PRJM6000 Project Management

0 Download11 Pages / 2,724 Words

Course Code: PRJM6000
University: Curtin University

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Question:
Aim of Assignment:

Create a Project Charter, Requirements Traceability Matrix & Work Break Down Structure with Activities
Apply scope change management processes
Demonstrate understanding of project planning through the analysis of a case study 

[Note: Topic Notes 4(Initiation), 5 (Project Planning) and 6 (Scope Management) provide the background to complete this assignment) 
PART A
PROJECT CHARTER, WBS/Activities, SCOPE CHANGES 
[NOTE: Part I is a practical assignment. No academic references are required. It is not as a piece of academic writing. The Charter, Requirements Traceability Matrix and WBS with Activities must be written as formal project documents
Project Question/Topic: Construction of a Play ground
1. Produce a PROJECT CHARTER, using the template herein 

Problem / Opportunity Statement 
Strategic Alignment 
Benefits (6 marks), KPIs 
Deliverables (6 marks), High-level Requirement(s) , Exclusions 
Cost, Timeframe, Risks, (0) (no marks – just provides experience of completing a full charter) 

2. Produce a REQUIREMENTS TRACEABILITY MATRIX using the template herein, list 4 requirements then trace to features in the final deliverables  .
 
3. Create a WORK BREAKDOWN STRUCTURE with ASSOCIATED ACTIVITIES using the template herein: (list format, not chart format). (Note: the WBS must contain at least 15 work packages. If you have a large project, provide the top-level elements, and decompose 1, 2 or 3 of these elements so that at least 15 work packages are created .
 
4. Describe a possible SCOPE CHANGE requested by the sponsor. Fully evaluate the requested change. Produce and explain the revised sections of WBS, assuming that the change is accepted .
PART B
CASE STUDY: “Goal Definition and Performance Indicators in Soft Projects” (See separate handout) 
In answering the case study, make any necessary but reasonable assumptions. Support any answers wil direct reference to the text in the case study 
1. What are the :

Deliverable(s ) 
Benefits (4 marks). And suggest one suitable KPI for one of the benefits 
Strategic alignment 

2. Describe one specific project planning problem encountered in this project, and how it may have been avoided or better managed.
3. Describe one specific example of good project planning in the project.  
Answer:
Part A 

PROJECT CHARTER

Sponsor: ABC Limited

Project Title: ABC Revamp Project (ABP)

Prepared by:

Date: 15th January 2015

Problem/Opportunity Statement:
ABC Limited is a Singapore based firm that is into logistics management services. Services provided by the company include warehousing, logistics, contained deport management and transport management. Its clients include both local and international organizations like Mitsui O.S.K. Lines and A.P. Moller-Maersk A/S.
The valuation of the company is more than $1 billion after 30 years of working. The aim of this project is the enhance the IT infrastructure of the security unit of the company which operates with the offshore marine for the oil and gas distribution. For this revamp, the total budget allotted is SGD 90,000 and the specifications are approved. The schedule is also allotted for a definite period to achieve the targets of this project.

Key Deliverables
The key deliverables of this revamping project include:
·         Windows 7 installed with the latest antivirus/security software over all the workstations.

Data back up and data restoration should be done during the installation.
The weekly status report of project’s progress should be prepared and discussed at team meetings.
Record action items discussed in meeting on Minutes of Meeting (MOM) and follow up with it thereafter.
Project Plan is to be prepared and approval to be taken for that
A formal sign off has to be provided by Higher management
The resources are required to be identified and roles and responsibility assigned.
The project plan would be shared by project manager
The project signoff for delivery items and time by the Project Manager

 Key Requirements
 The project have certain technical requirements:

The Risk Mitigation Plan preparation and review of this plan by a dedicated team before the actual enhancement is carried out
Maintaining of company data and resources integrity
A centralized server must store data such that users can retrieve this data only after they are verified and authorized.
Development of a stable and secure platform.
To perform routine operations of the company.
Technical training and motivation for the company employees

 
 Exclusions

Delivery: The required deliveries of project items as have to be made as per specified project timelines.
Resources: The project has to be completed using resources approved  by the customer.
Budget: The project has to complete all deliveries within the allotted budget and if additional resources are required, approvals have to be taken for additional budget
Time: The project has to follow the timelines when completing requirements. If additional resources are needed to adhere to these timelines, it can increase costs and the project may not remain feasible.
Resources: Resources that are skilled must only be deployed on the project for delivering assignments as they have to adhere to schedule and at the same time deliver quality.

Benefit
· Data Backup
· removal of operation bottlenecks

KPIs
· Backup data can be used in case of disaster through a              recovery process.
· Windows server 2010 would be used for streamlining the           operations and removing blockages by 70%.

Strategic Alignment
The project is suggested for the company with an aim to satisfy their growing needs. It must facilitate business processes and increases the company revenues. The company should either perform as pr customer expectations or should exceed them.

Approximate Cost
 USD 1,00,000

Approximate Timeframe
4 months

Key Risks
·         Increases license cost.
 
APPROVAL                 Yes      /       No
Authority:           ______________________________                                  Date:____________
                                 Sponsor

Requirements Traceability Matrix 

Product requirement

Deliverable component

Install Windows server 2010

windows server 2010 to be installed on all computers

Install Anti-virus

An updated version of anti-virus has to be installed on all machines

Network connectivity

Full network access to be provided to all machines

Upgrade software

All software should be upgrades on all systems.

Work Breakdown Structure
 

WBS

Task Name

Duration

1

IT Infrastructure Enhancement

190 days

1.1

  Planning

39 days

1.1.1

            Requirement Analysis

5 days

1.1.2

             Feasibility study & Feasibility Analysis Report Submission

5 days

1.1.3

            Creation of Project Plan

3 days

1.1.4

            Finalize the list of delivery items

3 days

1.1.5

            Prepare communication plan

5 days

1.1.6

            Creation of Test Plan

5 days

1.1.7

            Creation of Change Request Plan

5 days

1.1.8

            Prepare Risk Management & Mitigation Plan

5 days

1.1.9

            Signoffs

3 days

1.2

  Design & Analysis

85 days

1.2.1

            Hardware Configuration

30 days

1.2.1.1

            Perform compatibility study

10 days

1.2.1.2

              Perform market survey

7 days

1.2.1.3

            Creation of configuration Plan (Computers)

5 days

1.2.1.4

            Submission of material – bill

5 days

1.2.1.5

            Approval on the bill Amount

3 days

1.2.2

            Vendor Selection

45 days

1.2.2.1

            Submission of tender for hardware

15 days

1.2.2.2

            Checklist preparation for vendor selection

5 days

1.2.2.3

            Identify hardware vendors

5 days

1.2.2.4

            Set-up

20 days

1.2.3

            Data Backup

10 days

1.3

  Purchase & Store

36 days

1.3.1

            Raise purchase order for hardware

11 days

1.3.1.1

            Checking the quality of the hardware

5 days

1.3.1.2

            Transfer the parts in the warehouse

6 days

1.3.2

            Install

25 days

1.3.2.1

            Machine identifications for hardware upgrade

4 days

1.3.2.2

            Software installation on identified machines

3 days

1.3.2.3

            Demo Presentation to the company management

3 days

1.3.2.4

            Perform Enhancement to the client

15 days

1.4

  Test and deployment

30 days

1.4.1

            Machine Test

24 days

1.4.1.1

            Machine Portability Testing

20 days

1.4.1.2

            Sign-offs

4 days

1.4.2

            Network testing

6 days

1.4.2.1

            Check the connectivity and data flow in machine placed on the network

3 days

1.4.2.2

            Sign-offs

3 days

 Scope Change Process 

Change Request: Domain networking

Project:  Revamp Project

Date: 20/01/15

Change Requestor: Management board

Change No: 1

Change Category (Check all that apply):
? Schedule      ? Cost ? Scope           ? Requirements/Deliverables
? Testing/Quality        ? Resources   
 

Does this Change Affect (Check all that apply):
? Corrective Action    ? Preventative Action ? Defect Repair          ? Updates
? Other

Describe the Change Being Requested:
One of the change requested is the addition of a security layer in the upgraded machines. The machines have to be placed on the company network and all the connecting services like mailing and file hosting have to be banned on these machines. The changes required are important to the company as they are related to security which is crucial aspect of the company. Significant time as well as efforts would be needed to make these changes. The changes would prevent employees for making use of company systems for personal use. Thus, these systems would be safe and the security solutions that would be enabled would further strengthen the security by preventing it from virus attacks. The transferring of the domain on which services would be placed would require additional port for support from the server. This would require construction of port holders for all the systems. On upgraded machines, CISCO agent would also be provided.
 

Describe the Reason for the Change:
Security has been a major concern for the company for long and thus, an upgrading with addition of security layer was sought. The company systems also faced virus attacks in past due to the lack of proper security. The company has planned to upgrade one unit as a pilot. After this installation, it was realized that more than one employees were using a single system. Moreover, some of them were not well accustomed to working machines and thus, there was a risk that they could end up installing an unofficial software or do personal activities like emailing. This would make the system vulnerable. Thus, changes in registry would not be allowed such that users can only open the company permitted websites.
 

Alternatives Considered:
Requested change can be managed without the allotment of additional resource and thus, no alternative is suggested.

Technical Changes Required for implementation:
·         The network engineer would be given responsibility for installing CISCO software on the systems
·         Additional ports that are required and the CISCO software would be purchased

Risks due to these Change:
·         There can be added cost to the budget due to additional port requirements.

Estimated Resources and Costs for Implementing Change:
·         Resources would be used for ports set-up and CISCO installation
·         The cost of the change is $50,000.

Disposition:
? Approve       ? Reject          ? Defer

Justification of Approval, Rejection, or Deferral:
Reason for change is logical.

 Revised section of WBS 
 

WBS ID

Task Name

1.5

Domain networking

1.5.1

Purchase ports and set-up materials

1.5.2

Identify port locations

1.5.3

Identify and set-up ports

1.5.4

Identify server machine

1.5.5

Set-up server machine

1.5.6

Connect machine ports to server ports

1.5.7

Place machines on company domain

1.5.8

Install CISCO software

1.5.9

Test machines

1.5.10

Sign-offs

Part B:
Outputs
The subsequent outputs are the result of the project-

Low and high level necessities
Plan for allocating resources with description of the job
Plan of the project
Results of market research
Controlling procedures. 

Advantages
The requirement for the aggressive system of information was caused due to the tactical pro-notation of the tourism focused government established society, located in Canada. The main aim of the system was the generation of timely and high quality intelligence which would assist the numerous managers of production to take tactical actions and decisions so that the Canadian Tourism Industry is benefitted. The explanation of the advantages of the system is provided below-

The administrator will be knowledgeable regarding the locations which were performing better when compares to other locations. Therefore, by utilizing this intelligence, the largest amount of benefits can be timely yielded. A major indicator of the performance for this advantage will be the amount of reports which can be provided with the necessary accuracy in comparison to the amount of reports which can be generated with the consequential accuracy
The subsequent advantage will be knowledge of all the risks and benefits.

Tactical Configuration
The major goals of the specific agency of the government is collection of intelligence, processing and utilizing it so that it can be used for promotion and marketing of Canada as a destination for tourists. Additionally, other goals consists of helping the neighboring tourist agencies and companies, offers them with critical intelligence which might assist them in serving consumers better, offers them with operational support and other objectives. Keeping this in consideration, the aggressive system of intelligence is focused on bridging the gap by providing superior quality intelligence like the dynamics of the market, competitions and other various activities. 
Improper Plan of the Project
The authority had taken into assumption numerous things which were not true, in every regard. This was clearly expressed in ways which were lacking either the proper experience in regards to the development of the system or the management of the project or they were too sluggish while the project was going on. A proper plan for the project is not made on the basis of unrealistic suppositions. The project needed realistic suppositions which are based on broad contextual research. The biggest mistake which was made by the main management was to initiate the whole project on the basis of various suppositions. The first and major supposition was the fact that only one model of aggressive system of information was present and that this model was sufficient for the entire project. The management was not knowledgeable regarding the numerous system of intelligence – which were being presently used – within the market have been personalized and modified in accordance with the requirements and wants of a specific company. Due to this misinterpretation or lack of comprehension, the authority made a decision to duplicate attributes of the present model within their patented and future aggressive system of information. Additionally, they believed that the present system can be transferred without any alterations being done. The plan of the project was the most critical phase of all the project phases. If anything which might get sabotaged during this phase, the whole project might be sabotaged and a digestive system could be produced which might be quite hazardous. This supposition was done at the very start and it proved to be quite successful, but it may have been a failure. This is due to the fact that a complicated system of information is unique to the company and an individual system which works for all companies is quite rare. 
Proper Plan of the Project
A precise instance for a proper planning of a project was the time when the authority took the decision to locate the proper standards of the industry and the finest practices. They precisely segmented the whole team of the project into two teams – the 1st team were the internal team who were accountable for creating the groundwork, interface and handling the critical functional components of the whole project. The 2nd team were the external team. This team was made up of consultants and specialists of the industry who were assumed to do the proper research so that the finest practices and standards of the industry. If a project has the real-world standards, standards of the industry and uses the finest practices, it will assist in production of a properly efficient and approved system. This will additionally assist in the production of systems that are powerful, simple to create and straightforward to integrate. On top of this, the project that utilizes the finest practices and benchmarks tend to be more complete and successful.

Free Membership to World’s Largest Sample Bank

To View this & another 50000+ free samples. Please put
your valid email id.

E-mail

Yes, alert me for offers and important updates

Submit 

Download Sample Now

Earn back the money you have spent on the downloaded sample by uploading a unique assignment/study material/research material you have. After we assess the authenticity of the uploaded content, you will get 100% money back in your wallet within 7 days.

UploadUnique Document

DocumentUnder Evaluation

Get Moneyinto Your Wallet

Total 11 pages

PAY 7 USD TO DOWNLOAD

*The content must not be available online or in our existing Database to qualify as
unique.

Cite This Work
To export a reference to this article please select a referencing stye below:

APA
MLA
Harvard
OSCOLA
Vancouver

My Assignment Help. (2020). Project Management. Retrieved from https://myassignmenthelp.com/free-samples/prjm6000-project-management/work-breakdown-structure.html.

“Project Management.” My Assignment Help, 2020, https://myassignmenthelp.com/free-samples/prjm6000-project-management/work-breakdown-structure.html.

My Assignment Help (2020) Project Management [Online]. Available from: https://myassignmenthelp.com/free-samples/prjm6000-project-management/work-breakdown-structure.html[Accessed 19 December 2021].

My Assignment Help. ‘Project Management’ (My Assignment Help, 2020) accessed 19 December 2021.

My Assignment Help. Project Management [Internet]. My Assignment Help. 2020 [cited 19 December 2021]. Available from: https://myassignmenthelp.com/free-samples/prjm6000-project-management/work-breakdown-structure.html.

×
.close{position: absolute;right: 5px;z-index: 999;opacity: 1;color: #ff8b00;}

×

Thank you for your interest
The respective sample has been mail to your register email id

×

CONGRATS!
$20 Credited
successfully in your wallet.
* $5 to be used on order value more than $50. Valid for
only 1
month.

Account created successfully!
We have sent login details on your registered email.

User:

Password:

MyAssignmenthelp.com is one of the noted service providers that deliver essay help. We provide tailored essay assistance to make sure that student gets online essay help exactly in the way they want it to be written. We at MyAssigemnthelp.com have built teams of consultants, who readily attend every query related to help me writing my essay. We provide essay writing help in forms of tips and steps in order o assist students with tough essay assignments.

Latest Project Management Samples

div#loaddata .card img {max-width: 100%;
}

SBM 1201 Project Scope, Time And Cost Management
Download :
0 | Pages :
12

Course Code: SBM1201
University: Asia Pacific International College

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answer:
Introduction
This project plan deals with the development of a fuel-efficient HHO Generator. The HHO fuel cells may appear to provide high fuel efficiency to the users. Nevertheless, there are a few confinements and focuses to be seen, as given beneath. This is to clear up that there is NO 100% substitution of petroleum derivative by including HHO cell. HHO gas is otherwise called Brown Gas, yet this is to illuminate that HHO gas is n…
Read
More
Tags:
Australia Footscray Management organisational behviour University of New South Wales Masters in Business Administration 

HS2061 Information Systems Project Management
Download :
0 | Pages :
9

Course Code: HS2061
University: Holmes Institute

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answer:
Case Overview:
The project owner of the Signed, sealed, delivered courier service is facing the problems of managing order of couriers in the synchronised manner. The project manager is incapable of managing central warehouse for the dispatching of products. The important information can be lost with the passage of time. The inventory management of the warehouse is the major concern for the owner of the company. He is looking forward …
Read
More

OPS 935 Project Management
Download :
0 | Pages :
11

Course Code: OPS935
University: University Of Wollongong

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answer:
Introduction
This essay explores the impacts of digital technologies on project management. It explores how adoption of digital technologies by companies for managing their project have affected their, project managers, human resource, business processes, timelines, deliverables, and practices  of risk management, people management and quality management.
Impact of Digital technologies on Project Management Practices
Digital te…
Read
More
Tags:
Australia Saint Kilda Management International Management University of New South Wales Masters in Business Administration 

ITC505 ICT Project Management
Download :
0 | Pages :
10

Course Code: ITC505
University: Charles Sturt University

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answers
Case Study- Social Media Research Center
Task-1: Project Charter
Project Objectives
The main objective of the project is to develop a web-based system within the organization “Social Media research Center”. It is analyzed that the Social Media research center wants to develop the web based system in order to connect people with the organization for promoting its research center. The web-based system that is developed conta…
Read
More
Tags:
Australia Alfredton Management IT Network Security  University of New South Wales Masters in Business Administration 

ITC505 ICT Project Management
Download :
0 | Pages :
7

Course Code: ITC505
University: Charles Sturt University

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answers
Part One- Project Name / Team / Description
Project Name:
RALS Solution
Team Name:
Consultants for RALS
Project Description:
RALS organizes show for the farmers and other related small business persons to display their latest technology equipment for betterment in the field of agriculture and crop production. The show has different types of stalls and other facilities for which many volunteers …
Read
More

Next

Need an essay written specifically to meet your requirements?

Choose skilled experts on your subject and get an original paper within your deadline

156 experts online

Your time is important. Let us write you an essay from scratch

Tips and Tricks from our Blog

11174 Introduction To Management

Free Samples 11174 Introduction To Management .cms-body-content table{width:100%!important;} #subhidecontent{ position: relative; overflow-x: auto; width: 100%;} 11174 Introduction

Read More »