width:100%!important;} #subhidecontent{ position: relative;
overflow-x: auto;
width: 100%;}
Measurement For The Item Of Work
0 Download5 Pages / 1,098 Words
Question:
Discuss about the Measurement For The Item Of Work.
Answer:
Table 1: Concrete work
ITEMS
Unit
Quantity
Concrete placement
M3
224
Floor finishing
M2
109
Rebar works
M3
125
Floor fabrication
kgs
113
Table 2: Masonry
ITEMS
Unit
Quantity
Glazed tiles
M2
106
Brickwork
M2
242
Plaster wall and ceiling
M2
120
Vinyl Floor tile
M2
32
NB: the excel sheets attached provides the activity precedence diagram and the critical path is established using the method of critical path method where zero float activities are the candidates for inclusion in the critical path network.
Determine appropriate productivity constants for the item of work
The productivity constant for a Mason in brickwork laying is given as (Scribd, 2018) 1.0hrs per m2 and for Metal work is 0.8hrs per m2
Determine tradesman hours worked
In Masonry, for example, placement of reinforced concrete on slabs:
Labour= 1.3hrs per m3
For 150 slab- 107m3 (allow 12% waste) hence = 107+107×0.12= 119.84m3
Therefore trades man hours worked= 119.84/1.3= 92.18 hrs
Determine a suitable gang size
Gang size n= Q/Pw
Where n= number of workers, Q= quantity of work, and W= work duration, P= productivity (in m3/hr)
= 113/(1.3-1 x 24×6) = 1.02 roughly 2 men
Determine time needed to complete the task.
For the 1st task, the productivity constant: Rebar works for ground floor is 0.14kgs per hr
The total amount of work available to do ground floor = 125
Hence time needed to complete work= 125 x 0.14x 5= 87.5hrs = 3.65days
For task 2, the productivity constant: Glazed tiles are 6.0sqr meter per hr
Hence time to complete work = 6.0 x 106= 636hrs= 26.5 days
Review the task shown in the project and verify its sequence and the duration allowed. Would you make any changes? If so what would you change, and why?
This is a perfect job scheduling since the predecessor must be allowed sufficient time to cure before the task can set in. Afterwards task 1 is simply a continuation of predecessor hence this is okay.
In the second task selected, (Glazed tiles), the predecessor activity is task 23 takes 2 days while the activity that follows the selected task is a continuation of the said task as we move to the next level. This is also a perfect scheduling strategy since the basement needs to be ready and adequate to carry the elements of windows and doors otherwise it would be impossible to accomplish this task without the predecessor task being done first.
Critique the program provided – find and discuss any inconsistencies that you can find. Would you ask for changes to be made, and why?
In the section of waterproofing, it should have been scheduled earlier not later when masonry is already done. Sound waterproofing requires that consideration be made right at the time of sinking the foundation walls and piers: unfortunately in this case, the foundation was done without much consideration to waterproofing.
Secondly, the program does not include acoustic requirements yet it is also critical for effective building performance; that should have been factored in perhaps as one of the finishing construction elements.
The program also seems to be highly inflexible given the almost time dependent lineated activities, in other words, there are more activities that are dependent on the predecessor activities such that should there be any delay as a result of unexpected external shocks, then the whole project will greatly be affected. This is what a critical path is.To cushion it against the externalities would require the contingency plan to be reviewed in anticipation for these shocks hence overall project timeline will have to be revised by reducing the number of conditional activities.
Additionally, the program is designed for implementation per trades section. However, the most effective method would have been if it was divided into phases, such that we appreciate time value of the project. After every phase is completed, we undertake a brief project review to capture the strengths and weaknesses so far. This could be done by considering the levels of the building since most tasks, a part from foundation establishment, are repetitive among the levels.
However, the current activity program provides a basis onto which further improvements can be made.
Overall is the schedule realistic or optimistic? Would you accept the schedule and provide it to your client or architect?
As far as the current schedule is concerned, it seems to be optimistic as some critical elements of consideration have been neglected yet they directly impact the project performance. For instance, we assume that the project will go on successfully without a careful thought to the externalities. That needs to be accommodated. Besides, certain activities would run concurrently if the program is revised as proposed.
Assume that construction activities have fallen behind program. Task compression is required. For the two tasks selected earlier outline:
Time cost and compression impacts of working overtime each day.
To undertake compression, we would have to increase the total labour and equipment in each task and time:
Hence suppose, we compress the 1st task by additional 4hours per day and task 2 by 3 hours per day and then we add an extra labour of 3 in each case;
The extra cost (assuming equipment cost negligible):
For Task 1:
And new activity time for the task: 3.65+ 4/24×5= 4.48 days
For Task 2:
Activity time: 3+ 3/24×3= 3.375 days
The labour cost implications:
For Mechanical: 31.28 x 0.83+3×31.28= 119.8024 AUD
For Metal work: 23.46 x 3+23.46×0.375= 79.1775 AUD
Time cost and compression impacts of working 6 days per week.
To undertake compression in this case, we would have to increase the number of days by 1 in each case:
For task 67:
New activity time= 5+5/6= 5.833 days
For activity 24:
New activity time= 3+1/2= 3.5 days
Hence suppose, we compress the 1st task (task 67) by additional 4hours per day and task 2 (task 24) by 3 hours per day and then we add an extra labour of 3 in each case;
The extra cost (assuming equipment cost negligible):
For Task 67:
And new activity time for task 67: 5+ 4/24×5= 5.83 days
For Task 24:
Activity time: 3+ 3/24×3= 3.375 days
And the labour implications:
For Mechanical: 31.28×0.83+3×31.28= 119.8024 AUD
For Masonry: 1.5×31.28+2×31.28= 109.48
Outline other ways to compress the project schedule
(i) We can do Project fast tracking in which activities can be merged as concurrent activities while choosing to delay some activities that may not be very impactful if delayed by some hours or days.
(ii) In crashing the project, we can increase the labour and equipment capacity so as to cover more within a short period.
(iii) We undertake time study beforehand to reveal the areas that are a bottleneck to the entire project and strategize on improving performance.
Reference
Scribd. (2018). Productivity Rate (Labor & Eqpt). [online] Available at: https://www.scribd.com/doc/151591149/Productivity-Rate-Labor-Eqpt [Accessed 7 Apr. 2018].
Free Membership to World’s Largest Sample Bank
To View this & another 50000+ free samples. Please put
your valid email id.
Yes, alert me for offers and important updates
Submit
Download Sample Now
Earn back the money you have spent on the downloaded sample by uploading a unique assignment/study material/research material you have. After we assess the authenticity of the uploaded content, you will get 100% money back in your wallet within 7 days.
UploadUnique Document
DocumentUnder Evaluation
Get Moneyinto Your Wallet
Total 5 pages
PAY 3 USD TO DOWNLOAD
*The content must not be available online or in our existing Database to qualify as
unique.
Cite This Work
To export a reference to this article please select a referencing stye below:
APA
MLA
Harvard
OSCOLA
Vancouver
My Assignment Help. (2019). Measurement For The Item Of Work. Retrieved from https://myassignmenthelp.com/free-samples/measurement-for-the-item-of-work.
“Measurement For The Item Of Work.” My Assignment Help, 2019, https://myassignmenthelp.com/free-samples/measurement-for-the-item-of-work.
My Assignment Help (2019) Measurement For The Item Of Work [Online]. Available from: https://myassignmenthelp.com/free-samples/measurement-for-the-item-of-work[Accessed 19 December 2021].
My Assignment Help. ‘Measurement For The Item Of Work’ (My Assignment Help, 2019)
My Assignment Help. Measurement For The Item Of Work [Internet]. My Assignment Help. 2019 [cited 19 December 2021]. Available from: https://myassignmenthelp.com/free-samples/measurement-for-the-item-of-work.
×
.close{position: absolute;right: 5px;z-index: 999;opacity: 1;color: #ff8b00;}
×
Thank you for your interest
The respective sample has been mail to your register email id
×
CONGRATS!
$20 Credited
successfully in your wallet.
* $5 to be used on order value more than $50. Valid for
only 1
month.
Account created successfully!
We have sent login details on your registered email.
User:
Password:
Worried about the originality of your academic paper? Get started with MyAssignmenthelp.com and receive a plagiarism-free solution at a reasonable price. You can ask the in-house experts to “check my paper for plagiarism” or request them to “write my paper for me” to get a plagiarism-free paper in your hand. The website offers proofreading services as well as paper writing support. In both cases, the experts at the site take significant measures to deliver a plagiarism-free solution. You can even use the online reference generator offered by the website to avoid plagiarism in your copy.
Latest Project Management Samples
div#loaddata .card img {max-width: 100%;
}
SBM 1201 Project Scope, Time And Cost Management
Download :
0 | Pages :
12
Course Code: SBM1201
University: Asia Pacific International College
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answer:
Introduction
This project plan deals with the development of a fuel-efficient HHO Generator. The HHO fuel cells may appear to provide high fuel efficiency to the users. Nevertheless, there are a few confinements and focuses to be seen, as given beneath. This is to clear up that there is NO 100% substitution of petroleum derivative by including HHO cell. HHO gas is otherwise called Brown Gas, yet this is to illuminate that HHO gas is n…
Read
More
Tags:
Australia Footscray Management organisational behviour University of New South Wales Masters in Business Administration
HS2061 Information Systems Project Management
Download :
0 | Pages :
9
Course Code: HS2061
University: Holmes Institute
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answer:
Case Overview:
The project owner of the Signed, sealed, delivered courier service is facing the problems of managing order of couriers in the synchronised manner. The project manager is incapable of managing central warehouse for the dispatching of products. The important information can be lost with the passage of time. The inventory management of the warehouse is the major concern for the owner of the company. He is looking forward …
Read
More
OPS 935 Project Management
Download :
0 | Pages :
11
Course Code: OPS935
University: University Of Wollongong
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answer:
Introduction
This essay explores the impacts of digital technologies on project management. It explores how adoption of digital technologies by companies for managing their project have affected their, project managers, human resource, business processes, timelines, deliverables, and practices of risk management, people management and quality management.
Impact of Digital technologies on Project Management Practices
Digital te…
Read
More
Tags:
Australia Saint Kilda Management International Management University of New South Wales Masters in Business Administration
ITC505 ICT Project Management
Download :
0 | Pages :
10
Course Code: ITC505
University: Charles Sturt University
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answers
Case Study- Social Media Research Center
Task-1: Project Charter
Project Objectives
The main objective of the project is to develop a web-based system within the organization “Social Media research Center”. It is analyzed that the Social Media research center wants to develop the web based system in order to connect people with the organization for promoting its research center. The web-based system that is developed conta…
Read
More
Tags:
Australia Alfredton Management IT Network Security University of New South Wales Masters in Business Administration
ITC505 ICT Project Management
Download :
0 | Pages :
7
Course Code: ITC505
University: Charles Sturt University
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answers
Part One- Project Name / Team / Description
Project Name:
RALS Solution
Team Name:
Consultants for RALS
Project Description:
RALS organizes show for the farmers and other related small business persons to display their latest technology equipment for betterment in the field of agriculture and crop production. The show has different types of stalls and other facilities for which many volunteers …
Read
More
Next