Rutledge Companion To Production And Operations

0 Download10 Pages / 2,272 Words

Question:
Discuss about the Rutledge Companion to Production and Operations.
 
Answer:

Project Scope Statement
Project management
Skillage IT has appointed project manager. The project manager will prepare the project plan and it will help the enterprise to implement a network architecture and an improved information system.
Business Needs:
The project is helpful for companies to oppose the declining trend as per as productivity is considered. Stating in other words, it has been affecting the revenue.
Project Description:
First of all installation and configuration of new networks infrastructures is to be done. This must include the plans of disaster recovery, isolating LOB or Lune of Business software and upgrading to recent Microsoft SQL server version. This has been possessing developed malware detection and improved virus. This has also included updated email communications software suite and the latest office application suite.
At the second stage, the SLA or Service Level Agreement has been needed to support new systems at the required level of the business. Lastly, the user training has been programmed for assuring the easy transaction towards the new systems.
 
Project requirements
Skillage IT will appoint a project manager. Skillage IT requires other project stakeholders that will significantly to the project and they are data entry officer, CEO, Sales Manager, manufacturing Supervisor and CFO. Skillage IT requires to implement a network architecture and the network architecture involves disaster recovery plans, upgrade to latest MS SQL server version. The network architecture will facilitate malware detection and malware mitigation. It also include implementation of SLA. Skillage IT must provide user training so that the employees can use the system smoothly and effectively.
Scheduling requirements
The project is scheduled to complete within five weeks by September 30. The total budget required for the project is $155,000.
Technical Specifications
The IT team or the technical team who will work for the project will require a web server, a management server, an app server, a SQL database server, and an email server.
SWOT analysis
Strength
The enhanced network architecture will enhance their productivity. The new network architecture will increase their market share. The order processing efficiency will definitely increase. Skillage IT’s yearly revenue will increase as well.
Weakness
Skillage IT will have to spend a lot of money to install the network architecture. The employees of the enterprise are not used to the technology and they will suffer. Their data will be handled and maintained by the IT professionals so there are chances of data breaches.
Opportunity
The latest adopted network architecture will give them the competitive edge. They can stay ahead of their competitors. Thus, they can see a hike in the revenues.
Threats
The competitors can play tricks, they can hack their system and database. The hackers can steal all the important data of the employees and the clients they serve. They fail to adopt the advanced network architecture and can be at trouble
 
User documentation
The project manager must documented all the issues and the risks they are facing. He must prepare a plan which will consist of all the activities that need to be carried out.
Pilot
The project sponsor wants to develop a beta version of the network architecture and the improved information system. They want to check whether the system will fetch them real benefits or not. They will test how does the new network will occur.
Usability testing
Every employees will be asked to review the information system architecture they recently adopt. They will use the software system and will share feedback how they feel. They will also suggest how the software can be modified.
Automation of administrative tasks
The new information system will be capable of evaluating the financial report automatically. There are less chance of errors. Skillage IT can get fast and effective results. The enterprise can be attacked by the hackers and the enterprise’s security and privacy can be at stake. The new information system will come with some advanced features which will ensure security and privacy of the company.
Ongoing maintenance support
The IT team who will work for the software will work on the maintenance of the information system and the software. The IT will update or upgrade the system. Skillage IT will always get updated service all the time, the new updated system will give them the desired business edge. The new information system and the network architecture will give them the security against the malware attack.
 
Hand-over documentation
The project manager will prepare the plan. The plan will contain the list of activities that will be undertaken. The plan will also contain the project resources list and the project budget list. All those handy details will be documented in the report and will be handed over to the sponsor. The sponsor will review the documentation and will approve the plan. The sponsor will provide the funding and the whole team can start working on the project thereafter.
Project Plan

Task Name

Duration

Start

Finish

Predecessors

Skillage IT Project Plan Enterprise Resource Planning Implementation Project Kick Off

90 days

Mon 04/06/18

Fri 05/10/18

 

   Enterprise Resource Planning

23 days

Mon 04/06/18

Wed 04/07/18

 

      Designing Project Blueprint

12 days

Mon 04/06/18

Tue 19/06/18

 

         Point Of Sale (POS) Integration

4 days

Mon 04/06/18

Thu 07/06/18

 

         Finalising IDOCs and the fields hat ae needed

8 days

Fri 08/06/18

Tue 19/06/18

4

      Project Realisation

11 days

Wed 20/06/18

Wed 04/07/18

 

         Implementing and Configuring Standard IDOCs

4 days

Wed 20/06/18

Mon 25/06/18

5

         Enhance and Developing IDOCs

7 days

Tue 26/06/18

Wed 04/07/18

7

   WMS

17 days

Fri 08/06/18

Mon 02/07/18

 

      Designing Project Blueprint

5 days

Fri 08/06/18

Thu 14/06/18

4

      Project Realisation

5 days

Tue 26/06/18

Mon 02/07/18

7

   POS Design

17 days

Fri 15/06/18

Mon 09/07/18

 

      Preliminary Software Specifications Review

4 days

Fri 15/06/18

Wed 20/06/18

10

      Developing Functional Specifications

5 days

Thu 21/06/18

Wed 27/06/18

13

      Developing POS Prototype as per Project Functional Specifications

6 days

Fri 15/06/18

Fri 22/06/18

10

      Detailed Review of POS Project Functional Specifications

6 days

Fri 15/06/18

Fri 22/06/18

10

      Incorporate Feedback into Functional POS Project Functional Specifications

7 days

Mon 25/06/18

Tue 03/07/18

16

      Obtaining Approval for further Proceedings

4 days

Wed 04/07/18

Mon 09/07/18

17

   POS Development

30 days

Mon 25/06/18

Fri 03/08/18

 

      Assigning Software Development Staff

10 days

Mon 25/06/18

Fri 06/07/18

13,16

      Coding

20 days

Mon 09/07/18

Fri 03/08/18

20

   POS Project Integration

38 days

Mon 06/08/18

Wed 26/09/18

 

      Solution Architecture

5 days

Mon 06/08/18

Fri 10/08/18

21

      Developing WSO2 SAP Adapter

7 days

Mon 13/08/18

Tue 21/08/18

23

      Deploying Architecture

7 days

Wed 22/08/18

Thu 30/08/18

24

      Project Integration Use Cases

6 days

Fri 31/08/18

Fri 07/09/18

25

      Project Field Mapping

4 days

Mon 10/09/18

Thu 13/09/18

26

      Providing Training

3 days

Fri 14/09/18

Tue 18/09/18

27

      Developing Transformation Scripts

3 days

Wed 19/09/18

Fri 21/09/18

28

      QA Testing

3 days

Mon 24/09/18

Wed 26/09/18

29

   Enterprise Resource Planning Software Going Live

7 days

Thu 27/09/18

Fri 05/10/18

 

      Preparing Golive

4 days

Thu 27/09/18

Tue 02/10/18

30

      Golive

3 days

Wed 03/10/18

Fri 05/10/18

32

Quality Management Plan
The primary objective of the quality planning is to ensure the project is undergoing successfully. Skillage IT can test whether the project will fetch them real benefits or not. Skillage IT can suggest changes if they want to. Therefore, with the aid of quality checking they can assure that they will get the best quality software to use.
Basic principles
To assure that the software that have been planned to develop meet the criteria.

Regular meetings must be conducted to assure that the design, development of the software met the quality
All the stakeholders of the project must work in a group and must accomplish the project

Quality Standards

The project manager should manage the quality of the project and must not compromise with the quality
The project manager and his team must solve all the errors on time

 
Quality Assurance

The project manager must assure quality to meet the quality standards
The project quality will help to know whether the project is on right track or not

Quality Control

Quality control defines that the all the deliverables of the project in time
The project components are maintained properly to keep the flow of the project activities

Change Management Plan
The changes made within the project must be documented well. It will help the project manager and the stakeholders to acknowledge the issues raised. It will also let them know how to solve the issues raised. The stakeholders can commit errors and mistakes. It will help them to stay alert in future. The project sponsor may ask for any changes. Those changes must be documented and the project manager must take the responsibility to make the amendments. In all the above cases, the project manager must modify the project plan and must apply the appropriate changes. The change management plan will help to carry out the project effectively and according to the demands of the clients or sponsor.
Stakeholder Meeting
Data Entry Officer
For the computers of initial days the entering of orders has been much effective. However, management was not helpful. They all needed to do that complain regarding how slow the performance has been.
Manufacturer Supervisor:
The people working as fast as they could has been always waiting for the tasks to appear over the screen of job list.  However, at many times the screens has possessed no tasks in that at all. Every sufficient materials people were present and they have not been only the orders to fill.
CEO:
It is also seen that the project has been kept waiting bit longer. This is to get the daily and weekly reports of summary. However, commonly the system has not been much bad. It is also known that those supervisors have been complaining much regarding the slowness. Further, they thought that this has been the reason of various backlog within the process of order. Moreover, it is also known that this has been one of the possible factors. However, there has been further investigation needed at various areas of the practices. This has been to assure that they are optimized from before. Thus, solutions are needed and not the complaints. Here, the only one seeming to be providing the solution has been the different skillage I.T. It is also thought that they are able to get back to the track having the least amount of loss. Besides, currently CFP has been stating that the system has been outdated. This has needed to be written off totally over the tax. Hence the upgrade is needed to be approved.
Sales Manager:
Here, the people have been selling plenty over the road. They are found to be working very hardly there. Next, many excuses has been fed from manufacturing regarding various orders not coming in. Further, there have been problems that have been getting the list of the specific system. This has been taking a little time. However the computers have been holding much information.
CFO
It is also known from that from the individual view-point, that the system has been unacceptably slow. It has been taking about 2 hours to create the activity statement for every month for the clients. These clients have been taking about less than 15 minutes. Currently, the system has been 5 years old and has been stating the CEO for past 2 years to update. Further, there must be various tax benefits that are needed to be done. It is also known that it can be afforded. However, the numbers are done and the it is quite unaffordable to do that. As the number gets decreased, there should not the existence of the company. Thus, it has been good news that people has been moving towards Skillage I.T regarding the help of up-gradation.
 
References
Browning, T.R., 2017. Project Design and Management. In The Routledge Companion to Production and Operations Management (pp. 214-233). Routledge.
Carlton, D., 2017. Competence versus Confidence in IT Project Leadership and its Impact on Project Outcomes. The Journal of Modern Project Management, 5(1).
de Guimarães, J.C.F., Severo, E.A. and Vieira, P.S., 2017. Cleaner production, project management and strategic drivers: an empirical study. Journal of cleaner production, 141, pp.881-890.
Godwin, L., Newman, J.J. and Thomas, W.J., 2017. Herding Cats: Project Management for Digital Scholarship.
Jabbarzadeh, A., 2018. Application of the AHP and TOPSIS in project management. Journal of Project Management, 3(2), pp.125-130.
Jabbarzadeh, A., 2018. Application of the AHP and TOPSIS in project management. Journal of Project Management, 3(2), pp.125-130.
Kerzner, H. and Saladis, F.P., 2017. Project management workbook and PMP/CAPM exam study guide. John Wiley & Sons.
Kuchta, D. and Ptaszy?ska, E., 2017, July. Fuzzy based risk register for construction project risk assessment. In AIP Conference Proceedings (Vol. 1863, No. 1, p. 230006). AIP Publishing.
Nonino, F., 2018. Project Selection Frameworks and Methodologies for Reducing Risks in Project Portfolio Management. In Global Business Expansion: Concepts, Methodologies, Tools, and Applications (pp. 547-566). IGI Global.
Reed, A.H. and Angolia, M., 2018. Risk Management Usage and Impact on Information Systems Project Success. International Journal of Information Technology Project Management (IJITPM), 9(2), pp.1-19.
Shokoohyar, S., Qi, A. and Katok, E., 2017. Project Management under Risk-Sharing Contracts.
Turner, R., 2017. Farsighted project contract management. In Contracting for Project Management (pp. 33-57). Routledge.

Free Membership to World’s Largest Sample Bank

To View this & another 50000+ free samples. Please put
your valid email id.

E-mail

Yes, alert me for offers and important updates

Submit 

Download Sample Now

Earn back the money you have spent on the downloaded sample by uploading a unique assignment/study material/research material you have. After we assess the authenticity of the uploaded content, you will get 100% money back in your wallet within 7 days.

UploadUnique Document

DocumentUnder Evaluation

Get Moneyinto Your Wallet

Total 10 pages

PAY 6 USD TO DOWNLOAD

*The content must not be available online or in our existing Database to qualify as
unique.

Cite This Work
To export a reference to this article please select a referencing stye below:

APA
MLA
Harvard
OSCOLA
Vancouver

My Assignment Help. (2019). Rutledge Companion To Production And Operations. Retrieved from https://myassignmenthelp.com/free-samples/rutledge-companion-to-production-and-operations.

“Rutledge Companion To Production And Operations.” My Assignment Help, 2019, https://myassignmenthelp.com/free-samples/rutledge-companion-to-production-and-operations.

My Assignment Help (2019) Rutledge Companion To Production And Operations [Online]. Available from: https://myassignmenthelp.com/free-samples/rutledge-companion-to-production-and-operations[Accessed 19 December 2021].

My Assignment Help. ‘Rutledge Companion To Production And Operations’ (My Assignment Help, 2019) accessed 19 December 2021.

My Assignment Help. Rutledge Companion To Production And Operations [Internet]. My Assignment Help. 2019 [cited 19 December 2021]. Available from: https://myassignmenthelp.com/free-samples/rutledge-companion-to-production-and-operations.

×
.close{position: absolute;right: 5px;z-index: 999;opacity: 1;color: #ff8b00;}

×

Thank you for your interest
The respective sample has been mail to your register email id

×

CONGRATS!
$20 Credited
successfully in your wallet.
* $5 to be used on order value more than $50. Valid for
only 1
month.

Account created successfully!
We have sent login details on your registered email.

User:

Password:

Myassignment help has a long experience of over 10+ years in providing quality solutions for nusring assignments, management assignments, law assignments, finance assignments, programming language assignments, literature essay, maths assignments, statistics assignments and hundred more subjects. We delivery quality assignments for high school to K-12 levels. All our experts have good years of experience teaching in reputed institutes and hence know the areas where students make most mistakes in assignments and works. They help to get to quality assignments in no time. Connect with us if you want a boost in your grades and academic reputation.

Latest Project Management Samples

div#loaddata .card img {max-width: 100%;
}

SBM 1201 Project Scope, Time And Cost Management
Download :
0 | Pages :
12

Course Code: SBM1201
University: Asia Pacific International College

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answer:
Introduction
This project plan deals with the development of a fuel-efficient HHO Generator. The HHO fuel cells may appear to provide high fuel efficiency to the users. Nevertheless, there are a few confinements and focuses to be seen, as given beneath. This is to clear up that there is NO 100% substitution of petroleum derivative by including HHO cell. HHO gas is otherwise called Brown Gas, yet this is to illuminate that HHO gas is n…
Read
More
Tags:
Australia Footscray Management organisational behviour University of New South Wales Masters in Business Administration 

HS2061 Information Systems Project Management
Download :
0 | Pages :
9

Course Code: HS2061
University: Holmes Institute

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answer:
Case Overview:
The project owner of the Signed, sealed, delivered courier service is facing the problems of managing order of couriers in the synchronised manner. The project manager is incapable of managing central warehouse for the dispatching of products. The important information can be lost with the passage of time. The inventory management of the warehouse is the major concern for the owner of the company. He is looking forward …
Read
More

OPS 935 Project Management
Download :
0 | Pages :
11

Course Code: OPS935
University: University Of Wollongong

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answer:
Introduction
This essay explores the impacts of digital technologies on project management. It explores how adoption of digital technologies by companies for managing their project have affected their, project managers, human resource, business processes, timelines, deliverables, and practices  of risk management, people management and quality management.
Impact of Digital technologies on Project Management Practices
Digital te…
Read
More
Tags:
Australia Saint Kilda Management International Management University of New South Wales Masters in Business Administration 

ITC505 ICT Project Management
Download :
0 | Pages :
10

Course Code: ITC505
University: Charles Sturt University

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answers
Case Study- Social Media Research Center
Task-1: Project Charter
Project Objectives
The main objective of the project is to develop a web-based system within the organization “Social Media research Center”. It is analyzed that the Social Media research center wants to develop the web based system in order to connect people with the organization for promoting its research center. The web-based system that is developed conta…
Read
More
Tags:
Australia Alfredton Management IT Network Security  University of New South Wales Masters in Business Administration 

ITC505 ICT Project Management
Download :
0 | Pages :
7

Course Code: ITC505
University: Charles Sturt University

MyAssignmentHelp.com is not sponsored or endorsed by this college or university

Country: Australia

Answers
Part One- Project Name / Team / Description
Project Name:
RALS Solution
Team Name:
Consultants for RALS
Project Description:
RALS organizes show for the farmers and other related small business persons to display their latest technology equipment for betterment in the field of agriculture and crop production. The show has different types of stalls and other facilities for which many volunteers …
Read
More

Next

Need an essay written specifically to meet your requirements?

Choose skilled experts on your subject and get an original paper within your deadline

156 experts online

Your time is important. Let us write you an essay from scratch