PAQM321 Project And Quality Management Assessment
0 Download10 Pages / 2,467 Words
Course Code: PAQM321
University: Kent Institute Australia
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Question:
Course Learning Outcomes addressed:Information strategy, Business strategy and planning and Technical strategy and planning
a. To gather, critically analyse, manage and present in meaningful ways information and data, and
b. To devise risk assessments when solving complex problems in local and global business environments Business change implementation and Business change management
a. To appraise and interpret the requirements of clients in order to solve complex business problems by designing and testing system modelling approaches Service design, Service transition and Service operation
a. To monitor, research and interpret the fast changing and global world of information technology in terms of hardware, networks, software, and tools Communication skills
a. To prepare design and system documentation and written reports
b. To elicit requirements from clients, discuss intermediate solutions and present oral reports as individuals and in teams Teamwork and self-management skillsa. To work collaboratively in small teams on a variety of large and small projects to produce models, software, documentation and reportsb. To take responsibility for their own time management delivering quality required material on time in dynamically changing technological and communication contexts whether as an individual or member of a small team.
Answer:
Scope of the project
The project scope includes:
Development of an information system for Bendigo Tours and travel
Providing facilities like online reservation, hotel reservation, catering, ticket delivery and more.
Syncing hotel reservation system with the present website
Integration of system with social media
The risk register that is developed for the stakeholders who are engaged with the information system development for Bendigo tours and travel is provided in the table that is provided below:
Stakeholders
Impact
Probability
Project manager
High
High
Project planner
High
Low
Application manager
Medium
Low
Developer
Medium
Medium
Database administrator
Medium
High
Coder
Medium
Low
Tester
Medium
Low
Quality analyst
Low
Low
Financial manager
Medium
Medium
Stakeholder management strategy
The strategies that are required to be adopted in order to mange the stakeholders who are involved with the information system development are listed below:
Stakeholder mapping: Before the initiation phase, stakeholder analysis is needed to be conducted for identifying the stakeholders. Identification and examination of various types of key factors including various types of proximity as per the project, demographics as well as interest in the project (Mok, Shen and Yang 2015). Gaining proper understanding of the internal stakeholders such as suppliers, contractors, shareholders and more are required.
Influence: Understanding the level of influence generally helps in allowing stakeholders to interact directly with the team members of the project. The influence range is broad from positive sentiment and supports activism against the project. For measuring the possible influence of the project stakeholders, determining the level of influence is important.
Determination of triggers: Stakeholders reacts in a way to various actions of the project by determining the triggers and mitigating various actions by avoiding preventable complaints (Schnackenberg and Tomlinson 2016). When the stakeholders experience the changes within the environment or business expectation then they generally create a reaction.
Team contract
The contract that is created for the project team mainly include information regarding team agreement, code of conduct and ground rules for a team.
Team agreement
The mission of the team is to work together as a unit so that the team members can be able to complete the project work on time.
The primary outcome and goals of the project team is to successfully complete the team assignment that is provided
Improving the understanding of the team members in the field of data managementTeam members must work as per the work that is assigned to them by taking proper decision in a group
The main purpose of the team is to work hard and achieve maximum efficiency
Code of conduct
Arriving on time to the meetings quite punctually
Finishing the assigned tasks quite effectively as well as efficiently
Complete the work diligently and honestly
Proper contribution should be provided to the members positively as well as equally.
Ground rules for communication
It is a necessity to understand the goals and objectives of communication
Keeping the discussion on any topic of communication quite concisely
Listening to the views of others and acknowledging the valid points which are made by the person
Financial analysis
The financial analysis that is mainly performed for the development of information system for the organization “Bendigo Tours and travel” is provided in the given table.
Discount Rate
6.5%
0
1
2
3
4
5
Total
Cost
$ 4,60,000.00
$ 55,000.00
$ 55,000.00
$ 55,000.00
$ 27,500.00
$ 27,500.00
$ 6,80,000.00
Discount Factor
0.94
0.88
0.83
0.78
0.73
Discounted Costs
$ 51,643.19
$ 48,491.26
$ 45,531.70
$ 21,376.38
$ 20,071.72
$ 1,87,114.26
Benefits
$ 3,20,000.00
$ 3,20,000.00
$ 3,20,000.00
$ 3,20,000.00
$ 3,20,000.00
$ 16,00,000.00
Discount Factor
0.94
0.88
0.83
0.78
0.73
Discounted Benefits
$ 3,00,469.48
$ 2,82,130.97
$ 2,64,911.71
$ 2,48,743.39
$ 2,33,561.87
$ 13,29,817.42
Discounted Benefits – Costs
$ 2,48,826.29
$ 2,33,639.71
$ 2,19,380.01
$ 2,27,367.00
$ 2,13,490.14
$ 11,42,703.16
Cumulative Benefits – Costs
$ 2,65,000.00
$ 2,65,000.00
$ 2,65,000.00
$ 2,92,500.00
$ 2,92,500.00
$ 13,80,000.00
ROI
6.11
NPV
6,82,703.16
SDLC model
Agile SDLC model can be utilized for this particular project as this project helps in promoting continuous iteration of testing and development throughout the entire software development life. The main reason behind using agile project methodology is that agile project helps in allowing the changes within the project and provides an opportunity to constantly refine as well as reprioritize the changes that are needed within the project (Peroni 2016). In addition to this, with the help of this project methodology, the entire project is broken down into number of manageable units so that the entire project team can be able to focus on high-quality development, collaboration as well as testing (Tavakoli, Gandomani and Ahmadi 2016). In addition to this, it is found that agile is one of the powerful tools that is mainly used for software development that not only helps in providing benefits to the project development team but also assists in giving number of important business-related benefits to the client.
The phases of the selected agile methodology for the development of the information system within the project is mainly elaborated below:
Conception phase: Projects are generally envisioned as well as prioritized in order to focus on the project goals and objectives.
Inception phase: In this phase, team members are identified, funding take place and other type of discussion are performed for the development of the website.
Iteration phase: In this phase, the development team mainly works in order to deliver the working of the entire software-based iteration (Elsayed et al. 2015).
Release phase: In this phase, quality of the project is checked and other activities like testing and documentation development is generally performed.
Production phase: In this particular phase, ongoing support to the software is generally provided (Sánchez 2015).
Retirement phase: This is the last phase of the project, in which the project activities are ended including the customer notification as well as migration.
Schedule trade off and float
On the basis of critical path method, schedule trade off is generally performed in order to calculate the float which is reflected in the below table.
WBS
Task Name
Duration
Total Slack
0
Implementation of information system for Bendigo Tours and travel
78 days
0 days
1
Conceptualization phase
11 days
0 days
1.1
Conservation with project team
3 days
0 days
1.2
Development of project proposal
2 days
0 days
1.3
Development of proper agreement
3 days
0 days
1.4
Determination of project stakeholders
2 days
0 days
1.5
Approval of project plan
1 day
0 days
2
Inception phase
21 days
0 days
2.1
Collecting ideas
4 days
63 days
2.2
Collecting review from the clients
3 days
0 days
2.3
Developing design
5 days
0 days
2.4
Checking project feasibility
3 days
0 days
2.5
Analyzing budget
5 days
0 days
2.6
Conducting meeting
4 days
0 days
2.7
Approval of final design
1 day
0 days
3
Iteration phase
36 days
0 days
3.1
Construction of prototype
3 days
0 days
3.2
Database development
5 days
0 days
3.3
Validation of code
4 days
0 days
3.4
Cross-browser testing
3 days
0 days
3.5
Optimization
2 days
0 days
3.6
Building web content
17 days
0 days
3.6.1
Developing navigation structure
1 day
0 days
3.6.2
Creating site content pages
1 day
0 days
3.6.3
International airline reservation and ticketing
2 days
25 days
3.6.4
Worldwide hotel reservation feature
2 days
0 days
3.6.5
Catering feature
2 days
0 days
3.6.6
Free ticket delivery
3 days
0 days
3.6.7
Camping services
2 days
0 days
3.6.8
Ground handling services
3 days
0 days
3.6.9
Conferences
3 days
12 days
3.7
Developing user experience
5 days
0 days
3.7.1
Updating details
2 days
0 days
3.7.2
Integrating with social media
3 days
0 days
4
Release phase
7 days
0 days
4.1
Web application access
3 days
0 days
4.2
Estimation of hardware and software
4 days
3 days
4.3
Testing and reviewing
3 days
0 days
5
Closure phase
4 days
0 days
5.1
Risk assessment
3 days
1 day
5.2
Quality management
3 days
0 days
5.3
Reviewing project
1 day
0 days
Communication plan
The communication plan that is developed for the development of information system is generally reflected in the table that is provided below:
Audience
Message
Vehicle
Frequency
Responsible
Team members
The project team members communicate the project objectives and goals so that the project team can be able to perform effectively.
Face to face
Once
Project manager
Project manager
The team leaders discuss the difficulties that are faced by the project team in order to develop the information system
Face to face, Email
Monthly
Team leaders
Project planner
The team leader provides project status report for providing information about project progress.
Face to face, Email
Weekly
Team leaders
Project manager
The financial manager provides information about the project finances to the project manager
Face to face, Email
Weekly
Project manager
Five potential risks and risk register
The potential risks and challenges that are related with the development of information system are generally reflected in the table below:
ID
Risk
Description
Consequence
Likelihood
Mitigation
R1
Improper schedule slippage
If the schedule of the project is not tracked on a regular basis, then it is quite difficult to finish the project on time.
Critical
Almost certain
The schedule of the project must be tracked on a regular basis for avoiding schedule slippage.
R2
Lack of resources
If sufficient project resources are provided then it is quite difficult to complete the project on time.
Major
Possible
The resources that are required for the project must be estimated before the project initiation phase.
R3
Improper construction of prototype
If the project prototype is not properly constructed then the system that will be developed will not function properly.
Major
Likely
The designed prototype must be checked on regular basis for avoiding technical issues.
R4
Inexperienced team members
If the team members who are involved with the project are not experienced then they face lot of difficulties in finishing the project work.
Moderate
Likely
Hiring experienced project team member is necessary for finishing the work of the project
Consequence
Likelihood
Insignificant
Minor
Moderate
Major
Critical
Rare
Unlikely
Possible
R2
Likely
R4
R3
Almost certain
R1
Monitoring and controlling project success
Week
Weekly status
Week 1
In week 1, conversation with the project team members is done and project proposal for the project is prepared.
Week 2
In week 2, proper agreement is prepared and the stakeholders who will be engaged with the project are identified.
Week 3
In week 3, proper ideas as well as review from the clients are collected.
Week 4
In week 4, project design is created and the feasibility of the project design is checked.
Week 5
In week 5, budget for the project is analyzed and proper meeting for the project is conducted.
Week 6
In week 6, navigation structure and site content pages of the website is developed.
Week 7
In week 7, feature of airline reservation and hotel reservation is created.
Week 8
In week 8, catering features as well as free ticket delivery feature is developed.
Week 9
In week 9, proper user experience for the website is mainly developed.
Week 10
In week 10, web application access is developed and the required software and hardware is developed.
Week 11
In week 11, information system that is developed is tested.
Week 12
In week 12, risk assessment and quality management is done for closing the project.
Bibliography
De Carvalho, M.M., Patah, L.A. and de Souza Bido, D., 2015. Project management and its effects on project success: Cross-country and cross-industry comparisons. International Journal of Project Management, 33(7), pp.1509-1522.
Diouf, D. and Boiral, O., 2017. The quality of sustainability reports and impression management: A stakeholder perspective. Accounting, Auditing & Accountability Journal, 30(3), pp.643-667.
Elsayed, H.A.G., Alharbi, A.N., AlNamlah, H. and Saba, T., 2015. Role of agile methodology in project management and leading management tools. J Bus Technov, 3, pp.188-193.
Kaiser, M.G., El Arbi, F. and Ahlemann, F., 2015. Successful project portfolio management beyond project selection techniques: Understanding the role of structural alignment. International Journal of Project Management, 33(1), pp.126-139.
Mok, K.Y., Shen, G.Q. and Yang, J., 2015. Stakeholder management studies in mega construction projects: A review and future directions. International Journal of Project Management, 33(2), pp.446-457.
Papke-Shields, K.E. and Boyer-Wright, K.M., 2017. Strategic planning characteristics applied to project management. International Journal of Project Management, 35(2), pp.169-179.
Peroni, S., 2016. A simplified agile methodology for ontology development. In OWL: Experiences and Directions–Reasoner Evaluation (pp. 55-69). Springer, Cham.
Sánchez, M.A., 2015. Integrating sustainability issues into project management. Journal of Cleaner Production, 96, pp.319-330.
Schnackenberg, A.K. and Tomlinson, E.C., 2016. Organizational transparency: A new perspective on managing trust in organization-stakeholder relationships. Journal of Management, 42(7), pp.1784-1810.
Tavakoli, Z., Gandomani, T.J. and Ahmadi, M., 2016. Knowledge Management in Agile Software Development: A Case Study of XP Agile Methodology. International Journal of Software Engineering and Technology, 2(1).
Todorovi?, M.L., Petrovi?, D.?., Mihi?, M.M., Obradovi?, V.L. and Bushuyev, S.D., 2015. Project success analysis framework: A knowledge-based approach in project management. International Journal of Project Management, 33(4), pp.772-783.
Free Membership to World’s Largest Sample Bank
To View this & another 50000+ free samples. Please put
your valid email id.
Yes, alert me for offers and important updates
Submit
Download Sample Now
Earn back the money you have spent on the downloaded sample by uploading a unique assignment/study material/research material you have. After we assess the authenticity of the uploaded content, you will get 100% money back in your wallet within 7 days.
UploadUnique Document
DocumentUnder Evaluation
Get Moneyinto Your Wallet
Total 10 pages
PAY 6 USD TO DOWNLOAD
*The content must not be available online or in our existing Database to qualify as
unique.
Cite This Work
To export a reference to this article please select a referencing stye below:
APA
MLA
Harvard
OSCOLA
Vancouver
My Assignment Help. (2020). Project And Quality Management Assessment. Retrieved from https://myassignmenthelp.com/free-samples/paqm321-project-and-quality-management-assessment.
“Project And Quality Management Assessment.” My Assignment Help, 2020, https://myassignmenthelp.com/free-samples/paqm321-project-and-quality-management-assessment.
My Assignment Help (2020) Project And Quality Management Assessment [Online]. Available from: https://myassignmenthelp.com/free-samples/paqm321-project-and-quality-management-assessment[Accessed 19 December 2021].
My Assignment Help. ‘Project And Quality Management Assessment’ (My Assignment Help, 2020)
My Assignment Help. Project And Quality Management Assessment [Internet]. My Assignment Help. 2020 [cited 19 December 2021]. Available from: https://myassignmenthelp.com/free-samples/paqm321-project-and-quality-management-assessment.
×
.close{position: absolute;right: 5px;z-index: 999;opacity: 1;color: #ff8b00;}
×
Thank you for your interest
The respective sample has been mail to your register email id
×
CONGRATS!
$20 Credited
successfully in your wallet.
* $5 to be used on order value more than $50. Valid for
only 1
month.
Account created successfully!
We have sent login details on your registered email.
User:
Password:
Writing a research paper is not a difficult task compared to understand how to cite research paper properly. Students get anxious when it comes to citing a paper. You would be delighted to know that MyAssignmenthelp.com has some of the best experts who can make sure your paper is properly cited. They have experiences on using different citation styles from APA referencing to Chicago style referencing. If you have any questions regarding how to do a research paper, contact our support team. They will help you to talk to our experts.
Latest Project Management Samples
div#loaddata .card img {max-width: 100%;
}
SBM 1201 Project Scope, Time And Cost Management
Download :
0 | Pages :
12
Course Code: SBM1201
University: Asia Pacific International College
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answer:
Introduction
This project plan deals with the development of a fuel-efficient HHO Generator. The HHO fuel cells may appear to provide high fuel efficiency to the users. Nevertheless, there are a few confinements and focuses to be seen, as given beneath. This is to clear up that there is NO 100% substitution of petroleum derivative by including HHO cell. HHO gas is otherwise called Brown Gas, yet this is to illuminate that HHO gas is n…
Read
More
Tags:
Australia Footscray Management organisational behviour University of New South Wales Masters in Business Administration
HS2061 Information Systems Project Management
Download :
0 | Pages :
9
Course Code: HS2061
University: Holmes Institute
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answer:
Case Overview:
The project owner of the Signed, sealed, delivered courier service is facing the problems of managing order of couriers in the synchronised manner. The project manager is incapable of managing central warehouse for the dispatching of products. The important information can be lost with the passage of time. The inventory management of the warehouse is the major concern for the owner of the company. He is looking forward …
Read
More
OPS 935 Project Management
Download :
0 | Pages :
11
Course Code: OPS935
University: University Of Wollongong
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answer:
Introduction
This essay explores the impacts of digital technologies on project management. It explores how adoption of digital technologies by companies for managing their project have affected their, project managers, human resource, business processes, timelines, deliverables, and practices of risk management, people management and quality management.
Impact of Digital technologies on Project Management Practices
Digital te…
Read
More
Tags:
Australia Saint Kilda Management International Management University of New South Wales Masters in Business Administration
ITC505 ICT Project Management
Download :
0 | Pages :
10
Course Code: ITC505
University: Charles Sturt University
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answers
Case Study- Social Media Research Center
Task-1: Project Charter
Project Objectives
The main objective of the project is to develop a web-based system within the organization “Social Media research Center”. It is analyzed that the Social Media research center wants to develop the web based system in order to connect people with the organization for promoting its research center. The web-based system that is developed conta…
Read
More
Tags:
Australia Alfredton Management IT Network Security University of New South Wales Masters in Business Administration
ITC505 ICT Project Management
Download :
0 | Pages :
7
Course Code: ITC505
University: Charles Sturt University
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answers
Part One- Project Name / Team / Description
Project Name:
RALS Solution
Team Name:
Consultants for RALS
Project Description:
RALS organizes show for the farmers and other related small business persons to display their latest technology equipment for betterment in the field of agriculture and crop production. The show has different types of stalls and other facilities for which many volunteers …