PROJ6002 Project Planning And Budgeting
0 Download6 Pages / 1,355 Words
Course Code: PROJ6002
University: Laureate International Universities
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: United States
Question:
Successful completion of this assessment will result in achievement of the following subject learning outcomes:
Evaluate and apply a range of project scope, cost andtime management planning techniques and practicesto address the needs of complex project briefs, including global, paying particular attention to issues impacting project outcomes.
Present and justify budgetary and planning outcomes to a globally diverse range of stakeholders who represent competing interests in order to obtain agreement and commitment to action.
Apply quality management planning tools and techniques to achieve expected project outcomes.
In addition to your cost estimates and budget, include a to describe the processes, and tools and techniques you are using in your cost management plan, as well as justification of yourbudgetary plan. You can use the templates found in this module’s Learning Resources or a format of your own.
In Module 5, you will develop the quality management planning component of your Cost and Quality Management Plans. Refer to the learning resources and the template provided for guidance. The written portion of your quality management plan should consist. You can use the templates found in this module’s Learning Resources or a format of your own.
If you work in group, nominate a group leader within your group and this group leader will submit the group assessment on behalf of the group.
At the end of your assessment, you will individually, and anonymously, evaluate the contribution of your group members and yourself in this assessment, using the Group Contribution Form provided. rate yourself and then rate each of your fellow group members on their performance and contribution to this assessment. Individually submit the completed groupcontribution form on Blackboard.
Answer:
Cost Management Planning
The budget of the project is estimated as follows.
Human Resource Costs
Task Name
Duration
Predecessors
Resource Names
Cost
Bungalow Project
170 days
$274,800.00
Project Execution
170 days
$274,800.00
Clear Ground
2 wks
Labourers [600%]
$14,400.00
Lay Foundations
3 wks
2
Labourers [400%], Tradesmen [200%]
$25,200.00
Build Dwarf Walls
2 wks
3
Labourers [200%], Tradesmen [400%]
$19,200.00
Oversite Concrete
1 wk
3
Labourers [400%]
$4,800.00
Floor Joists
2 wks
4,5
Tradesmen [200%]
$7,200.00
Main Walls
5 wks
6
Labourers [200%], Tradesmen [400%]
$48,000.00
Door and Window Frames
3 wks
6
Tradesmen [200%]
$10,800.00
Ceiling Joists
2 wks
7,8
Tradesmen [200%]
$7,200.00
Roof Timbers
6 wks
7,8
Tradesmen [200%]
$21,600.00
Tiles
2 wks
9,10
Labourers [200%], Tradesmen [300%]
$15,600.00
Floorboards
3 wks
9,10
Tradesmen [200%]
$10,800.00
Ceiling Boards
2 wks
11,12
Tradesmen [200%]
$7,200.00
Skirtings
1 wk
11,12
Tradesmen [200%]
$3,600.00
Glazing
2 wks
13,14
Tradesmen [200%]
$7,200.00
Plastering
2 wks
15
Labourers, Tradesmen [300%]
$13,200.00
Electrics
3 wks
15
Tradesmen [200%]
$10,800.00
Plubming and Heating
4 wks
15
Labourers, Tradesmen [300%]
$26,400.00
Painting
3 wks
16,17,18
Tradesmen [400%]
$21,600.00
Material Costs
It has been found from the case study that the total material and plant costs as $33600.
Total Budget
From the calculations and estimation, the total budget of the project is found to be $ (274800+33600) = $308,400.
During the estimation of the costs of the project, several techniques have been used. For calculating the human resource costs in the project, bottom up estimation technique has been used with the assist of Microsoft Project Software (Heldman, 2018). In this estimation process, an activity timeline has been created based on the dependencies and durations of each individual task. After the completion of the timeline, human resources were added to each of the tasks (Harrison & Lock, 2017). In this project, there were two main human resources – labourers and tradesmen. In each of the tasks, different numbers of labourers and tradesmen are required. The numbers are denoted by a percentage e.g. in the task where 6 labourers are required, it is denoted by “labourers [600%]”. After allocation, the resource costs were set i.e. for labourers, the cost rate was $30 per hour and for tradesmen, the rate was $45 per hour. After setting these values, Microsoft Project, automatically calculates the expenditure in each activity as well as the total expenditure for the human resources.
For calculating the material costs, the unit rates of materials were determined for each of the tasks (Tonchia, 2018). The total material cost was calculated by multiplying the unit rate and the number of weeks they were being used in the project.
In addition to the development of the budget, it is also important to develop suitable cost management plan so that the project does not deviate from the determined resource usage and cost during execution (Wysocki, 2014). During the project, it should be ensured that right amount of human resources are deployed to work the specified number of days and the working hours (10 hours per day and 50 hours a week). Each work must be completed within the specified end date so that the next work starts at the right time.
Quality Management Planning
Quality Planning
Quality planning is defined as the formulation of a set of guidelines that define the required quality standard of the project. The quality standards depend on the type and nature of the project and vary widely. Again, just setting the quality standards is not sufficient for a project. It is also required to develop a suitable plan for implementation and monitoring of the quality management plan. The plan should include the steps that are required to meet the quality standards and suitable monitoring plan to ensure the suitable quality standards are being met during the project.
Like other projects, this project must also meet certain quality standards. These quality standards are to be set before the project work is started. In this particular project, the required quality standards include the following aspects.
Material Quality – Since this project involves the construction of a bungalow, a large amount of construction materials are utilized through the project (Kerzner & Kerzner, 2017). It is important that the materials are of the highest quality as low quality materials can cause problems like unfinished building, destruction of the building under moderate forces like strong winds or pressure and others.
Design Quality – In addition to the materials, it is also important to emphasize on the quality of design of the bungalow (Pheng, 2018). Poor quality designs often lead to severe complications during construction and may also cause accidents in the near future due to falling off of building parts and walls.
Quality of Work – Even though the material and design qualities are high, it is also important to provide high quality of work in the project so as to utilize the materials to develop the bungalow based on the actual design provided. For providing the best quality work, the workers are provided with sufficient amount of time (working 10 hours a day, 5 days a week). Poor quality of work will be penalized if identified during the course of the project or during the post project review.
Quality Assurance
Quality assurance is defined as the set of actions and metrics that are used to determine whether the quality standards of the project met. In this project, as discussed already, there are three main quality aspects – material, design and work. In order to assure the standard quality of the materials, reliable vendors are to be chosen who have good background of supply of good quality materials at the best possible price (Low & Ong, 2014). There are also several laboratory tests available to check the overall quality of the materials. For design quality, design engineer with established professional background must be selected. For the work quality, only skilled labour with previous work experiences in similar projects will have to chosen and recruited.
Quality Control
In addition to implementation and assurance of project quality, it is important to deploy quality control measures in order to ensure the project does not deviate from its quality standards. Penalties can be imposed for both vendors and workers in case they deliver poor quality materials or work (Nicholas & Steyn, 2017). Furthermore, in order to ensure the design of the bungalow is not poor, a pre-determined design of the building will be provided such that the engineer can work on it and develop a final design accordingly.
It is the duty of the project manager to emphasize and monitor on the quality of the project outcome although in some cases, a specialist quality control manager is recruited to monitor the quality of the project. Similarly, in this project, a specialist quality control manager will be appointed in order to supervise the quality of the project. The quality control manager will have a number of duties that include the following:
Check the quality of materials purchased for setting up the bungalow
Consult with the technical specialist to ensure the design of the bungalow is up to the required quality
Supervise the project work to ensure the quality of the project work is as per the requirements
References
Harrison, F., & Lock, D. (2017). Advanced project management: a structured approach. Routledge.
Heldman, K. (2018). PMP: project management professional exam study guide. John Wiley & Sons.
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Low, S. P., & Ong, J. (2014). Project Quality Management. Critical success factors for.
Nicholas, J. M., & Steyn, H. (2017). Project management for engineering, business and technology. Routledge.
Pheng, L. S. (2018). Project Quality Management. In Project Management for the Built Environment (pp. 113-125). Springer, Singapore.
Tonchia, S. (2018). Project Cost Management and Finance. In Industrial Project Management (pp. 153-170). Springer, Berlin, Heidelberg.
Wysocki, R. K. (2014). Effective project management: traditional, agile, extreme. John Wiley & Sons.
Free Membership to World’s Largest Sample Bank
To View this & another 50000+ free samples. Please put
your valid email id.
Yes, alert me for offers and important updates
Submit
Download Sample Now
Earn back the money you have spent on the downloaded sample by uploading a unique assignment/study material/research material you have. After we assess the authenticity of the uploaded content, you will get 100% money back in your wallet within 7 days.
UploadUnique Document
DocumentUnder Evaluation
Get Moneyinto Your Wallet
Total 6 pages
PAY 4 USD TO DOWNLOAD
*The content must not be available online or in our existing Database to qualify as
unique.
Cite This Work
To export a reference to this article please select a referencing stye below:
APA
MLA
Harvard
OSCOLA
Vancouver
My Assignment Help. (2021). Project Planning And Budgeting. Retrieved from https://myassignmenthelp.com/free-samples/proj6002-project-planning-and-budgeting/business-and-technology.html.
“Project Planning And Budgeting.” My Assignment Help, 2021, https://myassignmenthelp.com/free-samples/proj6002-project-planning-and-budgeting/business-and-technology.html.
My Assignment Help (2021) Project Planning And Budgeting [Online]. Available from: https://myassignmenthelp.com/free-samples/proj6002-project-planning-and-budgeting/business-and-technology.html[Accessed 18 December 2021].
My Assignment Help. ‘Project Planning And Budgeting’ (My Assignment Help, 2021)
My Assignment Help. Project Planning And Budgeting [Internet]. My Assignment Help. 2021 [cited 18 December 2021]. Available from: https://myassignmenthelp.com/free-samples/proj6002-project-planning-and-budgeting/business-and-technology.html.
×
.close{position: absolute;right: 5px;z-index: 999;opacity: 1;color: #ff8b00;}
×
Thank you for your interest
The respective sample has been mail to your register email id
×
CONGRATS!
$20 Credited
successfully in your wallet.
* $5 to be used on order value more than $50. Valid for
only 1
month.
Account created successfully!
We have sent login details on your registered email.
User:
Password:
Get a step closer to achieving higher grades with our urgent assignment help services. Our expert writer follows your university guidelines while writing, structuring and formatting your paper. We also assignment proofread and edit your assignment before sending it to you. We analyze the overall quality of your assignment to make sure it meets the highest academic standards. Thus, place your order with us without a second thought.
Latest Management Samples
div#loaddata .card img {max-width: 100%;
}
MPM755 Building Success In Commerce
Download :
0 | Pages :
9
Course Code: MPM755
University: Deakin University
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answers:
Introduction
The process of developing a successful business entity requires a multidimensional analysis of several factors that relate to the internal and external environment in commerce. The areas covered in this current unit are essential in transforming the business perspective regarding the key commerce factors such as ethics, technology, culture, entrepreneurship, leadership, culture, and globalization (Nzelibe, 1996; Barza, 2…
Read
More
SNM660 Evidence Based Practice
Download :
0 | Pages :
8
Course Code: SNM660
University: The University Of Sheffield
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: United Kingdom
Answers:
Critical reflection on the objective, design, methodology and outcome of the research undertaken Assessment-I
Smoking and tobacco addiction is one of the few among the most basic general restorative issues, particularly to developed nations such as the UK. It has been represented that among all risk segments smoking is the fourth driving purpose behind infections and other several ailments like asthma, breathing and problems in the l…
Read
More
Tags:
Australia Maidstone Management Business management with marketing University of New South Wales Masters in Business Administration
BSBHRM513 Manage Workforce Planning
Download :
0 | Pages :
20
Course Code: BSBHRM513
University: Tafe NSW
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answer:
Task 1
1.0 Data on staff turnover and demographics
That includes the staffing information of JKL industries for the fiscal year of 2014-15, it can be said that the company is having problems related to employee turnover. For the role of Senior Manager in Sydney, the organization needs 4 managers; however, one manager is exiting. It will make one empty position which might hurt the decision making process. On the other hand, In Brisba…
Read
More
MKT2031 Issues In Small Business And Entrepreneurship
Download :
0 | Pages :
5
Course Code: MKT2031
University: University Of Northampton
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: United Kingdom
Answer:
Entrepreneurial ventures
Entrepreneurship is the capacity and willingness to develop, manage, and put in order operations of any business venture with an intention to make profits despite the risks that may be involved in such venture. Small and large businesses have a vital role to play in the overall performance of the economy. It is, therefore, necessary to consider the difference between entrepreneurial ventures, individual, and c…
Read
More
Tags:
Turkey Istanbul Management University of Employee Masters in Business Administration
MN506 System Management
Download :
0 | Pages :
7
Course Code: MN506
University: Melbourne Institute Of Technology
MyAssignmentHelp.com is not sponsored or endorsed by this college or university
Country: Australia
Answer:
Introduction
An operating system (OS) is defined as a system software that is installed in the systems for the management of the hardware along with the other software resources. Every computer system and mobile device requires an operating system for functioning and execution of operations. There is a great use of mobile devices such as tablets and Smartphones that has increased. One of the widely used and implemented operating syste…