PLM240: Project Management Report
0 Download19 Pages / 4,609 Words
Course Code: PLM240
University: University Of Maryland
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: United States
Question:
1.Background Information about the Project
a) Project Purpose and Justification
b) Project Description and Key Deliverables
2.Project Scope
a) Project Requirements
b) Work Breakdown Structure (WBS)
3.Project Schedule
a) Gantt Chart with Resource Assignments
b) Project Network Diagram and Critical Path
c) Project Milestone
4.Project Cost
a)Project Costs
b)Project Budget
5.Project Stakeholders
a) Stakeholder Analysis
b) Communications Management
6.Project Risks
a) Project Success Measures
7.Justification of Organisational Capacity to Undertake the Project
Answer:
1.Background Information about the Project
a) The project is deployed for the development of the improved healthcare facilities by the development of a healthcare mobile application suitable for the improved services and treatment. The mobile application would help in easing the treatment facilities by forming the improved information processing. The patients, staffs and nurses would be able to employ the use of the application for facilitating the transfer of the information. The project of Development of Healthcare App for Koala City Council would allow the users for developing effective and improved operations.
The implication of the application for the treatment of the patients due to the project of Development of Healthcare App for Koala City Council would help in,
Increasing the capability of treatment facilities for the patients
Integrating the database so that communication can be eased
b) The project is formed for the development of treatment facility to the patients of Koala City Council by using the Healthcare application development. The main objective of the project is to form an effective start by introducing key stakeholders and reviewing project preliminary scope, assumptions, constraints, and milestones.
The key deliverables of the project are Healthcare Mobile Application, Project plan, Cost Estimation/Budget, Risk Management Plan, Communication Plan, and Stakeholder Analysis Plan.
2.Project Scope
a) The project of Development of Healthcare App for Koala City Council requires both human and material resources for the development of the healthcare application. The resources required for the project are listed below,
Human: Analyst, Documenter, Project Manager, Planner, Designer, Database Developer, Tester, Programmer, Engineer, and Trainer
Material: Software, Simulation Software, Database Software, Testing Tool, Programming Tools, and Network Tools
b) The work breakdown structure for the project of Development of Healthcare App for Koala City Council in organizational structure is given below,
3. Project Schedule
a) Gantt chart is a project planning diagram made from the table of the project schedule made in any specific software (Rodger et al., 2015). The implication of the project Gantt chart is implied for the improved project planning and documentation. The project Gantt chart is helpful for the deployment of the project schedule in an estimated table resource for the project. The project schedule for the project of Development of Healthcare App for Koala City Council with the resource allocation is shown in the table below,
WBS
Task Name
Duration
Start
Finish
Predecessors
Resource Names
0
Development of Healthcare App for Koala City Council
94 days
Mon 4/2/18
Thu 8/9/18
1
Project Initialization
15 days
Mon 4/2/18
Fri 4/20/18
1.1
Requirement Analysis
3 days
Mon 4/2/18
Wed 4/4/18
Analyst
1.2
Stakeholder Analysis
2 days
Thu 4/5/18
Fri 4/6/18
2
Analyst
1.3
Feasibility Analysis
2 days
Mon 4/9/18
Tue 4/10/18
3
Analyst
1.4
Initiation Documentation
4 days
Wed 4/11/18
Mon 4/16/18
4
Documenter
1.5
Charter Documentation
3 days
Tue 4/17/18
Thu 4/19/18
5
Documenter
1.6
Project Kick off meeting
1 day
Fri 4/20/18
Fri 4/20/18
6
Project Manager
2
Project Planning
16 days
Mon 4/23/18
Mon 5/14/18
2.1
Selection of plan methodology
2 days
Mon 4/23/18
Tue 4/24/18
7
Planner
2.2
Plan outline is formed
4 days
Wed 4/25/18
Mon 4/30/18
9
Planner
2.3
Plan is reviewed
2 days
Tue 5/1/18
Wed 5/2/18
10
Planner
2.4
Plan is completed
7 days
Thu 5/3/18
Fri 5/11/18
11
Planner
2.5
Plan Approval
1 day
Mon 5/14/18
Mon 5/14/18
12
Project Manager
3
App Designing
13 days
Tue 5/15/18
Thu 5/31/18
3.1
App design software is selected
2 days
Tue 5/15/18
Wed 5/16/18
13
Designer, Software[1]
3.2
User Interface is designed
5 days
Thu 5/17/18
Wed 5/23/18
15
Designer
3.3
Simulation of the design
3 days
Thu 5/24/18
Mon 5/28/18
16
Tester, Simulation Software[1]
3.4
Design Review
2 days
Tue 5/29/18
Wed 5/30/18
17
Designer
3.5
Design is approved
1 day
Thu 5/31/18
Thu 5/31/18
18
Engineer
4
App development
29 days
Fri 6/1/18
Wed 7/11/18
4.1
Database is created
5 days
Fri 6/1/18
Thu 6/7/18
19
Database Developer, Database Software[1]
4.2
Prototype Testing
3 days
Fri 6/8/18
Tue 6/12/18
21
Tester, Testing Tool[1]
4.3
Integration of the database
3 days
Wed 6/13/18
Fri 6/15/18
22
Database Developer
4.4
Programming of the application functions
7 days
Mon 6/18/18
Tue 6/26/18
23
Programmer, Programming Tools[1]
4.5
System Alignment
3 days
Wed 6/27/18
Fri 6/29/18
24
Engineer, Network Tools[1]
4.6
Black box testing for functions
2 days
Mon 7/2/18
Tue 7/3/18
25
Tester, Testing Tool[1]
4.7
White box testing for functions
2 days
Wed 7/4/18
Thu 7/5/18
26
Tester, Testing Tool[1]
4.8
System is reviewed
3 days
Fri 7/6/18
Tue 7/10/18
27
Engineer
4.9
Application development is completed
1 day
Wed 7/11/18
Wed 7/11/18
28
Engineer
5
Go Live Application
20 days
Thu 7/12/18
Wed 8/8/18
5.1
Application Launch Plan
2 days
Thu 7/12/18
Fri 7/13/18
29
Planner
5.2
Implementation of application launch plan
2 days
Mon 7/16/18
Tue 7/17/18
31
Engineer
5.3
Development of training manuals
3 days
Wed 7/18/18
Fri 7/20/18
32
Trainer
5.4
Training Programs are formed
2 days
Mon 7/23/18
Tue 7/24/18
33
Trainer
5.5
Training is provided
5 days
Wed 7/25/18
Tue 7/31/18
34
Trainer
5.6
Beta test of usage
3 days
Wed 8/1/18
Fri 8/3/18
35
Tester, Testing Tool[1]
5.7
Staff review is evaluated
2 days
Mon 8/6/18
Tue 8/7/18
36
Analyst
5.8
Application is launched for healthcare
1 day
Wed 8/8/18
Wed 8/8/18
37
Engineer
6
Project is Closed
1 day
Thu 8/9/18
Thu 8/9/18
38
Project Manager
The Gantt chart for the project of Development of Healthcare App for Koala City Council is shown below,
The project schedule and Gantt chart have shown that the project can be divided into Project Initialization, Project Planning, App Designing, App development, and Go Live Application. The project start date is Mon 4/2/18 and the end date is Thu 8/9/18 for the duration of 94 working days. The project has been expected to complete in 4 months of time with the application development activities running for 3 months and the application launching for 1 months of time. The project initialization comprises of requirement analysis, stakeholder analysis, feasibility analysis, initiation documentation, charter documentation, and project kick off meeting activities. The project planning comprises of selection of plan methodology, plan outline is formed, plan is reviewed, plan is completed, and plan approval.
The app designing comprises of app design software is selected, user interface is designed, simulation of the design, design review, and design is approved. The app development comprises of database is created, prototype testing, integration of the database, programming of the application functions, system alignment, black box testing for functions, white box testing for functions, system is reviewed, and application development is completed. The go live application comprises of application launch plan, implementation of application launch plan, development of training manuals, training programs are formed, training is provided, beta test of usage, staff review is evaluated, and application is launched for healthcare.
b) Project Network Diagram is made with the help of the drawing tools and the design include the project activities listed in a parallel box and connected in a sequential way (Kerzner, 2013). The project network diagram is helpful for listing out the activities in a diagram method for the alignment of the project diagram. The network diagram for the project of Development of Healthcare App for Koala City Council is given below,
The project network diagram is made for deploying the improved project management activities and the alignment of the project tasks (Olson & Anderson, 2016). The project alignment methodology is formed for forming the use of waterfall methodology and the integration of the project activities in a systematic and aligned method. The network diagram helps in forming a pictorial representation of the project activities along with project summary activities and the development iof the improved project activities. The integration of the project development methodology would allow the formation of the project activities in waterfall methodology for overcoming the deployment issues and considering the advanced processes.
The project planning structure is waterfall in approach and the activities of the project are sequential in nature. The project analysis is deployed for the deployment of the application and carrying out the alignment of the improved project operations. The critical path of the project is sequential and it is shown below,
c) The project milestone consists of the major attainable factors for the project that can be pointed out from the project schedule table (Burke, 2013). The milestones generally are the last activity of the project phase and they form the final closure of the project phase. The project initialization phase consists of project kick off meeting as the milestone event. The project planning phase consists of plan approval as the milestone event. The app designing phase consists of design is approved as the milestone event. The app development phase consists of application development is completed as the milestone event. The go live application phase consists of application is launched for healthcare as the milestone event.
WBS
Task Name
Duration
Start
Finish
1.6
Project Kick off meeting
1 day
Fri 4/20/18
Fri 4/20/18
2.5
Plan Approval
1 day
Mon 5/14/18
Mon 5/14/18
3.5
Design is approved
1 day
Thu 5/31/18
Thu 5/31/18
4.9
Application development is completed
1 day
Wed 7/11/18
Wed 7/11/18
5.8
Application is launched for healthcare
1 day
Wed 8/8/18
Wed 8/8/18
4.Project Cost
a) The project cost estimation is deployed for effective employment of the improved activities in an estimated project budget (Parker & Fox, 2016). The cost estimation can be employed by the use of the improved project analysis and development. The cost estimation is also helpful for listing the project operations in a table format along with the expected usage of the resources and the cost occurred for the activities. The cost estimating worksheet is implied with the parametric estimate factors of WBS ID, type of resource, cost variable, cost per unit, number of units, and cost estimate. The cost estimation would also involve the development of the total cost of completing the project by summing up the individual expense of the resources used for the project. The following table would show the cost estimation of the project,
COST ESTIMATING WORKSHEET
Project Name: Development of Healthcare App for Koala City Council
Parametric Estimates
WBS ID
Type of Resource
Cost Variable
Cost per Unit
Number of Units
Cost Estimate
1.1
Human
$/hr
$80.00
24
$1,920.00
1.2
Human
$/hr
$80.00
16
$1,280.00
1.3
Human
$/hr
$80.00
16
$1,280.00
1.4
Human
$/hr
$90.00
32
$2,880.00
1.5
Human
$/hr
$90.00
24
$2,160.00
1.6
Human
$/hr
$140.00
8
$1,120.00
2.1
Human
$/hr
$100.00
16
$1,600.00
2.2
Human
$/hr
$100.00
32
$3,200.00
2.3
Human
$/hr
$100.00
16
$1,600.00
2.4
Human
$/hr
$100.00
56
$5,600.00
2.5
Human
$/hr
$140.00
8
$1,120.00
3.1
Human
$/hr
$110.00
16
$1,760.00
3.1
Material
$/use
$3,199.00
1
$3,199.00
3.2
Human
$/hr
$110.00
40
$4,400.00
3.3
Human
$/hr
$80.00
24
$1,920.00
3.3
Material
$/hr
$2,799.00
1
$2,799.00
3.4
Human
$/hr
$110.00
16
$1,760.00
3.5
Human
$/hr
$140.00
8
$1,120.00
4.1
Human
$/hr
$110.00
40
$4,400.00
4.1
Material
$/use
$2,599.00
1
$2,599.00
4.2
Human
$/hr
$80.00
24
$1,920.00
4.2
Material
$/use
$1,499.00
1
$1,499.00
4.3
Human
$/hr
$110.00
24
$2,640.00
4.4
Human
$/hr
$130.00
56
$7,280.00
4.4
Material
$/use
$4,999.00
1
$4,999.00
4.5
Human
$/hr
$140.00
24
$3,360.00
4.5
Material
$/use
$3,299.00
1
$3,299.00
4.6
Human
$/hr
$80.00
16
$1,280.00
4.6
Material
$/use
$1,499.00
1
$1,499.00
4.7
Human
$/hr
$80.00
16
$1,280.00
4.7
Material
$/use
$1,499.00
1
$1,499.00
4.8
Human
$/hr
$140.00
24
$3,360.00
4.9
Human
$/hr
$140.00
8
$1,120.00
5.1
Human
$/hr
$100.00
16
$1,600.00
5.2
Human
$/hr
$140.00
16
$2,240.00
5.3
Human
$/hr
$80.00
24
$1,920.00
5.4
Human
$/hr
$80.00
16
$1,280.00
5.5
Human
$/hr
$80.00
40
$3,200.00
5.6
Human
$/hr
$80.00
24
$1,920.00
5.6
Material
$/use
$1,499.00
1
$1,499.00
5.7
Human
$/hr
$80.00
16
$1,280.00
5.8
Human
$/hr
$140.00
8
$1,120.00
6
Human
$/hr
$140.00
8
$1,120.00
Total Cost Estimated
$99,931.00
b) The project budget can also be calculated by considering the expense of the individual project phases in the estimated time duration. The project budget estimation is implied for the calculating the all over resource usage in the individual project phase and then calculate the total cost of the project. The following is a project budget estimation table,
Project Budget Estimation
Project Name: Development of Healthcare App for Koala City Council
Phase of Project
Resource Usage
Resource Type
Cost
Project Initialization
120 hrs
Human
$10,640.00
Project Planning
128 hrs
Human
$13,120.00
App Designing
104 hrs
Human
$10,960.00
2
Material
$5,998.00
App development
232 hrs
Human
$26,640.00
5
Material
$15,394.00
Go Live Application
160 hrs
Human
$14,560.00
1
Material
$1,499.00
Project is Closed
8 hrs
Human
$1,120.00
Total Budget
$99,931.00
5.Project Stakeholders
a) The stakeholder analysis is done for ensuring that the project would comprise of the development of the improved communication in the organization (Heagney, 2012). The project of forming the improved project activities would require the deployment of the project analysis and deployment. The stakeholders of the project are Analyst, Documenter, Project Manager, Planner, Designer, Database Developer, Tester, Programmer, Engineer, and Trainer. They are responsible for the various activities of the project as listed below,
Project Stakeholder
Activities Involved in
Client- Koala City Council
Sponsoring the project
Analyst
Requirement Analysis
Stakeholder Analysis
Feasibility Analysis
Staff review is evaluated
Documenter
Initiation Documentation
Charter Documentation
Project Manager
Project Kick off meeting
Plan Approval
Project is Closed
Planner
Selection of plan methodology
Plan outline is formed
Plan is reviewed
Plan is completed
Application Launch Plan
Designer
App design software is selected
User Interface is designed
Design Review
Database Developer
Database is created
Integration of the database
Tester
Simulation of the design
Prototype Testing
Black box testing for functions
White box testing for functions
Beta test of usage
Programmer
Programming of the application functions
Engineer
Design is approved
System Alignment
System is reviewed
Application development is completed
Implementation of application launch plan
Application is launched for healthcare
Trainer
Development of training manuals
Training Programs are formed
Training is provided
Patients, Staffs and Nurses
Users of the Application
STAKEHOLDER ANALYSIS MATRIX
Project Title: Development of Healthcare App for Koala City Council
Date Prepared: 14th January, 2018
Project Manager and Contractor
Client- Koala City Council
Patients, Staffs and Nurses
Analyst, Documenter, Planner, Designer, Database Developer, Tester, Programmer, Engineer, and Trainer
Interest
The stakeholder analysis comprises of the various stakeholders grouped in terms of the interest and the power in the project operations. The stakeholder analysis has classified the project stakeholders in four sections namely High Power-Low Interest, High Power-High Interest, Low Power-High Interest, and Low Power-Low Interest. The project managers and contractors of the project have high power and low interest in the project activities. The client of the project (Koala City Council) acts as the stakeholder with high power and high interest. The patients, staffs and nurses acts as the stakeholder with low power and low interest. The project team members (such as analyst, documenter, planner, designer, database developer, tester, programmer, engineer, and trainer) act as the stakeholder with low power and high interest.
b) Communication Management is implied for forming the effective transfer of the information within the involved project stakeholders (Rodger et al., 2015). The stakeholders of the project are aligned with the development of the improved communication management. The transfer of the information is aligned for the management of the project activities and carrying out the specific analysis of the project operations. The communication management plan for the project is given below,
COMMUNICATIONS MANAGEMENT PLAN
Project Title: Development of Healthcare App for Koala City Council
Date Prepared: 14th January, 2018
href=”#Stakeholder” title=”List the people or the groups of people who should receive project information.” Stakeholder
href=”#Information” title=”Describe the information to be communicated: For example, status reports, project updates, meeting minutes, etc.” Information
href=”#Method” title=”Describe how the information will be delivered. For example, e-mail, meetings, Web meetings, etc.” Method
href=”#Timing_or_Frequency” title=”List how often the information is to be provided or under what circumstances.” Timing or Frequency
href=”#Sender” title=”Insert the name of the person or the group that will provide the information.” Sender
Project Client
Project progress, resource exhaustion, and activities rescheduling
Board Meetings
Monthly
Project Manager
Project Team
Requirements of the project and the activity scheduling
Kick off meetings
Once
Project Manager
Users
Process of using the healthcare application and detailed analysis of the functions
Training Manuals
Once
Trainer
Project Manager
Technical requirements, complexities, and probable issues along with required solutions.
Project Progress Reports
Weekly
Engineer
Engineer
Functionality of the application is as expected or not
Test Results and Reports
Once
Tester
The table has shown that individual stakeholder of the project requires specific type of communication medium for a specific objective. The communication is implied for the management of the data transfer and implies improved conversation within the project activities. The project client can discuss with the project manager about project progress, resource exhaustion and activities rescheduling through board meetings on a monthly basis. The Project Team can discuss about the Requirements of the project and the activity scheduling through the kick off meetings once throughout the project lifecycle with the project manager. The users can discuss about the process of using the healthcare application and detailed analysis of the functions through the training manuals once throughout the project lifecycle with the trainer. The project manager can discuss the technical requirements, complexities, and probable issues along with required solutions through the project progress reports weekly throughout the project lifecycle with the engineer. The engineer can discuss the functionality of the application is as expected or not through the test results and reports once throughout the project lifecycle with the tester.
6.Project Risks
Project Risk Analysis is developed for ensuring that the effective and improved project operations are deployed for achieving the desired solutions (Bull et al., 2016). The project risk analysis is employed for analysing the risk factors and developing improved solutions for overcoming the probability of occurrence of the issues. The project would comprise of developing supportive plan for the application development so that the users can get the benefit of the faster health support. The risk register for the project is shown below,
RISK REGISTER
Project Title: Development of Healthcare App for Koala City Council
Date Prepared: 14th January, 2018
href=”#Risk_ID” title=”Enter a unique risk identifier.” Risk ID
href=”#Risk_Statement” title=”Describe the risk event or condition. A risk statement is usually phrased as “EVENT may occur, causing IMPACT” or “If CONDITION exists, EVENT may occur, leading to EFFECT.”” Risk Statement
href=”#Probability” title=”Determine the likelihood of the event or condition occurring.” Probability
href=”#Impact” title=”Describe the impact on one or more of the project objectives.” Impact
href=”#Score” title=”If you are using numeric scoring, multiply the probability times the impact to determine the risk score. If you are using relative scoring then combine the two scores (such as high-low or medium-high).” Score
href=”#Response” title=”Describe the planned response strategy to the risk or condition.” Response
Scope
Quality
Schedule
Cost
1841
Incompatible Data is resulted in forming the issues in completion of the application
3
4
4
3
5
19
Data management should be implied for dealing with the issues of the incompatible data
1842
Errors in programming is resulted due to the issues in program development policy
3
5
3
2
5
18
The programming errors are sorted with the deployment of programming methods
1843
Application not working would be resulted due to inconvenient issues
1
3
5
3
4
16
Appropriate testing is helpful for overcoming the probability of the issues in working
1844
Cost Overrun is resulted when the activities of the project would exhaust more resources
4
2
3
5
4
18
Provisional budget allocation should be used for forming the support to the cost management
1845
Time Delay is resulted when the project activities cannot be completed in estimated time.
5
3
5
3
5
21
The issues in project time delay can be sorted by following a specific project plan
a)
The project success can be measured with the help of the analysing the project outcomes in terms of deliverable success, process success, and stakeholder success. The deliverable success can be measured by the help of the calculating the project requirements that have been met. The project comprises of a key deliverable and some subsidy deliverables that are required for successful project completion. The achievement of these deliverables is also a measure of the project progress and success. The process success can be measured in terms of the method of managing and completing the project. The project management factors like timeline, cost estimation, communication, and control elements can be used for the analysis of the project success. The stakeholder success is more of a subjective measure type as it includes the coordination and communication in the project. The project success is dependent on the achievement of the client’s expectation from the project.
7.Justification of Organisational Capacity to Undertake the Project
Kick-off Meeting
20th April, 2018
Project Name: Development of Healthcare App for Koala City Council
Meeting Objective: Get the project off to an effective start by introducing key stakeholders and reviewing project preliminary scope, assumptions, constraints, and milestones.
Agenda: Development of the Healthcare Mobile Application for Koala City Council that would help them for providing better treatment to the patients
Introduction of attendees
The project kickoff meetings would be organized by the project manager and the attendees of the meetings would be the project team comprising of analyst, documenter, planner, designer, database developer, tester, programmer, engineer, and trainer.
Review of project preliminary scope
Brief Scope Definition: The project scopes to the development of treatment facility to the patients of Koala City Council by using the Healthcare application development
Project Deliverables: Healthcare Mobile Application, Project plan, Cost Estimation/Budget, Risk Management Plan, Communication Plan, and Stakeholder Analysis Plan
Project Success Criteria: The project success criteria involve the project deliverable success, process success, and stakeholder success.
Review of initial project stakeholder analysis
The initial project stakeholder analysis has yielded in client of the project (Koala City Council), patients, staffs and nurses, and project team as the primary stakeholders of the project.
Review of initial project constraints
The initial constraints of the project are time, budget, and technology dependency as the project is an IT based
Review of initial project milestones
The initial project milestones comprise of holding project kickoff meetings, developing an effective project plan, and designing the application for the healthcare.
Action items for next meeting
The next meetings would comprise of dividing the project work in terms of the improved change management and scope management planning
Introduction:
The project of the Development of Healthcare App for Koala City Council is implied for the development of the improved facilities for the deployment of the project integration and development. The following assignment is a project management plan developed for the project of Healthcare Application Development for improving the facilities of the treatment of the patients. The assignment comprises of developing project charter, complete stakeholder analysis and communication plan, complete project scope, WBS for the project, Gantt chart for the project, project cost benefit analysis, network diagram and critical path, planned budget, and risk identification.
References:
Bailey, D. (2015). Business continuity management into operational risk management: Assimilation is imminent… resistance is futile!. Journal of business continuity & emergency planning, 8(4), 290-294.
Bull, J. W., Jobstvogt, N., Böhnke-Henrichs, A., Mascarenhas, A., Sitas, N., Baulcomb, C., … & Carter-Silk, E. (2016). Strengths, weaknesses, opportunities and threats: A SWOT analysis of the ecosystem services framework. Ecosystem Services, 17, 99-111.
Burke, R. (2013). Project management: planning and control techniques. New Jersey, USA.
Caruana, A. (2016). A business continuity plan maturity index: a comparative study of Maltese licensed financial services firms (Bachelor’s thesis, University of Malta).
Cook, J. (2015). A six-stage business continuity and disaster recovery planning cycle. SAM Advanced Management Journal, 80(3), 23.
Davies, R., & Harty, C. (2013). Implementing ‘Site BIM’: a case study of ICT innovation on a large hospital project. Automation in Construction, 30, 15-24.
Gido, J. & Clements, J.P., (2014). Successful project management. Nelson Education.
Gozman, D., Wilcocks, L., Kovacevic, M., & Craig, A. (2017). Preparing for the wolf: sustainability through business continuity management. Intelligent Sourcing, (3), 50-63.
Heagney, J., (2012). Fundamentals of project management. AMACOM Div American Mgmt Assn.
Heldman, K., (2013). PMP: project management professional exam study guide. John Wiley & Sons.
Henderson, C., Klimas, J., Dunne, C., Leddin, D., Meagher, D., O’Toole, T., & Cullen, W. (2014). Key performance indicators for mental health and substance use disorders: a literature review and discussion paper. Mental Health and Substance Use, 7(4), 407-419.
Hills, M. (2016). Being resilient: business continuity principles for vetinary practice. In Practice, 38(10), 484-486.
H?ebí?ek, J., Soukopová, J., Štencl, M., & Trenz, O. (2014). Corporate key performance indicators for environmental management and reporting. Acta Universitatis Agriculturae et Silviculturae Mendelianae Brunensis, 59(2), 99-108.
Kerzner, H.R., (2013). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Kozma, R. B., & Vota, W. S. (2014). ICT in developing countries: Policies, implementation, and impact. In Handbook of research on educational communications and technology (pp. 885-894). Springer New York.
Kroczek, A., van Stam, G., & Mweetwa, F. (2013). Stakeholder theory and ICT in rural Macha, Zambia. In International Conference on ICT for Africa.
Leach, L. P. (2014). Critical chain project management. Artech House.
Marchewka, J.T., (2014). Information technology project management. John Wiley & Sons.
Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking project management performance and project success. International Journal of Project Management, 32(2), 202-217.
Nawi, H. S. A., Rahman, A. A., & Ibrahim, O. (2012). Government ICT project failure factors: project stakeholders’ views. Journal of Research and Innovation in Information System, 2, 69-77.
Olson, A., & Anderson, J. (2016). Resiliency scoring for business continuity plans. Journal of business continuity & emergency planning, 10(1), 31-43.
Parker, E., & Fox, A. (2016). Changing Perceptions About Business Continuity Planning (BCP) in Communities Around Mounts Bay in Cornwall, UK.
Parmenter, D. (2015). Key performance indicators: developing, implementing, and using winning KPIs. John Wiley & Sons.
Peltier, T. R. (2013). Information security fundamentals. CRC Press.
Phillips, J. (2013). PMP, Project Management Professional (Certification Study Guides). McGraw-Hill Osborne Media.
Podgórski, D. (2015). Measuring operational performance of OSH management system–A demonstration of AHP-based selection of leading key performance indicators. Safety Science, 73, 146-166.
Rodger, J. A., Bhatt, G., Chaudhary, P., Kline, G., & McCloy, W. (2015). The Impact of Business Expertise on Information System Data and Analytics Resilience (ISDAR) for Disaster Recovery and Business Continuity: An Exploratory Study. Intelligent Information Management, 7(04), 223.
Rowell, C.J., (2016). Book Review: Project Management for Information Professionals. Library Resources & Technical Services, 60(4), pp.280-281.
Sahebjamnia, N., Torabi, S. A., & Mansouri, S. A. (2015). Integrated business continuity and disaster recovery planning: Towards organizational resilience. European Journal of Operational Research, 242(1), 261-273.
Schumann, C.A., Gerischer, H., Tittmann, C., Orth, H., Xiao, F., Schwarz, B. and Schumann, M.A., (2014). Development of International Educational Systems by Competence Networking based on Project Management. Procedia-Social and Behavioral Sciences, 119, pp.192-201.
Schwalbe, K., (2015). Information technology project management. Cengage Learning.
Snedaker, S. (2013). Business continuity and disaster recovery planning for IT professionals. Newnes.
Stark, C. G., & Willemse, A. (2016, April). Maintaining Business Continuity During the Ebola Crisis. In SPE International Conference and Exhibition on Health, Safety, Security, Environment, and Social Responsibility. Society of Petroleum Engineers.
Torabi, S. A., Soufi, H. R., & Sahebjamnia, N. (2014). A new framework for business impact analysis in business continuity management (with a case study). Safety Science, 68, 309-323.
Verzuh, E. (2015). The fast forward MBA in project management. John Wiley & Sons
Walker, A. (2015). Project management in construction. John Wiley & Sons
Wallace, M., & Webber, L. (2017). The disaster recovery handbook: A step-by-step plan to ensure business continuity and protect vital operations, facilities, and assets. AMACOM Div American Mgmt Assn.
Xing, J., & Zio, E. (2016, September). An integrated framework for business continuity management of critical infrastructures. In ESREL 2016.
Free Membership to World’s Largest Sample Bank
To View this & another 50000+ free samples. Please put
your valid email id.
Yes, alert me for offers and important updates
Submit
Download Sample Now
Earn back the money you have spent on the downloaded sample by uploading a unique assignment/study material/research material you have. After we assess the authenticity of the uploaded content, you will get 100% money back in your wallet within 7 days.
UploadUnique Document
DocumentUnder Evaluation
Get Moneyinto Your Wallet
Total 19 pages
PAY 12 USD TO DOWNLOAD
*The content must not be available online or in our existing Database to qualify as
unique.
Cite This Work
To export a reference to this article please select a referencing stye below:
APA
MLA
Harvard
OSCOLA
Vancouver
My Assignment Help. (2020). Project Management Report. Retrieved from https://myassignmenthelp.com/free-samples/plm240-project-management-report.
“Project Management Report.” My Assignment Help, 2020, https://myassignmenthelp.com/free-samples/plm240-project-management-report.
My Assignment Help (2020) Project Management Report [Online]. Available from: https://myassignmenthelp.com/free-samples/plm240-project-management-report[Accessed 19 December 2021].
My Assignment Help. ‘Project Management Report’ (My Assignment Help, 2020)
My Assignment Help. Project Management Report [Internet]. My Assignment Help. 2020 [cited 19 December 2021]. Available from: https://myassignmenthelp.com/free-samples/plm240-project-management-report.
×
.close{position: absolute;right: 5px;z-index: 999;opacity: 1;color: #ff8b00;}
×
Thank you for your interest
The respective sample has been mail to your register email id
×
CONGRATS!
$20 Credited
successfully in your wallet.
* $5 to be used on order value more than $50. Valid for
only 1
month.
Account created successfully!
We have sent login details on your registered email.
User:
Password:
MyAssignmenthelp.com delivers assignment help to millions of students of USA. We have in-house teams of assignment writers who are experts on wide ranges of subjects. We have appointed teams of native writers who provide assignment help to students in New York City and all over the USA. They are skilled assignment writers who successfully cater to search terms like do my assignment in the USA
Latest Project Management Samples
div#loaddata .card img {max-width: 100%;
}
SBM 1201 Project Scope, Time And Cost Management
Download :
0 | Pages :
12
Course Code: SBM1201
University: Asia Pacific International College
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answer:
Introduction
This project plan deals with the development of a fuel-efficient HHO Generator. The HHO fuel cells may appear to provide high fuel efficiency to the users. Nevertheless, there are a few confinements and focuses to be seen, as given beneath. This is to clear up that there is NO 100% substitution of petroleum derivative by including HHO cell. HHO gas is otherwise called Brown Gas, yet this is to illuminate that HHO gas is n…
Read
More
Tags:
Australia Footscray Management organisational behviour University of New South Wales Masters in Business Administration
HS2061 Information Systems Project Management
Download :
0 | Pages :
9
Course Code: HS2061
University: Holmes Institute
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answer:
Case Overview:
The project owner of the Signed, sealed, delivered courier service is facing the problems of managing order of couriers in the synchronised manner. The project manager is incapable of managing central warehouse for the dispatching of products. The important information can be lost with the passage of time. The inventory management of the warehouse is the major concern for the owner of the company. He is looking forward …
Read
More
OPS 935 Project Management
Download :
0 | Pages :
11
Course Code: OPS935
University: University Of Wollongong
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answer:
Introduction
This essay explores the impacts of digital technologies on project management. It explores how adoption of digital technologies by companies for managing their project have affected their, project managers, human resource, business processes, timelines, deliverables, and practices of risk management, people management and quality management.
Impact of Digital technologies on Project Management Practices
Digital te…
Read
More
Tags:
Australia Saint Kilda Management International Management University of New South Wales Masters in Business Administration
ITC505 ICT Project Management
Download :
0 | Pages :
10
Course Code: ITC505
University: Charles Sturt University
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answers
Case Study- Social Media Research Center
Task-1: Project Charter
Project Objectives
The main objective of the project is to develop a web-based system within the organization “Social Media research Center”. It is analyzed that the Social Media research center wants to develop the web based system in order to connect people with the organization for promoting its research center. The web-based system that is developed conta…
Read
More
Tags:
Australia Alfredton Management IT Network Security University of New South Wales Masters in Business Administration
ITC505 ICT Project Management
Download :
0 | Pages :
7
Course Code: ITC505
University: Charles Sturt University
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answers
Part One- Project Name / Team / Description
Project Name:
RALS Solution
Team Name:
Consultants for RALS
Project Description:
RALS organizes show for the farmers and other related small business persons to display their latest technology equipment for betterment in the field of agriculture and crop production. The show has different types of stalls and other facilities for which many volunteers …